Connect with us

Concrete

Larger Gear Drives for Larger Vertical Roller Mills

Published

on

Shares

The global trend towards single-mill cement plants is unquestionable. With civil construction cost savings, higher throughput and lowered maintenance costs, the use of single large VRMs for cement and raw grinding is the optimal choice. The sheer size requires powerful, large-scale drive gear systems.

As operators look to increase equipment capacity, the key is to ensure long-term reliability that guarantees continuous kiln operation. There are several challenges. Whereas machine design is often the limiting factor for large ball mills and roller presses, it is the drive systems that require focus in vertical roller mills (VRMs). Placing silos before and after the kiln can reduce short interruptions in the milling processes, but long standstills caused by unexpected mechanical failures are difficult to avoid.
Reliability of VRMs depends on the drive system, the grinding system and the operational behaviour of the mill. To help lower initial cost investments aimed at preventing downtime, particular attention must be devoted to the drive system and critical grinding components, such as roller and table.
The rollers and the grinding table are exposed to high abrasive wear depending on the feed material properties, the product fineness, and the combination of rollers and table materials. At regular intervals, therefore, the table and roller wear liners must be exchanged or repaired by surface-layer welding.
Without the natural redundancy of an approach with two mills in parallel, flexibility is key. The OK™ mill has individual roller arrangements with swing-out mechanisms to facilitate maintenance or replacement of the rollers. In the case of mechanical failure, the mill can easily operate with fewer rollers. The only requirement is that the remaining rollers are uniformly distributed around the table circumference and that they are all the same size. Production can then continue, albeit at a reduced rate, to minimise operational disruption.
Impressively, the OK mill can achieve 60 to 70 per cent of nominal output with half of its rollers out of service.
“The design power of such large VRMs depends on the grindability of material. Raw mill applications require up to approximately 9,000kW, with slag and cement grinding needing up to 14,000kW. Regardless of the type, these VRMs’ drive systems need to deliver reliable torque transmission.”

Drive Systems
Conventional drive systems typically consist of a switch-gear to connect the drive motor to the electrical grid. The transformer converts the grid voltage to the motor design voltage and protects the equipment from voltage peaks. A rotor starting device and a highly flexible coupling connects the motor and gearbox.
Yet there are limits to such a system. The bevel stage in the gearbox, primarily used to redirect the rotating movement from the horizontal motor shaft into the vertical direction of the grinding table, limits power capability. For design power of up to approximately 9,000kW, this can be overcome by increasing the gear ratio in the following planetary stage, which keeps the bevel stage size within feasible dimensions. However, this does not fulfil mill requirements and a further increase in drive power requires larger dimensions, especially the diameter of the bevel wheels. This decreases the overall reliability of the drive system. Conventional gear units cannot operate VRMs with higher design power. The drive system for these applications is based on two main principles: partition of power to several drive units and elimination of the weakest element in the drive train.

Partitioning Drive Power
By separating the drive power, large VRMs can provide the required torque with multiple motors. The motors are designed either as individual drive assemblies containing their own motors, couplings and gearboxes or as small vertical motors, integrated partially into the gear casing and connected to a central toothed wheel inside the gearbox.


As a result, power distribution bevel stages are considerably smaller or, in vertical motors, completely eliminated. The drive systems are built so that they can operate with fewer motors in the case of malfunction or maintenance. This means that operation at a reduced production rate can still occur, minimising production losses during scheduled maintenance. This has the effect, however, of increasing complexity of the power distribution between the main switchgear and the motors and also increasing maintenance effort.
In addition to the main switch gear, each motor needs a separate circuit breaker and a motor control cabinet to allow operation with a reduced number of motors. In order to provide uniform torque to the common central wheels, the load and speed of each motor is synchronised by either a variable frequency converter or a highly flexible or fluid coupling. During start-up, when the mill is running at full speed with fewer motors, the timing of the connecting additional motors is essential to prevent torque peaks.

Elimination of Weakest Element
The integrated drive system in the VRM replaces the bevel stage with one vertical motor built into the gear casing. While this does not affect the power distribution, compared with the conventional system, the overall dimensions of the motor must be adapted to the available space for a bevel stage in a conventional gearbox. Otherwise, costly design changes of the mill support and foundation are required.
“The challenge with the integrated system is developing an electrical motor with the highest possible power density.”
A design study comparing different motor types showed that meeting space requirements is only possible with a synchronous motor with permanent magnet excitation and a single coil stator. To operate such type motors, variable frequency converters are necessary. Integration also makes special cooling necessary because air-cooled motors do not reach the required power density.
For example, the motor in FLSmidth MAAG® Gear’s CEM Drive includes special cooling tubes in the stator arrangement. This provides optimal flow of the cooling media and enables the use of gear lubrication oil in the motor cooling circuit.

Smart Design
Despite the challenges associated with large VRMs, there are important benefits to having an integrated drive system embedded in the design. Power distribution, such as that in a partial-load system, is not required and the number of rotating parts is kept to a minimum. The variable frequency converter allows the operator to adjust the mill table speed without time delay and to influence the grinding process individually when grinding different products in the same mill or as feed quality changes over time.
Large VRMs can help to meet the demands of a single-mill cement line by addressing the typical challenges of grinding systems. In doing so, FLSmidth’s OK mill can provide a solution for most single-mill cement lines wanting to increase their throughput.

Concrete

UltraTech Cement FY26 PAT Crosses Rs 80 bn

Company reports record sales, profit and 200 MTPA capacity milestone

Published

on

By

Shares



UltraTech Cement reported record financial performance for Q4 and FY26, supported by strong volumes, higher profitability and improved cost efficiency. Consolidated net sales for Q4 FY26 rose 12 per cent year-on-year to Rs 254.67 billion, while PBIDT increased 20 per cent to Rs 56.88 billion. PAT, excluding exceptional items, grew 21 per cent to Rs 30.11 billion.

For FY26, consolidated net sales stood at Rs 873.84 billion, up 17 per cent from Rs 749.36 billion in FY25. PBIDT rose 32 per cent to Rs 175.98 billion, while PAT increased 36 per cent to Rs 83.05 billion, crossing the Rs 80 billion mark for the first time.

India grey cement volumes reached 42.41 million tonnes in Q4 FY26, up 9.3 per cent year-on-year, with capacity utilisation at 89 per cent. Full-year India grey cement volumes stood at 145 million tonnes. Energy costs declined 3 per cent, aided by a higher green power mix of 43 per cent in Q4.

The company’s domestic grey cement capacity has crossed 200 MTPA, reaching 200.1 MTPA, while global capacity stands at 205.5 MTPA. UltraTech also recommended a special dividend of Rs 2.40 billion per share value basis equivalent to Rs 240.

Continue Reading

Concrete

Towards Mega Batching

Optimised batching can drive overall efficiencies in large projects.

Published

on

By

Shares



India’s pace of infrastructure development is pushing the construction sector to work at a significantly higher scale than previously. Tight deadlines necessitate eliminating concreting delays, especially in large and mega projects, which, in turn, imply installing the right batching plant and ensuring batching is efficient. CW explores these steps as well as the gaps in India’s batching plant market.

Choose well

Large-scale infrastructure and building projects typically involve concrete consumption exceeding 30,000-50,000 cum per annum or demand continuous, high-volume pours within compressed timelines, according to Rahul R Wadhai, DGM – Quality, Tata Projects.

Considering the daily need for concrete, “large-scale concreting involves pouring more than 1,000–2,000 cum per day while mega projects involve more than 3,000 cum per day,” says Satish R Vachhani, Advanced Concrete & Construction Consultant…

To read the full article Click Here

Continue Reading

Concrete

Andhra Offers Discom Licences To Private Firms Outside Power Sector

Policy allows firms over 300 MW to seek distribution licences

Published

on

By

Shares



The Andhra Pradesh government will allow private firms that require more than 300 megawatt (MW) of power to apply for distribution licences, making the state the first to extend such licences beyond the power sector. The policy targets information technology, pharmaceuticals, steel and data centres and aims to reduce reliance on state utilities as demand rises for artificial intelligence infrastructure.

Approved applicants will be able to procure electricity directly from generators through power purchase agreements, a change officials said will create more competitive tariffs and reduce supply risk. Licence holders will use the Andhra Pradesh Transmission Company (APTRANSCO) network on payment of charges and will not need a separate distribution network initially.

Licences will be granted under the Electricity Act, 2003 framework, with the Central and State electricity regulators retaining authority over terms and approvals. The recent Electricity (Amendment) Bill, 2025 sought to lower entry barriers, enable network sharing and encourage competition, while the state commission will set floor and ceiling tariffs where multiple discoms operate.

Industry players and original equipment manufacturers welcomed the policy, saying competitive supply is vital for large data centre investments. Major projects and partnerships such as those involving Adani and Google, Brookfield and Reliance, and Meta and Sify Technologies are expected to benefit as capacity expands in the state.

Analysts noted India’s data centre capacity is forecast to reach 10 gigawatts (GW) by 2030 and cited International Energy Agency estimates that global data centre electricity consumption could approach 945 terawatt hours by the same year. A one GW data centre needs an equivalent power allocation and one point five times the water, which authorities equated to 150 billion litres (150 bn litres).

Advisers warned that distribution licences will require close regulation and monitoring to prevent misuse and to ensure tariffs and supply obligations are met. Officials said the policy aims to balance investor requirements with regulatory oversight and could serve as a model for other states.

Continue Reading

Video Thumbnail

    SIGN-UP FOR OUR GENERAL NEWSLETTER


    Trending News

    SUBSCRIBE TO THE NEWSLETTER

     

    Don't miss out on valuable insights and opportunities to connect with like minded professionals.

     


      This will close in 0 seconds