Connect with us

Concrete

Larger Gear Drives for Larger Vertical Roller Mills

Published

on

Shares

The global trend towards single-mill cement plants is unquestionable. With civil construction cost savings, higher throughput and lowered maintenance costs, the use of single large VRMs for cement and raw grinding is the optimal choice. The sheer size requires powerful, large-scale drive gear systems.

As operators look to increase equipment capacity, the key is to ensure long-term reliability that guarantees continuous kiln operation. There are several challenges. Whereas machine design is often the limiting factor for large ball mills and roller presses, it is the drive systems that require focus in vertical roller mills (VRMs). Placing silos before and after the kiln can reduce short interruptions in the milling processes, but long standstills caused by unexpected mechanical failures are difficult to avoid.
Reliability of VRMs depends on the drive system, the grinding system and the operational behaviour of the mill. To help lower initial cost investments aimed at preventing downtime, particular attention must be devoted to the drive system and critical grinding components, such as roller and table.
The rollers and the grinding table are exposed to high abrasive wear depending on the feed material properties, the product fineness, and the combination of rollers and table materials. At regular intervals, therefore, the table and roller wear liners must be exchanged or repaired by surface-layer welding.
Without the natural redundancy of an approach with two mills in parallel, flexibility is key. The OK™ mill has individual roller arrangements with swing-out mechanisms to facilitate maintenance or replacement of the rollers. In the case of mechanical failure, the mill can easily operate with fewer rollers. The only requirement is that the remaining rollers are uniformly distributed around the table circumference and that they are all the same size. Production can then continue, albeit at a reduced rate, to minimise operational disruption.
Impressively, the OK mill can achieve 60 to 70 per cent of nominal output with half of its rollers out of service.
“The design power of such large VRMs depends on the grindability of material. Raw mill applications require up to approximately 9,000kW, with slag and cement grinding needing up to 14,000kW. Regardless of the type, these VRMs’ drive systems need to deliver reliable torque transmission.”

Drive Systems
Conventional drive systems typically consist of a switch-gear to connect the drive motor to the electrical grid. The transformer converts the grid voltage to the motor design voltage and protects the equipment from voltage peaks. A rotor starting device and a highly flexible coupling connects the motor and gearbox.
Yet there are limits to such a system. The bevel stage in the gearbox, primarily used to redirect the rotating movement from the horizontal motor shaft into the vertical direction of the grinding table, limits power capability. For design power of up to approximately 9,000kW, this can be overcome by increasing the gear ratio in the following planetary stage, which keeps the bevel stage size within feasible dimensions. However, this does not fulfil mill requirements and a further increase in drive power requires larger dimensions, especially the diameter of the bevel wheels. This decreases the overall reliability of the drive system. Conventional gear units cannot operate VRMs with higher design power. The drive system for these applications is based on two main principles: partition of power to several drive units and elimination of the weakest element in the drive train.

Partitioning Drive Power
By separating the drive power, large VRMs can provide the required torque with multiple motors. The motors are designed either as individual drive assemblies containing their own motors, couplings and gearboxes or as small vertical motors, integrated partially into the gear casing and connected to a central toothed wheel inside the gearbox.


As a result, power distribution bevel stages are considerably smaller or, in vertical motors, completely eliminated. The drive systems are built so that they can operate with fewer motors in the case of malfunction or maintenance. This means that operation at a reduced production rate can still occur, minimising production losses during scheduled maintenance. This has the effect, however, of increasing complexity of the power distribution between the main switchgear and the motors and also increasing maintenance effort.
In addition to the main switch gear, each motor needs a separate circuit breaker and a motor control cabinet to allow operation with a reduced number of motors. In order to provide uniform torque to the common central wheels, the load and speed of each motor is synchronised by either a variable frequency converter or a highly flexible or fluid coupling. During start-up, when the mill is running at full speed with fewer motors, the timing of the connecting additional motors is essential to prevent torque peaks.

Elimination of Weakest Element
The integrated drive system in the VRM replaces the bevel stage with one vertical motor built into the gear casing. While this does not affect the power distribution, compared with the conventional system, the overall dimensions of the motor must be adapted to the available space for a bevel stage in a conventional gearbox. Otherwise, costly design changes of the mill support and foundation are required.
“The challenge with the integrated system is developing an electrical motor with the highest possible power density.”
A design study comparing different motor types showed that meeting space requirements is only possible with a synchronous motor with permanent magnet excitation and a single coil stator. To operate such type motors, variable frequency converters are necessary. Integration also makes special cooling necessary because air-cooled motors do not reach the required power density.
For example, the motor in FLSmidth MAAG® Gear’s CEM Drive includes special cooling tubes in the stator arrangement. This provides optimal flow of the cooling media and enables the use of gear lubrication oil in the motor cooling circuit.

Smart Design
Despite the challenges associated with large VRMs, there are important benefits to having an integrated drive system embedded in the design. Power distribution, such as that in a partial-load system, is not required and the number of rotating parts is kept to a minimum. The variable frequency converter allows the operator to adjust the mill table speed without time delay and to influence the grinding process individually when grinding different products in the same mill or as feed quality changes over time.
Large VRMs can help to meet the demands of a single-mill cement line by addressing the typical challenges of grinding systems. In doing so, FLSmidth’s OK mill can provide a solution for most single-mill cement lines wanting to increase their throughput.

Concrete

Cement Firms to Invest Rs. 130 bn in Green Energy by FY28

Cement companies plan to expand clean energy capacity to 6 GW by FY28

Published

on

By

Shares



India’s major cement companies are set to raise their clean energy capacity to 6 GW by March 2028 from around 4 GW at the end of March 2026, according to ratings agency ICRA. The planned expansion is expected to involve investments of Rs. 130 bn over the next two years.

The additional capacity could generate annual savings of Rs. 62 bn to Rs. 67 bn, resulting in an estimated payback period of 1.8 to 2.2 years. Cement is an emission-intensive industry, and leading producers have established net-zero roadmaps covering the next 15 to 20 years.

The calcination process accounts for 57 to 60 per cent of the sector’s total emissions, while fuel combustion contributes 27 to 30 per cent and electricity consumption accounts for 10 to 13 per cent. ICRA said the figures highlighted the need for a broad decarbonisation strategy involving green power, blended cement, alternative fuels and improvements in clinker efficiency.

Green energy is considered one of the most commercially attractive decarbonisation options because it can reduce emissions while lowering operating costs. Every 5 per cent increase in green power replacement can reduce power and fuel costs by Rs. 15 to Rs. 16 per tonne. A 25 per cent replacement level could therefore save Rs. 75 to Rs. 80 per tonne and expand operating margins by 140 to 160 basis points.

Cement producers are also assessing carbon capture, utilisation and storage, although high implementation costs, energy requirements and limited transport and storage infrastructure are expected to slow commercial adoption. The government has proposed Rs. 200 bn over five years to support deployment across key sectors. Meanwhile, companies are targeting thermal substitution rates of 10 to 15 per cent over the next three to five years, compared with the current industry level of around 6 per cent.

Continue Reading

Concrete

Centre Defers Clearance for Limestone Mine Near Bustard Habitat

Panel seeks revised mining plan and safeguards for pipelines and wildlife

Published

on

By

Shares



The Centre has deferred environmental clearance for a proposed limestone mine near a Great Indian Bustard habitat in Ramgarh, Rajasthan’s Jaisalmer district. The critically endangered species has an estimated wild population of about 130 in India.

Continue Reading

Concrete

Telangana to Supply Subsidised Cement for Indiramma Houses

Poor families allotted Indiramma houses to receive cement at Rs. 230 per bag

Published

on

By

Shares



The Telangana government will supply cement at a subsidised price of Rs. 230 per 50-kg bag to poor and low-income families allotted Indiramma houses. The prevailing market price is between Rs. 310 and Rs. 320 per bag, the Assembly was informed on Thursday.

Continue Reading

Video Thumbnail

    SIGN-UP FOR OUR GENERAL NEWSLETTER

    Trending News

    SUBSCRIBE TO THE NEWSLETTER

     

    Don't miss out on valuable insights and opportunities to connect with like minded professionals.

     


      This will close in 0 seconds