Connect with us

Projects

Portland Cement Association´s centennial anniversary

Published

on

2016 marks the centennial annversary of the Portland Cement Association (PCA), the nation?s leading advocate for America’s cement manufacturers. Widely recognised as an authority on the technology, economics, and applications of cement and concrete, the PCA is a vocal advocate for sustainability, economic growth, sound infrastructure investment and overall innovation and excellence in construction.

In celebrating its 100th year, PCA will be hosting several events throughout the year, including:

February 2-5, 2016: World of Concrete, Las Vegas, Nevada. The official launch of Centennial Celebration.

March 14-15, 2016: PCA Spring Congress, Chicago. Main centennial celebration for PCA membership.

May 24-25, 2016: 2016 DC Fly-In, Washington, D.C., July 18, 2016: Open house at PCA Skokie headquarters and CTLGroup To find out more, please contact Erik Rancatore at (847) 972-9138 or visit www.cement.org.

Image Source: Google Images

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Projects

Adani Group to invest Rs 55,000 cr in Gujarat projects, including cement plant

Published

on

By

Billionaire Gautam Adani announced over Rs 55,000 crore investment in next five years in a clutch of projects in Gujarat including the world’s largest solar park, a copper plant, a cement unit, and a lithium battery manufacturing complex, envisaging direct employment to 50,000 people.

Adani Group, which operates Mundra port in the state, announced plans to foray into petrochemical business with a Rs 16,000 crore project with German chemical major BASF.

Speaking at the 9th Vibrant Gujarat Summit here, Adani said his group’s investments in Gujarat in the past five years exceed Rs 50,000 crores and “we are further accelerating our investments.”

“Over the next 5 years, our investments will include the world’s largest solar hybrid park in Khavda. The anticipated investment in this park is Rs 30,000 crore. We also plan to establish a 1 GW Data Center Park in Mundra, a one million ton copper smelting and refining project, a cement and clinker manufacturing unit in Lakhpat, an integrated Lithium battery manufacturing complex and expand our Photovoltaic manufacturing capabilities. Overall, we anticipate a total of Rs 55,000 crore of investment in all these projects,” he said.

Image Source: Google

Continue Reading

Projects

Bangladesh’s Chhatak Cement announces modernisation project

Published

on

By

Bangladesh’s Chhatak Cement Co Ltd has announced plans to modernise its facility and convert it from wet process to dry process. The company has begun to prepare a development project proposal, with a schedule to implement the upgrades by 2021.

According to company officials, Chhatak Cement has incurred an accumulated loss of over BDT3.63bn (US$43.25m) between FY13-14 and FY17-18, mainly due to its outdated machinery resulting in loss of production capacity. The plant is currently operating at 70,000 tonnes per annum (tpa).

However, the new project is anticipated to boost production capacity and increase annual company profit to around BDT1bn. The modernisation is expected to be financed by a BDT8.9bn investment from the government, with BDT5.34bn as a loan with a payback period of seven years and the rest as equity, according to The Financial Express.

Image Source: Google

Continue Reading

Projects

Forced shutdown of Viet-Dung Quat cement plant in Vietnam

Published

on

By

The Dai Viet-Dung Quat cement plant has been forced to temporarily shut down in the central province of Quang Ngai due to environmental pollution. Since 26 May, the locals had gathered in front of the plant to call for a shutdown.

Director of Central Region Cement JSC Trinh Van Dien, investor in the Dai Viet-Dung Quat cement plant, said, “We invited an environmental monitoring team to check the dust concentration and the results are safe. The local Department of Natural Resources and Environment hasn?t reached a conclusion on the noise level yet.”

He added, “We?ve had to temporarily close the plant, meaning we”re losing VND300m (US$13,437) and the 100 workers are kicking their heels at home. I don”t know what to do.”

The ground clearance work should have been done this year but the coal-powered plant project was delayed until 2020. As a result, the ground clearance work has also been delayed.

According to the locals, they want to be compensated for the relocation if the plant stays. “We don?t want to stay. We have to move,” local Nguyen Ne said.

Image Source: Google

Continue Reading

Trending News

SUBSCRIBE TO THE NEWSLETTER

 

Don't miss out on valuable insights and opportunities to connect with like minded professionals.

 


    This will close in 0 seconds