Connect with us

Concrete

Sometimes, a comedy of errors

Published

on

Shares

My first real project was one such. I was just two years out of engineering college, a mechanical engineer raring to have a go at the world. I was fortunate that I got a job in a well-known engineering and projects company, (at a very princely salary of Rs 700 per month, by the way!) and I spent the first two years on the shop floor in a heavy engineering workshop, where no two jobs were alike, no two machine tools were identical, and no two people thought or acted similarly. It was diversity at its best ever, as you can possibly see, and every hour, every day of it was worthwhile. It was here, that one night while I was on night shift duty in the machine shop, I took a break to go into the adjacent central office and typed out a three page letter addressed to the Managing Director, giving detailed suggestions on how the graduate engineers training scheme could be improved. But, that is another story, for another day.

Let us come back to the project story, for now. The year was 1981, I would guess. Without naming the project and the customer, let me just say that it was a hi-tech metallurgical project, being installed for the first time in India in an integrated steel plant, valued at approximately Rs 4 to 5 crore. This was being executed in collaboration with a famous German company. After two years of a good grind in the machine shop floor, I was given the role of a project coordinator in this project, operating initially from the Kolkata Project and Engineering Office, and then moving to site once erection work started. This is when all hell broke loose. This is where we proved beyond an iota of doubt that Mr Murphy was an optimist, because here everything went wrong, and more! I remember that we used to lament that everything that we engineered, manufactured or purchased for this project, gave trouble of some kind or other at site, starting from anti-static floor-mats to Programmable Logic Control Panels, from foundation bolts to hydraulic actuators.

Talking about foundation bolts, this is an item often forgotten, probably because it falls ??etween the stools??of scope of supply of the Supplier and the Erector and the Civil Contractor. First thing we found at site when kicking off erection work, was that the foundation bolts were missing, no one delivered them. It took a few days of running around to get the whole set manufactured, and things got delayed in the process. Today, the first thing that I check in a project, (always, everytime) is have the anchor bolts and inserts been delivered. That was lesson number one!

An anecdotal account of all the pitfalls we encountered at this project site, would have surely made absorbing reading, but sadly, it is somewhat difficult to recall full details of 30 year old incidents. However, some such snippets are still etched in mind.

Another freak problem was, that of fast uncontrolled descent of 25 tonne fabricated vacuum covers, when they were being stopped electrically at the end of the lift. This was due to the few milliseconds of delay of braking through electro-hydraulic thrustor brakes, but the free fall of the heavy covers was really scary. We solved this one at site by installing electro-mechanical timers in the motor circuit, such that motor is stopped with a delay, after the brake gets the signal. I personally loved this one, and that is why I may not forget this incident ever in my lifetime!

Hydraulics were an important part of the project, not only for actuation, but also for fine controls. There were several Moog Control valves with closed loop electronics, and obviously, there were special low-micron high pressure filters upstream of these valves. These were in addition to normal coarse filters in the circuit, as well as LP filters on return line, and recirculating filtration circuits. When we started testing and trial operations of the hydraulics, after thorough cleaning/pickling/pressure test etc, the HP filters started getting choked frequently, and soon we had consumed all spare filter cartridges, which were imported as two years??spares! This, despite the fact that the whole hydraulic Power System along with the Tank were located in a pressurized cellar. What ensued was a lot of study, a lot of data collection, and a lot of consultation with experts. We learnt a lot about selection criteria of hydraulic filters, agglomeration of particulates in hydraulic flow, logjam effect, etc. Ultimately, we zeroed in on a recirculating electrostatic paper filter system, which ran 24×7 in parallel, and brought down the particulate contamination in the tank, of all sizes, to considerably lower levels, and only then the imported HP Filter cartridges started giving long life. This incident made me some sort of an ??xpert??on hydraulic oil filtration.

I know that some the incidents will evoke laughter, but I will still take the risk of narrating the story of the travelling weigh hopper, which refused to travel. This one was a 800 KG capacity load-cell mounted motorised weigh hopper designed to travel on square bar rails, equipped with trailing cable. This hopper was to travel below several bunkers, and receive measured weights of various mineral additives, and then discharge the same into a two chamber vacuum lock. When we did everything right, and switched on the power from local control push button, the small little wheels of the hopper started rotating furiously, but it did not move forward. It was a real hilarious scene. The weight of the hopper was far too less compared to the motor power, and there was inadequate rolling friction for traction to take place. We did a star-delta switch arrangement to reduce the motor power, and it worked beautifully thereafter.

Pages of this issue will fall short of space, if I were to keep talking about all the other problems, related to things like steam ejectors, counter-sunk bolts for liner plates, electro-mechanical actuators, slide gates in ladles, etc., etc, and also, things may become too technical for some of us. The essence is, during design and manufacture phase of a project, we may do many things good or bad, right or wrong, but all of these come home to roost at site, during installation. No more can the problems or mistakes be overlooked or avoided, they have to be resolved then and there, and otherwise work will stall. In that way, Erection at site is the last bit of execution, which is unforgiving, merciless. Here, at site, none of the time-tested strategies like ??assing the buck?? ??elaying/postponing?? ??kirting the issue?? etc work. Here, one has to catch the proverbial bull by the horn and find a solution and implement the solution as soon as possible. Of course, this is the reason why site work is so interesting, at the same time so much more full of adrenalin, action and tension. On hindsight, I liked it. And my advice to young project managers is that they should not miss an opportunity to work at installation sites, particularly if the project is ??irst of its kind in the country?? One or two years of work at site is like five years in the air-conditioned office, in terms of enriching experience of problem solving and project management.

– SUMIT BANERJEE

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Concrete

UltraTech’s Kukurdih unit runs fully on green energy

The Chhattisgarh plant has met 100 per cent of its electricity needs through green energy since April 2026.

Published

on

By

Shares
UltraTech Cement’s Kukurdih Cement Works in Chhattisgarh has met 100 per cent of its electricity requirement through green energy every month since April 2026. Commissioned in 2024, the integrated cement manufacturing unit has an installed grey cement capacity of 3.3 million tonnes per annum.
The plant meets its electricity requirement through a combination of renewable power sourcing and Waste Heat Recovery Systems (WHRS). UltraTech said the combination enables the unit to meet its power needs through green energy while maintaining operational reliability.
Since April 2026, nearly a third of UltraTech’s 76 manufacturing units in India have maintained green energy utilisation above 50 per cent of their electricity requirement. Five units, including Kukurdih, have exceeded 95 per cent green energy utilisation.
The company is also progressively deploying Battery Energy Storage Systems (BESS) across its manufacturing network to support greater integration of renewable energy. UltraTech said it has not invested in new captive thermal power capacity at its integrated units, including greenfield projects and brownfield expansions, for more than 10 years.
As of Q1FY27, UltraTech’s captive green energy capacity stood at 1,897 MW, comprising 1,463 MW of renewable capacity from solar, wind and hybrid sources, and 434 MW of WHRS capacity.
Under its RE100 commitment, the company aims to increase the share of green power in its total power mix to 85 per cent by 2030 and 100 per cent by 2050.

Continue Reading

Concrete

Cement Prices Rise Rs. 7 per Bag in September; October Hikes Expected

Cement prices rose in September as companies weighed further increases.

Published

on

By

Shares

Cement companies may seek to raise prices by Rs. 5 to Rs. 20 per bag across most markets in October, although the ability to sustain the increases will depend on demand recovery and dealer acceptance, according to a report by Centrum Broking. The outlook follows a pickup in pricing momentum during September after largely stable prices in July and August.

The all-India average trade price increased by Rs. 7 per bag month-on-month to Rs. 356 in September. Centrum Broking’s channel checks indicated gains across both trade and non-trade segments, with non-trade prices recording sharper increases in most markets. However, higher company billing rates were not fully passed on to customers in several regions because dealers continued selling at earlier prices to meet quarter-end volume targets.

The brokerage said demand weakness in Q2FY27 was less pronounced than the usual seasonal trend, with construction activity improving in several markets towards the end of the quarter. Demand remained range-bound across several markets in July and August, while September produced mixed regional trends. Higher rainfall affected activity in some areas, whereas lower rainfall supported construction work elsewhere.

South India recorded the largest price increase in September, at Rs. 11 per bag, followed by West India at Rs. 9. Central, East and North India each reported increases of Rs. 5 per bag. Despite the September recovery, the average all-India trade price for Q2FY27 stood at Rs. 351 per bag, down Rs. 1 sequentially, as weaker pricing in July and August offset the later gains.

Centrum Broking said the success of any October increases would depend on the pace of demand recovery and dealers’ willingness to accept higher prices. Fuel prices have also risen sharply in recent weeks, making the implementation and sustainability of price increases a key factor for the cement industry’s pricing outlook.

Continue Reading

Concrete

Andhra Pradesh Clears Rs. 30 bn My Home Cement Plant

Project receives incentives of up to Rs. 11.29 bn from state

Published

on

By

Shares

The Andhra Pradesh government has approved a greenfield cement project worth Rs. 30 bn by My Home Industries, along with incentives of up to Rs. 11.29 bn. The decision comes amid a political controversy in Telangana involving allegations about landholdings associated with My Home Group.

According to an Industries and Commerce Department order issued on September 25, 2026, the project is expected to create 2,000 jobs and begin commercial production by March 2029. The proposed facility will have capacity to produce 3.5 MTPA of clinker and 3.5 MTPA of cement.

The total investment includes fixed capital investment of Rs. 25.97 bn, pre-operative expenses of Rs. 2.23 bn, contingencies of Rs. 1.26 bn and working capital margin of Rs. 540 mn. The incentive package is capped at Rs. 11.29 bn, equivalent to up to 43.48 per cent of fixed capital investment, subject to completion of the committed investment by March 2029.

The package includes a capital subsidy of 39 per cent of eligible fixed capital investment, capped at Rs. 9.43 bn, payable over 10 years from the start of commercial production. It also provides reimbursement of Rs. 1 per unit on electricity purchased from distribution companies for 10 years, subject to a ceiling of Rs. 1.86 bn. A further incentive equivalent to 2 per cent of fixed capital investment is linked to the creation of the committed jobs and other policy conditions.

The state has approved the allotment of 27.19 acres through the Andhra Pradesh Industrial Infrastructure Corporation at actual cost. The project also involves land linked to two temples and the realignment of a canal across approximately 9.93 acres, with conditions requiring alternative temple facilities and company-funded infrastructure work. Telangana Chief Minister A. Revanth Reddy has separately raised allegations concerning land associated with My Home Group, including 2,463 acres near Shamshabad. The allegations remain subject to verification through official records and any investigations.

Continue Reading

Video Thumbnail
â–¶

    SIGN-UP FOR OUR GENERAL NEWSLETTER

    Trending News

    SUBSCRIBE TO THE NEWSLETTER

     

    Don't miss out on valuable insights and opportunities to connect with like minded professionals.

     


      This will close in 0 seconds