Connect with us

Concrete

The World’s Largest Cricket Stadium!

Published

on

Shares

India is home to one of the most remarkable landmarks in the world! Located near the banks of Sabarmati River, the Narendra Modi Stadium in Ahmedabad, Gujarat, is the world?? largest cricket stadium and the second-largest stadium overall. First constructed in 1982, it had a seating capacity of about 35,000 spectators. The stadium can now accommodate over 110,000 cricket fans, surpassing the Melbourne Cricket Ground, which has the capacity to accommodate 100,000 spectators.

Initial brief

??&T?? brief was to construct a new stadium on the footprint of the older stadium with three times more capacity,??shares MV Satish, Whole Time Director & Senior Executive Vice-President – Buildings, L&T Construction. ??he facility also had to feature four dressing rooms, a clubhouse with 50 deluxe rooms and five suites, six indoor pitches, two outdoor practice grounds with pavilions and a main ground lit entirely with LED lights.??The mandate for this design-and-build tender from the client, the Gujarat Cricket Association, was awarded in 2016 and the project was completed in time for the ??amaste Trump??event in February 2020.

Overcoming design challenges

??ize and scale were the biggest challenges,??says Satish. ??he task of constructing an elliptical or oval-shaped stadium began with the detailed design for architecture, structure and allied services developed by the company?? in-house team of designers and engineers?? Myriad challenges were faced during project execution:

  • To speed up construction, precast technology was adopted. The entire superstructure of the stadium is made up of huge, unequally shaped ????columns (30 m in height, 2.7 m in width) weighing some 285 tonne. These were all precast as one piece and transported and erected at an extremely logistically challenged project site.

  • Prestressed cables and PTFE fabric were used for the steel roof structure. The roof has 1,000 m perimeter length, 10.5 m height truss and 30 m cantilever, and is provided at an elevation of about 40 m from ground level. The fabric design and execution teams had to interface for perfect execution.

  • The site is located 3.9 km from the runway of Ahmedabad airport. The permissible height for structures within a 4 km radius was only 45 m whereas the stadium rose to 51 m. The matter had to be taken up with the Airports Authority of India (AAI) to get the design approved without changes.

  • The site had obstructions on three sides with 1.3 km of the total 2.7 km boundary conflicting with an abutting residential colony, while there was a high-tension 132 kV wire that stalled 25 per cent of the construction on the other side, until it was shut off by the Gujarat Energy Transmission Corporation (GETCO).

Special features

To give spectators a 360? unobstructed view of the field of play and the boundary line from any given location on the podium required much detailing and precision in space planning and engineering. The appointed architects, Populous, developed an innovative design to accomplish this. ??s you climb to the upper seating bowl, you experience a panoramic view of the field of play, gradually offering a vista experience,??informs Satish.

The stadium has many interesting features:

  • Each aspect of the stadium, like ease of entry and seamless movement of 1,10,000 spectators, positioning of each tier and placement of the pillars, has been meticulously planned.

  • The 30 m cantilevered roof gives the stadium an impressive and aesthetic look that has been designed on a spoked wheel concept, comprising a steel truss outer compression ring and radial and circumferential cables with a fabric cover.

  • It is the first Indian stadium to have as many as 11 different pitches with the same soil used for both the playing and practice pitches.

  • It is the first stadium with four sets of dressing rooms for the players, each with an in-built gymnasium and other facilities.

  • It is the first stadium in India with LED lights that are uniquely designed and placed in clusters to eliminate shadows of players on the ground.

  • The stadium?? state-of-the-art drainage system can remove rainwater within 30 minutes of the rain stopping.

The stadium has the distinction of being the only cricket stadium in the country to be awarded the Gold Green Building rating by the Indian Green Building Council (IGBC). The award recognises the various green features of the stadium, like the 100 per cent LED lighting to reduce energy consumption, rainwater harvesting capacity of 3.2 million litre per day, potable water saving of 1.2 million litre every year and onsite sewage treatment plant of 1 mld capacity to treat and reuse 100 per cent wastewater for landscaping and flushing requirements.

Machinery and materials used

??ithout equipment, lifting tools and tackles, precast and structural erection was a dream!??says Satish. Some major equipment used included self-propelled modular trailers, crawler cranes in various sizes and 52 hydraulic jacks to lift the cable net structure for the roof (all at a time).

Specially designed self- compacted concrete (SSC) was used to avoid the use of vibrators and to assure quality. A special type of cable net was used on the roof that did not have any mechanical cantilever structure; the PTFE fabric was placed in a 30 m cantilever.

Safety measures

At peak time, L&T had almost 4,500 workmen onsite in addition to over 150 engineers, designers and architects. To ensure the safety of workmen and employees while working at heights and in precariously positioned spaces and safe crane movement along the high-tension line, the following measures were taken:

  • A safety height simulation with BIM 360 modelling was developed to monitor and control the height at which work was happening at the upper bowl.

  • Fall protection at a height of 30 m with CCTV monitoring was installed.

  • Fire load calculations were done at all facilities with independent assessment and fire-fighting equipment installed as per the fire load.

  • The entire site was monitored using CCTV cameras and the footage helped the team to monitor safety measures by zooming into certain sections to check safety railings, safety nets on the staging and other aspects.

How technology helped with the construction challenge!

The elliptical or oval shape of the stadium posed certain engineering challenges as the precast erection had two radii. Coordination of the MEP (mechanical, electrical and plumbing) works with the civil and structural works was a huge task to address. The team used building information modelling (BIM) software, SYNCRO, to execute this successfully.

– PRAHARSHI SAXENA

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Concrete

WCA Welcomes SiloConnect as associate corporate member

Published

on

By

Shares

The World Cement Association (WCA) has announced SiloConnect as its newest associate corporate member, expanding its network of technology providers supporting digitalisation in the cement industry. SiloConnect offers smart sensor technology that provides real-time visibility of cement inventory levels at customer silos, enabling producers to monitor stock remotely and plan deliveries more efficiently. The solution helps companies move from reactive to proactive logistics, improving delivery planning, operational efficiency and safety by reducing manual inspections. The technology is already used by major cement producers such as Holcim, Cemex and Heidelberg Materials and is deployed across more than 30 countries worldwide.

Continue Reading

Concrete

TotalEnergies and Holcim Launch Floating Solar Plant in Belgium

Published

on

By

Shares

TotalEnergies and Holcim have commissioned a floating solar power plant in Obourg, Belgium, built on a rehabilitated former chalk quarry that has been converted into a lake. The project has a generation capacity of 31 MW and produces around 30 GWh of renewable electricity annually, which will be used to power Holcim’s nearby industrial operations. The project is currently the largest floating solar installation in Europe dedicated entirely to industrial self-consumption. To ensure minimal impact on the surrounding landscape, more than 700 metres of horizontal directional drilling were used to connect the solar installation to the electrical substation. The project reflects ongoing collaboration between the two companies to support industrial decarbonisation through renewable energy solutions and innovative infrastructure development.

Continue Reading

Concrete

Cortec® Corporation applauded for its strong safety performance

Published

on

By

Shares

Cortec® Corporation has been recognised for its strong safety performance, receiving its sixth Governor’s Workplace Safety Award for its outstanding performance in 2025. As a Silver Achievement recipient, the company continues to maintain safety metrics well above national industry averages, an impressive accomplishment for a chemical manufacturing organisation. This achievement reflects Cortec’s proactive approach to workplace safety, focused on early hazard detection and employee involvement. The company will be formally recognised at the Minnesota Safety and Health Conference in May, highlighting how industrial companies are effectively strengthening workplace safety standards.

Continue Reading

Video Thumbnail

    SIGN-UP FOR OUR GENERAL NEWSLETTER


    Trending News

    SUBSCRIBE TO THE NEWSLETTER

     

    Don't miss out on valuable insights and opportunities to connect with like minded professionals.

     


      This will close in 0 seconds