Connect with us

Concrete

The World’s Largest Cricket Stadium!

Published

on

Shares

India is home to one of the most remarkable landmarks in the world! Located near the banks of Sabarmati River, the Narendra Modi Stadium in Ahmedabad, Gujarat, is the world?? largest cricket stadium and the second-largest stadium overall. First constructed in 1982, it had a seating capacity of about 35,000 spectators. The stadium can now accommodate over 110,000 cricket fans, surpassing the Melbourne Cricket Ground, which has the capacity to accommodate 100,000 spectators.

Initial brief

??&T?? brief was to construct a new stadium on the footprint of the older stadium with three times more capacity,??shares MV Satish, Whole Time Director & Senior Executive Vice-President – Buildings, L&T Construction. ??he facility also had to feature four dressing rooms, a clubhouse with 50 deluxe rooms and five suites, six indoor pitches, two outdoor practice grounds with pavilions and a main ground lit entirely with LED lights.??The mandate for this design-and-build tender from the client, the Gujarat Cricket Association, was awarded in 2016 and the project was completed in time for the ??amaste Trump??event in February 2020.

Overcoming design challenges

??ize and scale were the biggest challenges,??says Satish. ??he task of constructing an elliptical or oval-shaped stadium began with the detailed design for architecture, structure and allied services developed by the company?? in-house team of designers and engineers?? Myriad challenges were faced during project execution:

  • To speed up construction, precast technology was adopted. The entire superstructure of the stadium is made up of huge, unequally shaped ????columns (30 m in height, 2.7 m in width) weighing some 285 tonne. These were all precast as one piece and transported and erected at an extremely logistically challenged project site.

  • Prestressed cables and PTFE fabric were used for the steel roof structure. The roof has 1,000 m perimeter length, 10.5 m height truss and 30 m cantilever, and is provided at an elevation of about 40 m from ground level. The fabric design and execution teams had to interface for perfect execution.

  • The site is located 3.9 km from the runway of Ahmedabad airport. The permissible height for structures within a 4 km radius was only 45 m whereas the stadium rose to 51 m. The matter had to be taken up with the Airports Authority of India (AAI) to get the design approved without changes.

  • The site had obstructions on three sides with 1.3 km of the total 2.7 km boundary conflicting with an abutting residential colony, while there was a high-tension 132 kV wire that stalled 25 per cent of the construction on the other side, until it was shut off by the Gujarat Energy Transmission Corporation (GETCO).

Special features

To give spectators a 360? unobstructed view of the field of play and the boundary line from any given location on the podium required much detailing and precision in space planning and engineering. The appointed architects, Populous, developed an innovative design to accomplish this. ??s you climb to the upper seating bowl, you experience a panoramic view of the field of play, gradually offering a vista experience,??informs Satish.

The stadium has many interesting features:

  • Each aspect of the stadium, like ease of entry and seamless movement of 1,10,000 spectators, positioning of each tier and placement of the pillars, has been meticulously planned.

  • The 30 m cantilevered roof gives the stadium an impressive and aesthetic look that has been designed on a spoked wheel concept, comprising a steel truss outer compression ring and radial and circumferential cables with a fabric cover.

  • It is the first Indian stadium to have as many as 11 different pitches with the same soil used for both the playing and practice pitches.

  • It is the first stadium with four sets of dressing rooms for the players, each with an in-built gymnasium and other facilities.

  • It is the first stadium in India with LED lights that are uniquely designed and placed in clusters to eliminate shadows of players on the ground.

  • The stadium?? state-of-the-art drainage system can remove rainwater within 30 minutes of the rain stopping.

The stadium has the distinction of being the only cricket stadium in the country to be awarded the Gold Green Building rating by the Indian Green Building Council (IGBC). The award recognises the various green features of the stadium, like the 100 per cent LED lighting to reduce energy consumption, rainwater harvesting capacity of 3.2 million litre per day, potable water saving of 1.2 million litre every year and onsite sewage treatment plant of 1 mld capacity to treat and reuse 100 per cent wastewater for landscaping and flushing requirements.

Machinery and materials used

??ithout equipment, lifting tools and tackles, precast and structural erection was a dream!??says Satish. Some major equipment used included self-propelled modular trailers, crawler cranes in various sizes and 52 hydraulic jacks to lift the cable net structure for the roof (all at a time).

Specially designed self- compacted concrete (SSC) was used to avoid the use of vibrators and to assure quality. A special type of cable net was used on the roof that did not have any mechanical cantilever structure; the PTFE fabric was placed in a 30 m cantilever.

Safety measures

At peak time, L&T had almost 4,500 workmen onsite in addition to over 150 engineers, designers and architects. To ensure the safety of workmen and employees while working at heights and in precariously positioned spaces and safe crane movement along the high-tension line, the following measures were taken:

  • A safety height simulation with BIM 360 modelling was developed to monitor and control the height at which work was happening at the upper bowl.

  • Fall protection at a height of 30 m with CCTV monitoring was installed.

  • Fire load calculations were done at all facilities with independent assessment and fire-fighting equipment installed as per the fire load.

  • The entire site was monitored using CCTV cameras and the footage helped the team to monitor safety measures by zooming into certain sections to check safety railings, safety nets on the staging and other aspects.

How technology helped with the construction challenge!

The elliptical or oval shape of the stadium posed certain engineering challenges as the precast erection had two radii. Coordination of the MEP (mechanical, electrical and plumbing) works with the civil and structural works was a huge task to address. The team used building information modelling (BIM) software, SYNCRO, to execute this successfully.

– PRAHARSHI SAXENA

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Concrete

BMC Cement Concretisation Cuts Pothole Repairs By 70 Per Cent

Project worth Rs 170 billion (Rs 170 bn) aims to concretise 1,900 km by 2027

Published

on

By

Shares

The Brihanmumbai Municipal Corporation’s cement concretisation project, valued at Rs 170 billion (Rs 170 bn), has reduced expenditure on pothole repairs by 70 per cent over three years. Spending on repairs fell from Rs 2.02 billion in 2023–24 to Rs 1.56 billion in 2024–25 and then to Rs 890 million (Rs 890 mn) in 2025–26. The current tender is expected to be about Rs 440 million, representing a further 50 per cent reduction.

The project is being executed in two phases, with Phase I covering 307 km from October 2023 and Phase II covering 370 km from October 2024. The Indian Institute of Technology is auditing Phase II and will now also audit Phase I to ensure quality and accountability. Mumbai’s total road network spans approximately 2,050 km, of which about 1,200 km had been converted to cement concrete before 2022.

Since 2022 an additional 677 km were taken up for concretisation and nearly 71 per cent of that work, amounting to 481 km, has been completed. Municipal officials indicated that 10–15 per cent of the remaining work is expected to be completed by May 2026 and another 10 per cent by December 2026. The entire programme is scheduled for completion by May 2027, by which time nearly 1,900 km of Mumbai’s roads are expected to be fully concretised.

The administration has also developed a real time dashboard that displays detailed information about contracts, contractors and progress and citizens can access the latest updates online. The dashboard includes contact details for the civic officials and contractors responsible for particular roads to enhance transparency and accountability. The commissioner directed that ongoing works be completed by 31 May ahead of the monsoon to safeguard completion targets and minimise disruption.

Continue Reading

Concrete

Shree Cement Approves Rs 1,800 Crore Meghalaya Plant

Integrated unit to be completed by quarter ending March 2028

Published

on

By

Shares

Shree Cement has approved the establishment of an integrated cement plant in Meghalaya, signalling a targeted capacity expansion to serve regional demand. The board cleared a unit at Village Daistong in East Jaintia Hills District with a clinker capacity of zero point nine five million tonnes per annum (mn t) and a cement capacity of zero point nine nine million tonnes per annum (mn t). The project was approved on April four, 2026 and is designed as a new addition to the company’s production network where it currently has no existing plant.

The company has earmarked an estimated investment of Rs 1,800 crore (Rs 18 billion (bn)) for the project, which will be financed through a mix of internal accruals and debt. Management has indicated a balanced financing strategy to preserve cash flows while supporting long-term growth and operational investment. The financing approach is intended to avoid over reliance on external borrowing and to maintain financial discipline during the build out.

The plant is expected to improve logistics efficiency and compress distribution distances to emerging demand centres in the north-east, potentially lowering transportation costs and lead times. By locating production closer to demand the company aims to strengthen market access and respond more effectively to regional construction activity. The project forms part of a broader strategy to diversify the production base across geographies and reduce concentration risk.

Execution is planned over a multi-year window with completion targeted by the quarter ending March 2028 and the company will proceed with construction and requisite regulatory clearances. The integrated design is intended to enhance operational control and production efficiency once operational. The decision follows a regulatory filing dated April four, 2026 and the disclosed details have not been independently verified.

Continue Reading

Concrete

WCA Welcomes SiloConnect as associate corporate member

Published

on

By

Shares

The World Cement Association (WCA) has announced SiloConnect as its newest associate corporate member, expanding its network of technology providers supporting digitalisation in the cement industry. SiloConnect offers smart sensor technology that provides real-time visibility of cement inventory levels at customer silos, enabling producers to monitor stock remotely and plan deliveries more efficiently. The solution helps companies move from reactive to proactive logistics, improving delivery planning, operational efficiency and safety by reducing manual inspections. The technology is already used by major cement producers such as Holcim, Cemex and Heidelberg Materials and is deployed across more than 30 countries worldwide.

Continue Reading

Video Thumbnail

    SIGN-UP FOR OUR GENERAL NEWSLETTER


    Trending News

    SUBSCRIBE TO THE NEWSLETTER

     

    Don't miss out on valuable insights and opportunities to connect with like minded professionals.

     


      This will close in 0 seconds