Connect with us

Concrete

Optimising Concrete Precasting

Published

on

Shares

Precast concrete technology adds value and reduce cost of the project as compared to cast in-situ built.

In India, there is a huge demand for housing which neither the cities nor the housing sector is prepared for. The construction industry is also facing problems such as shortage of skilled labour, poor workmanship, low productivity and quality of construction plus time and cost overruns, to name a few. Using precast (pre-engineered pre-cast) concrete method improves the speed of construction and saves huge cost.

Concept of precast construction includes those buildings, where the majority of structural components are standardised and produced in bulk quantity which, later, together with other pieces, becomes part of a larger structure. These precast concrete elements are prepared, cast and hardened at specially-equipped plants with a permanent location in plants at project site or in a location away from the building site, and then transported to the site for assembly.

In order to get the best result from the precast concrete technology, experienced precast architects or structural engineers are required, along with well-trained and experienced erection crews are also must to carry out the site work with utmost satisfaction. Precast concrete products do not need any finishing (such as plastering) on site. By using coloured aggregates and form liners beautiful patterns can be achieved on facades/outer load bearing walls of building.

The precast concrete building technology can be efficiently and effectively used for townships, affordable and low-cost mass housing, IT/ITES parks and SEZs at a much competitive cost and on-time schedule to be adopted in the construction sector of India.

Advantages of precast concrete elements

  • Production in controlled environment results in high quality of factory-made strong durable products
  • Repetition of standard precast elements will lead to cost reduction
  • Plastering on precast walls and floor slabs is not needed because of smooth finishing
  • Production can continue in any weather condition
  • Better health and safety standards as compared to the conventional construction methods
  • Project can be better planned, managed and controlled. High speed can be achieved
  • Fast construction, less manpower required on site, and no shuttering required on site
  • Door and window frames can be installed in the wall panels before erection
  • Electricity conduits, pipes and boxes can be embedded in precast panels
  • Large span floor system leads to more flexibility as internal columns are avoided
  • Thin precast walls and facade panels increase the carpet area and reduced self-weight, increased life load
  • Precast concrete is a durable material, which requires less maintenance
  • Precise reinforcing during prefabrication saves steel
  • Precise consumption of all material used
  • Precast plant at site can reduce transportation distance and increase speed of erection

Precast concrete technology adds value and reduce cost of the project as compared to cast in-situ built versus precast:

  • Construction time cost = 50-60 per cent
  • Labour numbers on site cost = 50-60 per cent
  • Waste material on site cost = 40-45 per cent
  • Cost due to less snagging = 40-50 per cent

Indiapreacast.com gives full support for complete range of precast plants and machinery for manufacturing all types of precast concrete elements, including that of affordable/mass housing (even for on-site plants) like:

  • Load bearing hollow core planks
  • Lightweight non-load bearing wall panels, boundary wall, etc.
  • Can manufacture panels at project site
  • Saves transportation and government taxes

Project investment for 100 x 600 mm: Less than Rs 1 crore at Indiaprecast plant. European plants: Rs 8-12 crore. Project requirement: Land required: 1.5 acre plus, having length to width ratio 5:1. Power: 50 Kw is required for only wall panel production. Water: 10,000 liters per day. Labour: Average skilled labours 12 to 15. Raw Material: Cement, sand, aggregate 6 to10 mm/LECA: 2 to 10mm. Speed of Extruder m/c. -1.6 m/min.
Plant capacity: 400 m2/12 hours shifts.

Plants for pallet circulating system (PCS)/carousel system
In hi-tech and high-capacity computer controlled pallet circulating system/carousel system, the production of solid and sandwich elements is highly flexible. The system has been optimised for production of elements up to 12m in length and 4m in height. The employees specialise on individual working steps and are therefore more reliable and competent at their supervising workstations.

Production pallets are transported between the workstations using two side shifters, two concrete spreaders supplying concrete in either grey or coloured form, two vibrating units ensure that the concrete is compacted correctly and power trowels are used to guarantee smooth surfaces, insulated curing racks with 30 places provide the ideal conditions for element curing. A plotter, cleaning and oiling equipment and tilting station all serve to boost the efficiency of the system.

Concept of a carousel system

  • Concrete elements are produced on work tables (pallets)
  • Pallets are transported to the working stations, shuttering, reinforcement, concreting and compaction
  • After the curing time of eight hours at the curing places the finished elements will be removed and the empty pallet will be transported to the next working station
  • There are various methods for making affordable/mass/EWS/LIG housing by precast technology. Some of the most comm-only used are:

Method A
Suitable for ground up to fourth floor. Advantage of this method is that it is very low on investment

  • Plinth, beam and column – made from cast-in situ.
  • Floor and roof – made from precast, pre-stressed load bearing hollow core concrete slab/planks. (120mm thick slab x 600/1,200 mm width depending on requirement and design) along with structural screed of 50 mm.
  • External walls – made from hollow core non-load bearing lightweight interlocking wall panels 120/150 mm thick x 600 mm width or from AAC block/hollow block/solid Block. All to be plastered from inside and outside.
  • Internal partition – made from hollow core non-load bearing lightweight interlocking wall panels (100 mm thick x 600 mm width length to cut as per requirement from long slab only skim coat plaster required)
  • Other items made from molds include staircase, balcony mold, lift shaft and waterproof toilet pods

Method B

Suitable ground up to 13th floor. Advantage of this method is that it is average on investment.

  • Solid load bearing outer wall are precast (160/200 mm thick other dimension as per design). No beam and column. Made by plants for pallet circulating system with central shifter or by plants for pallet in-line – vibrated and tilted by mobile shuttle.
  • Floor and roof – made from precast, pre-stressed load bearing hollow core concrete slab/planks. (150/200/250 mm thick slab x 1,200 mm width depending on the requirement and design) along with structural screed of 50 mm.
  • Internal partition – made from hollow core non-load bearing lightweight interlocking wall panels (100 mm thick x 600 mm width length to cut as per requirement from long slab only skim coat plaster required).
  • Other items made from molds include staircase, balcony mold, lift shaft and waterproof toilet pods.

Method C
Suitable for ground up to 23rd floor. Advantage of this method is: fast construction but little high in investment as compared to above.

  • External walls solid load bearing type of 160/200/250 mm thick depending on the requirement and design. Made by plants for pallet circulating system with central shifter or by plants for pallet in-line – vibrated and tilted by mobile shuttle.
  • Floors/roof from half floor slab/semi-finished floor slab (up to 3 m width x 10 m long x 40/60 mm thick) made with lattice girder/truss for floor and roof. Plants for filigree/half floor slab with lattice girder on long line casting bed. (Including pre-stressed)
  • Internal partition walls – made from hollow core non-load bearing lightweight interlocking wall panels (100 mm thick x 600 mm width length to cut as per requirement from long slab only skim coat plaster required).
  • Other items made from molds include staircase, balcony mold, lift shaft and waterproof toilet pods.
  • Precast, pre-stressed load bearing hollow core concrete slab used for floor and roof are made by extrusion process on steel bed/concrete bed. Size available from 120 x 600 mm, 150 x 1,200 mm, 200 x 1,200 mm, 250 x 1,200 mm, 300 x 1,200 mm, 380 x 1,200 mm. The span depends on the load, steel reinforcement and thickness of the slab.
  • Hollow core non-load bearing lightweight interlocking wall panels for making partition walls are made by extrusion process on concrete bed/or automatic plant. Size available from 100 x 600, 120 x 600 mm, 150 x 600 mm. Most commonly used is 100 x 600 mm.

About the AUTHOR:
Vijay Shah
is a Consultant for Precast Plant and Machinery and its technology.?He is a mechanical engineer, having 40 years of experience and more than eight years in the precast industry.’He has visited major precast plant manufacturers and their clients in the world.

Web: www.indiaprecast.com

He can be contacted on:

Email: sogovijay@hotmail.com

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Concrete

UltraTech Cement Expands in Andhra Pradesh with Rs. 26.5 bn

Petnikota plant adds 3.6 MTPA cement dispatch capacity

Published

on

By

Shares

UltraTech Cement has expanded its manufacturing footprint in Andhra Pradesh with the commissioning of Petnikota Cement Works, an integrated cement plant built with an investment of around Rs. 26.5 bn. The facility is located in Petnikota village in Kolimigundla mandal of Nandyal district, in the Rayalaseema region.

Construction of the plant began in May 2025. The facility has a clinkerisation capacity of 3.3 MTPA and a cement dispatch capacity of 3.6 MTPA, strengthening the company’s production and distribution presence in the State.

The plant is expected to provide direct employment to 650 people and indirect employment to another 2,000. It has been designed to operate entirely on green energy and does not have a captive thermal power plant. The project also uses no groundwater, according to information released by the Andhra Pradesh Government.

Nara Lokesh, Andhra Pradesh Minister for Information Technology, said in the release that the facility was taken from groundbreaking to commissioning in 14 months. He described the project as a state-of-the-art addition to the company’s operations in the State and said it would create 2,650 direct and indirect employment opportunities.

Petnikota Cement Works adds to UltraTech Cement’s manufacturing capacity in Andhra Pradesh while supporting industrial activity in Nandyal district. The plant’s energy design and stated groundwater-use policy are also intended to reduce the environmental impact of its operations. The company has identified the facility as part of its continuing capacity expansion in the Indian cement market.

Continue Reading

Concrete

Nuvoco reports 13.5% revenue growth in Q2 FY27

Cement sales rose 9% to 4.7 MMT, while EBITDA increased 11%.

Published

on

By

Shares
Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.
The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.
On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid renewable energy project in Rajasthan. Once operational, the project is expected to generate about 100 million units of renewable electricity annually. The company expects it to reduce reliance on conventional power sources and improve long-term cost certainty across its Rajasthan operations.
Jayakumar Krishnaswamy, Managing Director, Nuvoco Vistas Corp. Ltd., said, “Q2 FY27 was a testament to resilient execution in a challenging operating environment. Despite intense and erratic rainfall in our key markets, global and regional logistics & supply chain disruptions, and elevated input costs stemming from ongoing geopolitical uncertainty, the Company delivered strong YoY growth in Revenue, EBITDA, and PAT. Our performance reflects the strength of our strategic levers of premiumisation and geographical mix optimisation, which helped realisations amid muted cement prices.”
He added, “During the quarter, the Company achieved a significant growth milestone with the successful commissioning of the 2 MMTPA Grinding Unit at Limla, Surat, underscoring our strong project execution capabilities. This achievement reinforces our confidence in delivering the remaining modules of the Vadraj Cement Project at Kutch and Sachana within the planned timelines. Looking ahead, while we remain mindful of evolving macroeconomic and geopolitical dynamics, we remain focused on operational excellence, accelerating premiumisation, optimising supply chain efficiencies, and executing our growth projects as planned.

Continue Reading

Concrete

Meghalaya Cabinet Approves MCCL Closure, Writes Off Rs. 244.3 mn

Cabinet approves winding up of state-owned cement company

Published

on

By

Shares

The Meghalaya Cabinet has approved the closure and winding up of Meghalaya Cherra Cement (MCCL), a state-owned cement company, with pending liabilities of approximately Rs. 244.3 mn to be written off as part of the process. The decision was announced by Chief Minister Conrad K Sangma on October 13, 2026.

The approved write-off comprises about Rs. 89 mn in sales tax dues and Rs. 155.3 mn in royalty dues. The Cabinet’s decision addresses the liabilities that remained after the company’s operations and enables the government to proceed with its formal closure.

Sangma said employee dues owed by MCCL had been settled in line with the state government’s commitment. The settlement of employee-related liabilities is a key part of the winding-up process and removes outstanding obligations to the company’s workforce.

The Chief Minister explained that MCCL is owned by the government, meaning the pending liabilities would otherwise involve transfers between the state government and its departments. Writing off the dues is intended to simplify the accounting and administrative steps required to complete the closure.

The decision is also intended to ensure that the winding-up does not create an additional financial burden for the state government. With employee payments settled and the sales tax and royalty liabilities addressed through the approved write-off, the Cabinet’s approval marks a further step towards completing the formal closure of MCCL.

The action follows the state government’s decision to discontinue the company and resolve its outstanding obligations through an orderly winding-up process. The approved measures cover the principal liabilities identified for settlement and allow the government to advance the remaining formal procedures associated with closing the state-owned enterprise.

Continue Reading

Video Thumbnail
▶

    SIGN-UP FOR OUR GENERAL NEWSLETTER

    Trending News

    SUBSCRIBE TO THE NEWSLETTER

     

    Don't miss out on valuable insights and opportunities to connect with like minded professionals.

     


      This will close in 0 seconds