Connect with us

Concrete

Material, Machinery and Manpower!

Published

on

Shares

Here?? the latest connection between the ancient cities of Prayagraj and Varanasi: the six-laning of the Handia to Varanasi section of NH-2 from 712.900-km to 785.544-km in Uttar Pradesh under NHDP Phase 5 on HAM. At Rs.24.47 billion, the completion of this highway has opened doors of accessibility for national and international tourists and devotees. It is also a major part of the Delhi Calcutta Golden Quadrilateral Project-1 and Asian Highway-1. The stretch passes through the major districts of Eastern Uttar Pradesh, i.e. Prayagraj, Bhadohi, Mirzapur and Varanasi.

With this project, the travel time between Prayagraj and Varanasi has been reduced to between one-and-a-half and two hours only, from three to four hours previously.

Initial brief

The NHAI (developer) tender document provided the development features as six-laning of the existing four-lane road in 72.644-km length, with the provision of five new elevated structures, three new grade separators, three minor bridges, 10 new VUPs, and 12 new PUPs, and provided the inventory of the existing four-lane road.

As for manpower, machinery and time, RC Jain, Senior Vice-President – Operations, GR Infraprojects, says. ??e have used a short-term schedule to map out the detailed tasks needed to coordinate day-to-day work in each specific activity for timely completion of the project.??The schedule was developed by the key personnel of the highway and structures team to plan and coordinate their work at the detail level. Further, the schedules used to be revised by the team every one, two or four weeks depending on the complexity of the work. ??his encouraged continuity of work to complete it within its given time schedule of 910 days. Although it was one project, we planned it in five separate packages and mobilised the team accordingly.??/p>

Machinery and materials

A huge fleet of specialised plant and equipment was procured. Ratan Lal Kashyap, Senior Vice-President – Procurement, GR Infraprojects, says, ??amp sites were established at five locations on the project stretch to execute such a humongous task within such a short period. Further, the advanced and newly purchased equipment fleet and machineries have played a vital role, resulting in less maintenance and good efficiency.??/p>

In highway works, this included two concrete batching plants for PQC concrete, an advanced HMP plant and WMM plant along with a number of pavers, graders, dozers, excavators, rollers and dumpers. As for structure works, here?? the list:

  • Four concrete batching plants to produce concrete

  • Three hydraulic rigs for piling works along with cranes of the required capacity

  • Boom placers, transit mixers, shuttering and stagging material and other allied tools and tackles for concreting works

  • Four launching girders operated simultaneously on five elevated structures with 228 spans of PSC precast segmental spine and wings in the superstructure

  • Four high-capacity cranes to launch the flyover girders

  • Development of a casting yard with EOT cranes, batching plant, and automatic cutting and binding machine for reinforcement

  • Advanced quality control lab for testing concrete and various other materials.

Further, in terms of vital construction materials used in highway construction, Kashyap mentions ??G-40 grade of bitumen for enhanced performance; polymer-modified bitumen for BC for enhanced performance; and CTSB in subbase to improve the CBR.??As for structure works, he adds, ??MT steel of Grade FE 550D: 45,000 mt; high-tensile strand (HTS): 6,500 mt; spherical bearings: 932; and modular expansion joints, which were used in the superstructure of the elevated structures.??/p>

How technology took over the construction challenge!

Jain elaborates on the role technology played in overcoming construction-related challenges that arose during the project:

  • RE wall: A huge quantity of earth fill was required for filling at the RE wall locations. For fulfilling the required quantity, the earth was stocked at various locations prior to the rainy season, by which we were able to continuously carry out the work. Further, traffic was also plying on the existing four-lane area; hence, work had to be executed with deployment of machinery with precise safety.

  • Kanwar Yatra during July-August each year and Kumbh Mela in January 2019: These were major deterrents to progress. During this period, the administration would take over control of the site to maintain safe passage for pilgrims travelling between Prayagraj and Varanasi. Progress was drastically hampered during such events. To overcome the situation, additional machinery and manpower were deployed during the day and night.

  • Highway works: Availability of hindrance-free land is the challenge, which constrains execution of work to bits and pieces, involving a lot of shifting of machinery. Thus was overcome by deploying extra machinery and continuous planning.

  • Structure works: An elevated structure having a 23.55-m deck width with a single pier is the most challenging to design and even more difficult to execute in a densely populated area managing the flow of existing highway traffic in available ROW of 26-30 m at most places. To overcome such challenges, a segmental superstructure with spine and wings arrangement was adopted. The spine and wing segments were cast in the casting yard, transported by specially designed trailers, erected by launching girders and, thereafter, prestressed with high-capacity jacks.

Despite the deployment of various techniques and technologies, work was completely suspended at the onset of pandemic. ??ut later,??as Kashyap shares, ??ith the help of the administration, adopting standard operating procedures for preventing COVID-19 among workers and maintaining social distancing and hygienic conditions at camps and workplaces, we could start critical works with 20 per cent of the workforce. We gradually increased this in the next three months as per approval from the local administration.??/p>

Accident-free execution and safe activity

The total number of labour involved in this project has varied month to month; on average, 367,500 man-month labourers were deployed during the construction period. Also, an elaborate safety plan was prepared at the start of work and regular safety audits were conducted by the safety consultant appointed by the client, NHAI. Jain says, ??HAI helped us ensure safety in the work zone for traffic and the workforce. We also had our separate safety team, which ensured safety measures were undertaken before the start of each activity and until the safe completion of the same.??/p>

Impact on economic development

This project will lead to various benefits such as economic development owing to better connectivity between Prayagraj and Varanasi and other areas of Uttar Pradesh; employment opportunities to locals during construction and operation phases; greater road safety; reduction in vehicle operating costs, environmental benefits such as reduction in emissions and noise levels because of smooth traffic flow on the improved road; and improvement in existing cross-drainage structures, minimising water logging along the road.

– SHRIYAL SETHUMADHAVAN

Project Details:

Cost: Rs 24.47 billion

Completion: November 2020

Construction period: 910 days

Total length: 72.644-km

Developer: National Highway Authority of India (NHAI)

Concessionaire: Varanasi Sangam Expressway

EPC contractor: GR Infraprojects

Consultant: Theme Engineering Services, Jaipur

Equipment supplier: Owned equipment by GR Infraprojects

Steel supplier: SAIL, TATA Steel

Road signage and thermoplast production: In-house development

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Concrete

NDMC Rolls Out Intensive Sanitation Drive Across Lutyens Delhi

Municipal body intensifies cleaning and monitoring across the capital

Published

on

By

Shares

The New Delhi Municipal Council has launched an intensive sanitation drive across Lutyens’ Delhi, aiming to raise cleanliness standards in the capital’s central precincts. The programme will combine enhanced manual sweeping with mechanised cleaning and systematic waste removal to cover parks, heritage precincts and prominent thoroughfares. Authorities described the initiative as a sustained effort to improve public hygiene and reduce environmental hazards while maintaining the area’s civic image.

Operational teams have been instructed to prioritise drain clearing and litter hotspots, with special attention to markets and transit nodes that attract heavy footfall. Coordination with city utilities and waste processing units will be stepped up to ensure timely collection and disposal, and supervisory rounds will monitor adherence to cleaning schedules. Officials also intend to use data-driven planning to deploy resources efficiently and to identify recurring problem areas.

The council plans to engage resident welfare associations and business stakeholders to foster community participation in maintaining cleanliness and to support behavioural change campaigns. Public communication will be amplified through notices and outreach to encourage responsible waste handling and to inform residents about collection timings and segregation norms. Enforcement measures for littering and unauthorised dumping will be reinforced as part of a broader strategy to deter violations and sustain cleanliness gains.

The move reflects a focus on urban sanitation that officials link to public health priorities and to the city administration’s commitment to maintaining civic amenities. Monitoring mechanisms will include regular reporting and inspections to review outcomes and to recalibrate operations where necessary, according to municipal sources. The council emphasised that continued community cooperation will be essential for the drive to deliver lasting improvements in the appearance and hygiene of the capital’s core areas.

Continue Reading

Concrete

UltraTech Appoints Jayant Dua As MD-Designate For 2027

Executive named to succeed current managing director in 2027

Published

on

By

Shares

UltraTech Cement has appointed Jayant Dua as managing director (MD) designate who will take charge in 2027, the company announced. The appointment signals a planned leadership transition at one of the country’s largest cement manufacturers. The board has set a clear timeline for the handover and has framed the move as part of a structured succession plan.

Jayant Dua will be referred to as MD after assuming the role and will be responsible for overseeing operations, strategy and growth initiatives across the company’s network. The company said the designation follows established governance norms and aims to ensure continuity in executive leadership. The appointment is expected to allow a phased transfer of responsibilities ahead of the formal changeover.

The decision is intended to provide strategic stability as UltraTech Cement navigates domestic infrastructure demand and evolving market dynamics. Management will continue to focus on operational efficiency, capacity utilisation and cost management while aligning investments with long term objectives. The board will monitor the transition and provide further information on leadership responsibilities closer to the effective date.

Investors and market observers will have time to assess the implications of the announcement before the change is effected, and analysts will review the company’s outlook in the context of the succession. The company indicated that it will communicate any additional executive appointments or organisational changes as they are finalised. Shareholders were advised to refer to formal filings and company releases for definitive details on governance or remuneration.

The leadership change will be managed with attention to stakeholder interests and operational continuity, and the company reiterated its commitment to delivery on ongoing projects and customer obligations. Senior management will engage with employees and partners to ensure a smooth handover while maintaining focus on safety and compliance. Further updates will be provided through official investor communications in due course.

Continue Reading

Concrete

Merlin Prime Spaces Acquires 13,185 Sq M Land Parcel In Pune

Rs 273 crore purchase broadens the developer’s Pune presence

Published

on

By

Shares

Merlin Prime Spaces (MPS) has acquired a 13,185 sq m land parcel in Pune for Rs 273 crore, marking a notable expansion of its footprint in the city.

The transaction value converts to Rs 2,730 mn or Rs 2.73 bn.

The parcel is located in a strategic area of Pune and the firm described the acquisition as aligned with its growth objectives.

The deal follows recent activity in the region and will be watched by investors and developers.

MPS said the acquisition will support its planned development pipeline and enable delivery of commercial and residential space to meet local demand.

The company expects the site to provide flexibility in product design and phased development to respond to market conditions.

The move reflects an emphasis on land ownership in key suburban markets.

The emphasis on land acquisition reflects a strategy to secure inventory ahead of demand cycles.

The purchase follows a period of sustained investor interest in Pune real estate, driven by expanding office ecosystems and residential demand from professionals.

MPS will integrate the new holding into its existing portfolio and plans to engage with local authorities and stakeholders to progress approvals and infrastructure readiness.

No financial partners were disclosed in the announcement.

The firm indicated that timelines will depend on approvals and prevailing market conditions.

Analysts note that strategic land acquisitions at scale can help developers manage costs and timelines while preserving optionality for future projects.

MPS will now hold an enlarged land bank in the region as it pursues growth, and the acquisition underlines continued corporate appetite for measured expansion in second tier cities.

The company intends to move forward with detailed planning in the coming months.

Stakeholders will assess how the site is positioned relative to existing infrastructure and connectivity.

Continue Reading

Trending News

SUBSCRIBE TO THE NEWSLETTER

 

Don't miss out on valuable insights and opportunities to connect with like minded professionals.

 


    This will close in 0 seconds