Connect with us

Concrete

Material, Machinery and Manpower!

Published

on

Shares

Here?? the latest connection between the ancient cities of Prayagraj and Varanasi: the six-laning of the Handia to Varanasi section of NH-2 from 712.900-km to 785.544-km in Uttar Pradesh under NHDP Phase 5 on HAM. At Rs.24.47 billion, the completion of this highway has opened doors of accessibility for national and international tourists and devotees. It is also a major part of the Delhi Calcutta Golden Quadrilateral Project-1 and Asian Highway-1. The stretch passes through the major districts of Eastern Uttar Pradesh, i.e. Prayagraj, Bhadohi, Mirzapur and Varanasi.

With this project, the travel time between Prayagraj and Varanasi has been reduced to between one-and-a-half and two hours only, from three to four hours previously.

Initial brief

The NHAI (developer) tender document provided the development features as six-laning of the existing four-lane road in 72.644-km length, with the provision of five new elevated structures, three new grade separators, three minor bridges, 10 new VUPs, and 12 new PUPs, and provided the inventory of the existing four-lane road.

As for manpower, machinery and time, RC Jain, Senior Vice-President – Operations, GR Infraprojects, says. ??e have used a short-term schedule to map out the detailed tasks needed to coordinate day-to-day work in each specific activity for timely completion of the project.??The schedule was developed by the key personnel of the highway and structures team to plan and coordinate their work at the detail level. Further, the schedules used to be revised by the team every one, two or four weeks depending on the complexity of the work. ??his encouraged continuity of work to complete it within its given time schedule of 910 days. Although it was one project, we planned it in five separate packages and mobilised the team accordingly.??/p>

Machinery and materials

A huge fleet of specialised plant and equipment was procured. Ratan Lal Kashyap, Senior Vice-President – Procurement, GR Infraprojects, says, ??amp sites were established at five locations on the project stretch to execute such a humongous task within such a short period. Further, the advanced and newly purchased equipment fleet and machineries have played a vital role, resulting in less maintenance and good efficiency.??/p>

In highway works, this included two concrete batching plants for PQC concrete, an advanced HMP plant and WMM plant along with a number of pavers, graders, dozers, excavators, rollers and dumpers. As for structure works, here?? the list:

  • Four concrete batching plants to produce concrete

  • Three hydraulic rigs for piling works along with cranes of the required capacity

  • Boom placers, transit mixers, shuttering and stagging material and other allied tools and tackles for concreting works

  • Four launching girders operated simultaneously on five elevated structures with 228 spans of PSC precast segmental spine and wings in the superstructure

  • Four high-capacity cranes to launch the flyover girders

  • Development of a casting yard with EOT cranes, batching plant, and automatic cutting and binding machine for reinforcement

  • Advanced quality control lab for testing concrete and various other materials.

Further, in terms of vital construction materials used in highway construction, Kashyap mentions ??G-40 grade of bitumen for enhanced performance; polymer-modified bitumen for BC for enhanced performance; and CTSB in subbase to improve the CBR.??As for structure works, he adds, ??MT steel of Grade FE 550D: 45,000 mt; high-tensile strand (HTS): 6,500 mt; spherical bearings: 932; and modular expansion joints, which were used in the superstructure of the elevated structures.??/p>

How technology took over the construction challenge!

Jain elaborates on the role technology played in overcoming construction-related challenges that arose during the project:

  • RE wall: A huge quantity of earth fill was required for filling at the RE wall locations. For fulfilling the required quantity, the earth was stocked at various locations prior to the rainy season, by which we were able to continuously carry out the work. Further, traffic was also plying on the existing four-lane area; hence, work had to be executed with deployment of machinery with precise safety.

  • Kanwar Yatra during July-August each year and Kumbh Mela in January 2019: These were major deterrents to progress. During this period, the administration would take over control of the site to maintain safe passage for pilgrims travelling between Prayagraj and Varanasi. Progress was drastically hampered during such events. To overcome the situation, additional machinery and manpower were deployed during the day and night.

  • Highway works: Availability of hindrance-free land is the challenge, which constrains execution of work to bits and pieces, involving a lot of shifting of machinery. Thus was overcome by deploying extra machinery and continuous planning.

  • Structure works: An elevated structure having a 23.55-m deck width with a single pier is the most challenging to design and even more difficult to execute in a densely populated area managing the flow of existing highway traffic in available ROW of 26-30 m at most places. To overcome such challenges, a segmental superstructure with spine and wings arrangement was adopted. The spine and wing segments were cast in the casting yard, transported by specially designed trailers, erected by launching girders and, thereafter, prestressed with high-capacity jacks.

Despite the deployment of various techniques and technologies, work was completely suspended at the onset of pandemic. ??ut later,??as Kashyap shares, ??ith the help of the administration, adopting standard operating procedures for preventing COVID-19 among workers and maintaining social distancing and hygienic conditions at camps and workplaces, we could start critical works with 20 per cent of the workforce. We gradually increased this in the next three months as per approval from the local administration.??/p>

Accident-free execution and safe activity

The total number of labour involved in this project has varied month to month; on average, 367,500 man-month labourers were deployed during the construction period. Also, an elaborate safety plan was prepared at the start of work and regular safety audits were conducted by the safety consultant appointed by the client, NHAI. Jain says, ??HAI helped us ensure safety in the work zone for traffic and the workforce. We also had our separate safety team, which ensured safety measures were undertaken before the start of each activity and until the safe completion of the same.??/p>

Impact on economic development

This project will lead to various benefits such as economic development owing to better connectivity between Prayagraj and Varanasi and other areas of Uttar Pradesh; employment opportunities to locals during construction and operation phases; greater road safety; reduction in vehicle operating costs, environmental benefits such as reduction in emissions and noise levels because of smooth traffic flow on the improved road; and improvement in existing cross-drainage structures, minimising water logging along the road.

– SHRIYAL SETHUMADHAVAN

Project Details:

Cost: Rs 24.47 billion

Completion: November 2020

Construction period: 910 days

Total length: 72.644-km

Developer: National Highway Authority of India (NHAI)

Concessionaire: Varanasi Sangam Expressway

EPC contractor: GR Infraprojects

Consultant: Theme Engineering Services, Jaipur

Equipment supplier: Owned equipment by GR Infraprojects

Steel supplier: SAIL, TATA Steel

Road signage and thermoplast production: In-house development

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Concrete

Ultra Concrete Age

Prof. A. S. Khanna (Retd., IIT Bombay) on how Ultra-high performance concrete (UHPC) improves strength, durability and lifecycle performance.

Published

on

By

Shares
The need of present time is stronger buildings, industrial or common utility buildings, such as Malls, Railway stations, hospitals, offices, bridges etc. For this, there is need of long durable, tough and stable concrete, which could stand under normal and seismic conditions. Tough railway bridges are required for bullet trains to pass without any damage. Railway tunnels, sea-links, coastal roads, bridges and multistorey buildings, are the need of the hour. The question comes, is the normal cement called OPC is sufficient to take care of such requirements or better combination of cements and sand mixtures is required?
Introduction
A good stable building structure can be made with a good quality of cement+sand+water system. Its quality can be enhanced by keeping the density of admixture higher (varies from 30 in normal buildings to bridges etc to 80). Further enhancement in the properties of various cements admixtures is made by adding several additives which give additional strength, waterproofing, flexibility etc. These are called construction chemicals…

Continue Reading

Concrete

NCB Signs MoU With Cement Manufacturer To Boost Construction Skills

Partnership to deliver nationwide training and certification

Published

on

By

Shares

The National Council for Cement and Building Materials (NCB) has signed a memorandum of understanding with a leading cement manufacturer to strengthen skill development and capacity building in the construction sector. The agreement was formalised at NCB premises in Ballabgarh and was signed by the Director General of NCB, Dr L. P. Singh, and the head of technical services at UltraTech Cement Limited, Er Rahul Goel. The collaboration seeks to bring institutional resources and industry expertise into a structured national training effort.

The partnership will deliver structured training and certification programmes across the country aimed at enhancing the capabilities of civil engineers, ready?mix concrete (RMC) professionals, contractors, construction workers and masons. Programme curricula will cover material quality testing, concrete mix proportioning, durability assessment and sustainable construction practices to support improved construction outcomes. Emphasis is to be placed on standardised assessment and certification to raise practice levels across diverse construction roles.

Practical learning elements will include workshops, site demonstrations, technical seminars and exposure visits to plants and RMC facilities to strengthen applied skills and on?site decision making. The Director General indicated confidence that a large number of professionals and workers would be trained over the next three to five years under the initiative. The partnership is designed to complement flagship government schemes such as the Skill India Mission and to align training outputs with national infrastructure priorities.

By combining the council’s technical mandate with industry experience, the initiative aims to develop a more skilled and quality?conscious workforce capable of meeting rising demand in infrastructure and housing. NCB will continue to coordinate programme delivery and quality assurance while industry partners provide practical exposure and technical inputs. The collaboration is expected to support long?term capacity building and more sustainable construction practices nationwide.

Continue Reading

Concrete

JSW Cement Commissions Nagaur Plant, Enters North India

New Rajasthan unit boosts capacity to 24.1 MTPA and expands reach

Published

on

By

Shares
JSW Cement has strengthened its national presence by commencing production at its greenfield integrated cement plant in Nagaur, Rajasthan, marking its entry into the north Indian market.
With this commissioning, the company’s installed grinding capacity has increased to 24.1 MTPA, while total clinker capacity, including its joint venture operations, stands at 9.74 MTPA.
The Nagaur facility comprises a 3.30 MTPA clinkerisation unit and a 2.50 MTPA cement grinding unit, with an additional 1.00 MTPA grinding capacity currently under development. Strategically located, the plant is positioned to serve high-growth markets across Rajasthan, Haryana, Punjab and the NCR.
The project has been funded through a mix of equity and long-term debt, with Rs 800 crore allocated from IPO proceeds towards part-financing the unit.
Parth Jindal, Managing Director, JSW Cement, stated that the commissioning marks a key milestone in the company’s ambition to become a pan-India player. He added that the project was completed within 21 months and positions the company to achieve its targeted capacity of 41.85 MTPA by FY29.
Nilesh Narwekar, CEO, JSW Cement, highlighted that the expansion aligns with the company’s strategy to tap into rapidly growing northern markets driven by infrastructure development. He noted that the company remains focused on delivering high-quality, eco-friendly cement solutions while progressing towards its long-term capacity goal of 60 MTPA.
The Nagaur plant has been designed with sustainability features, including co-processing of alternative fuels and a 7 km overland belt conveyor for limestone transport to reduce road emissions. The facility will also incorporate a 16 MW Waste Heat Recovery System to improve energy efficiency and lower its carbon footprint.
JSW Cement, part of the JSW Group, operates across the building materials value chain and currently has eight plants across India, along with a clinker unit in the UAE through its joint venture.

Continue Reading

Video Thumbnail
â–¶

    SIGN-UP FOR OUR GENERAL NEWSLETTER


    Trending News

    SUBSCRIBE TO THE NEWSLETTER

     

    Don't miss out on valuable insights and opportunities to connect with like minded professionals.

     


      This will close in 0 seconds