Vijay Shah, Managing Partner, India Precast, advocates the use of precast concrete as he puts forth details about its manufacturing, uses and methods while emphasising the sustainability of the product.
Explain the process of casting concrete in shapes and what is the grade of concrete used for making these shapes? Precast casting concrete elements are manufactured with the required steel reinforcement either in formwork, moulds or on steel plates with side shuttering etc. The concrete cast is made at a different location and is then transported to the site. Precast elements are made of minimum M20 to M50 grade of concrete.
What is the difference between precast and cast in-situ as uses of concrete?
The use of concrete in the precast method and the cast in-situ method differs widely based on many factors.
Precast concrete shapes are cast at a different location and are then transported to the site where construction work takes place while with the cast in-situ process, concrete is poured on-site.
Curing of precast concrete is fast as it takes place under ideal and controlled conditions while the cast in-situ concrete takes relatively longer to get cured but can be easily used for two-way structural systems.
For the precast concrete, the process is easy to do and is repeatable as the same moulds or framework can be used. This increases the value of construction and derives more value
while cast in-situ adapts building shapes and post tensioning.
The work and rework in the usage of precast shapes is less, thus, reduces cost at the site
while with the cast in-situ method there is a requirement of space allotment for concrete mix and necessary add-ins, that is added cost for the construction job.
Tell us about prestressed and reinforced concrete. Prestressed concrete is a combination of high strength concrete and tensioned steel strands. This combination makes a strong structural unit that is useful in building roof slabs, bridge girders etc. Reinforced concrete is manufactured from a combination of high strength concrete and normal reinforcement bars.
Tell us more about the precast elements manufactured, their shapes and sizes. Precast is one of the best ways to rapidly build industrial buildings, commercial buildings, affordable housing, mass, EWS, LIG housing, schools, hospitals, public buildings, agriculture railways, stadiums, sport centres, parking, bridges, airports etc. They have a higher productivity and quality set at industry level. Various types of precast elements manufactures are:
Floor and roof slabs are made from prestressed load bearing hollow core concrete slab and ribbed slabs. They are also made from half floor slab or semi-finished floor slab with a lattice girder
Precast stair cases, balcony, toilet pods, lift shafts, water tanks
Prestressed lintel, frames, beams, columns and double-tee beams
Internal partition walls are made with light-weight hollow core wall panels instead of AAC blocks or bricks
Boundary walls, fencing poles, U-drainage or trenches, box culvert etc.
What is hollowcore concrete flooring and what is its lifespan? Hollowcore slabs are precast, prestressed concrete elements that are generally used for flooring. Some of the advantages of using these flooring are longer lifespans and no propping, flexibility in designs, faster construction, lightweight structures, fire resistant structures, high load capacities and units manufactured specific to the project. The maximum span of hollowcore floors will depend on the floor depth and the specific loadings imposed on the floor.
What are the quality standards followed while making precast shapes for any project? Quality control is a very important aspect in the process of making precast concrete shapes. It is imperative to make precast shapes as per the exact requirement provided by the engineers and the construction party. To maintain the quality of product from our end,
We ensure there are quality control systems and procedures in place along with a quality assurance plan. Our programme consists of tests, trials, and general procedures for acceptance.
There is a laboratory and related facilities, which are required for the selection and control of the quality of materials and workmanship. The central quality laboratory is used for various quality control tests like cube test, workability test, slump test, sieve analysis etc. The materials used for making the final precast shapes also has to be shared for testing to various third-party laboratories with an advance intimation.
All the necessary tests are carried out in respective batching plants or sites depending on the use of concrete at our facility.
Documentation for all the tests conducted and their reports is maintained in records, for references and submission to the relevant authorities and the users of the same.
As precast use of concrete is conducted in a dedicated space and is in a monitored environment, it becomes easier to maintain high quality due to its repeatability factor. The necessary general precast machinery and moulds, steel tables, concrete batching and dispensing equipment, vibrating and finishing equipment and dedicated labour team help maintain the higher quality standards as compared to cast in-situ use of concrete.
How do you incorporate sustainability in the process of precasting? Precast use of concrete promotes sustainability with its repeatability factor. There’s more planning involved in the process and equipment like the moulds, vibrating machine, finishing machine are all reusable elements of the process. As mentioned, there is planning in precast use of concrete where only the required measure of concrete is mixed and poured into moulds that are made to precision as per the requirement of the project. The quantity is also previously defined, which means there is reduced to zero wastage of material. This waste reduction leads to lesser needs of cleaning and clearing equipment, which may further be fueled by other energy sources. Thus, precast concrete, by large, is a sustainable means of building.
What are the advantages of using precast concrete? There are multiple advantages of using a precast structure for any project like cost efficiency, speed, versatility, safety, sustainability and beauty. This includes:
The use of precast improves the quality and lifespan of any building
It reduces the time of building, thus reducing the costs involved for all the other equipment and labour that goes in to the project, thus, proving to be cost effective
The maintenance of a precast is lower due to its high quality and durability that is ensured while it is cast
This method of using concrete is a sustainable option due to its repeatability
What are the major challenges you face in the process of making precast shapes and in their transportation? The precast industry plays on volume and repetition. This is one of the major challenges as well. The requirement of having to repeat the process that contains a large volume of mixed concrete and getting the same perfection in the shapes is a cumbersome process. The initial investment in setting up the precast plant and acquiring all equipment and moulds is high. With bulk shapes to be transported from one place to another and the requirement for site space and handling, this time of concrete use is more suitable for tier 2 and tier 3 cities.
How do precast elements or shapes help in the profitability of a construction activity? As precast concrete is made at a different location than the construction site, the other jobs keep going on at the site and then the precast shapes are placed there. This reduces construction time to up to one-third to one-fifth as compared to cast in-situ concrete, thus, reducing cost of the construction. Construction maintenance is reduced as the quality of their precast structures are monitored and carefully administered at the plant level. This means it adds to the reliability, durability, accuracy, and ability to produce architectural elements in any building adding to its quality and strength. Precast also provides insulation, thermal inertia and fire resistance and the possibility of integration with MEP (Mechanical, Electrical and Plumbing) from the start of the project.
How can precast concrete contribute towards affordable mass housing in India? Defined shapes and technical requirements in precast concrete helps reduce the waste and increase the repeatability factor, thus, reduces the cost and time for any construction or building project. Higher control on quality, less time consumer leads to lesser need of labour and equipment on-site, which also adds to the profitability of the structure. All factors combined bring down the overall cost of the project, leading to that benefit translating to the end consumer and bringing a surge of affordable mass housing in India.
-Kanika Mathur
Comparison Between Cast-in-situ (conventional method) versus Technology Drive Precast
Sr. No Criteria Conventional Construction Precast Construction 3D Modular/ Panel & Hollow Core Slab. 1 Natural resource consumption High 30 per cent saving 2 Labour Problem Heavy labour problem while work in progress Less labour required 3 Dependability on skilled labor 60 per cent Dependability 4 Time consuming Verv High Fast track 5 Initial investment Low High 6 Finishin Normal Excellent 7 Quality production Poor Excellent as factory based. 8 Material wastage High Least 9 Speed/ Productivity Low Excellent 10 Strength Good Excellent 11 Durability Low High 12 Structure weight/ Deed load Very heavy Reduced 13 Brick Block and Plastering Required No Need 14 Service like Electrical, plumbing & sanitary Break, Provide & Re-build Pre-embedded
JSW Cement has commissioned an additional 1 MTPA cement grinding unit in Nagaur, Rajasthan, taking the company’s total cement grinding capacity to 25.1 MTPA. The commissioning was announced on Tuesday, October 6.
The company said the new unit had increased the total cement grinding capacity at its Rajasthan plant to 3.50 MTPA. The expansion adds to JSW Cement’s production infrastructure as it continues to build capacity across its operating network.
The company’s total clinker manufacturing capacity, including capacity at its joint venture JSW Cement FZC, stands at 9.74 MTPA. Clinker is an intermediate material used in cement production, and its availability supports the company’s grinding operations.
JSW Cement is also pursuing a proposed merger of its listed subsidiary Shiva Cement with the company. The scheme, approved by the boards of the respective companies, involves issuing five fully paid-up JSW Cement equity shares for every 41 shares held by Shiva Cement shareholders other than JSW Cement.
The arrangement remains subject to shareholder and regulatory approvals. JSW Cement currently holds 66.23 per cent of Shiva Cement’s paid-up equity share capital, and the shares held by JSW Cement in the subsidiary will be cancelled under the proposal without any issue of JSW Cement shares against that holding.
The scheme has an appointed date of April 1, 2026, and the company has indicated that completion could take 12 to 14 months, depending on the receipt of approvals. These include clearances from stock exchanges, the Securities and Exchange Board of India, the National Company Law Tribunal and other applicable authorities, along with approvals from shareholders and creditors where required. JSW Cement shares closed at Rs. 113.15 on the BSE, up Rs. 2.05, or 1.85 per cent.
Singh brings 20+ years of brand and marketing experience, and will lead integrated corporate brand communication initiatives at Wonder CementÂ
New Delhi
Wonder Cement, a leading cement manufacturer, has appointed Mahesh Singh as Vice President – Corporate Brand Communication. In his new role, he will oversee corporate brand strategy and communication, including digital and performance marketing, public relations, trade, events, exhibitions, sports and experiential marketing.
Singh brings over two decades of experience across marketing and communications, with roles spanning the automotive industry, agencies and entrepreneurship. He spent more than a decade with Honda Motorcycle & Scooter India, working across integrated communication, media, digital, retail and consumer engagement. His stint also included helping build the company’s digital marketing capabilities.
He moved to dentsu X India as Vice President – Strategy & Planning, working across categories such as automotive, auto components, electric vehicles, FMCG, consumer electronics, BFSI, apparel and brand consulting. His responsibilities included media and marketing strategy, product launches, content, performance marketing and consumer activations.
Singh subsequently took an entrepreneurial route with Radiant Brands before joining Shriram Ltd (SPR Autotech) as Head – Marketing & Communications. There, his remit included brand and corporate strategy, communications, PR and ORM, retail identity, loyalty programmes and events.
At Wonder Cement, Singh will be responsible for bringing together the company’s corporate brand communication initiatives across digital, performance marketing, PR, trade, sports and experiential platforms. The role will focus on creating an integrated approach to communication across consumers, trade partners and other key stakeholders.
The appointment brings to Wonder Cement a marketer whose career has spanned the brand, agency and entrepreneurial sides of the communications ecosystem.
Wonder Cement, part of the RK Group, is a cement manufacturer with roots in Rajasthan and a focus on quality, trust and transparency. The company has grown to six manufacturing plants, and a cement capacity of 21.5 MTPA. With more than 2,000 employees and a network of over 5,000 dealers, its operations span manufacturing, distribution and customer engagement, with a focus on consistent product quality and efficient execution.
JSW Cement has commissioned an additional 1 million tonne per annum (MTPA) cement grinding unit at its Nagaur Integrated Plant in Rajasthan. The commissioning takes the company’s total cement grinding capacity to 25.10 MTPA.Â
JSW Cement’s total clinker manufacturing capacity, including its joint venture JSW Cement FZC, now stands at 9.74 MTPA.
The company began operations in North India in March 2026 with the Nagaur Integrated Plant, comprising a 3.30 MTPA clinkerisation unit and a 2.50 MTPA cement grinding unit. With the latest expansion, the plant’s total grinding capacity has increased to 3.50 MTPA.
The additional capacity will cater to cement demand across Rajasthan, Haryana, Punjab and the National Capital Region (NCR). The expansion has been funded through a combination of equity and long-term debt.
During the quarter ended September 30, 2026, JSW Cement also commissioned an Alternate Fuel Handling System and a Waste Heat Recovery System (WHRS) at the Nagaur plant.
Nilesh Narwekar, CEO, JSW Cement, said the additional grinding capacity was a strategic priority for the company’s expansion in North India. He added that the Alternate Fuel Handling System and WHRS were expected to reduce production costs.