Connect with us

Concrete

The World’s Largest Cricket Stadium!

Published

on

Shares

India is home to one of the most remarkable landmarks in the world! Located near the banks of Sabarmati River, the Narendra Modi Stadium in Ahmedabad, Gujarat, is the world?? largest cricket stadium and the second-largest stadium overall. First constructed in 1982, it had a seating capacity of about 35,000 spectators. The stadium can now accommodate over 110,000 cricket fans, surpassing the Melbourne Cricket Ground, which has the capacity to accommodate 100,000 spectators.

Initial brief

??&T?? brief was to construct a new stadium on the footprint of the older stadium with three times more capacity,??shares MV Satish, Whole Time Director & Senior Executive Vice-President – Buildings, L&T Construction. ??he facility also had to feature four dressing rooms, a clubhouse with 50 deluxe rooms and five suites, six indoor pitches, two outdoor practice grounds with pavilions and a main ground lit entirely with LED lights.??The mandate for this design-and-build tender from the client, the Gujarat Cricket Association, was awarded in 2016 and the project was completed in time for the ??amaste Trump??event in February 2020.

Overcoming design challenges

??ize and scale were the biggest challenges,??says Satish. ??he task of constructing an elliptical or oval-shaped stadium began with the detailed design for architecture, structure and allied services developed by the company?? in-house team of designers and engineers?? Myriad challenges were faced during project execution:

  • To speed up construction, precast technology was adopted. The entire superstructure of the stadium is made up of huge, unequally shaped ????columns (30 m in height, 2.7 m in width) weighing some 285 tonne. These were all precast as one piece and transported and erected at an extremely logistically challenged project site.

  • Prestressed cables and PTFE fabric were used for the steel roof structure. The roof has 1,000 m perimeter length, 10.5 m height truss and 30 m cantilever, and is provided at an elevation of about 40 m from ground level. The fabric design and execution teams had to interface for perfect execution.

  • The site is located 3.9 km from the runway of Ahmedabad airport. The permissible height for structures within a 4 km radius was only 45 m whereas the stadium rose to 51 m. The matter had to be taken up with the Airports Authority of India (AAI) to get the design approved without changes.

  • The site had obstructions on three sides with 1.3 km of the total 2.7 km boundary conflicting with an abutting residential colony, while there was a high-tension 132 kV wire that stalled 25 per cent of the construction on the other side, until it was shut off by the Gujarat Energy Transmission Corporation (GETCO).

Special features

To give spectators a 360? unobstructed view of the field of play and the boundary line from any given location on the podium required much detailing and precision in space planning and engineering. The appointed architects, Populous, developed an innovative design to accomplish this. ??s you climb to the upper seating bowl, you experience a panoramic view of the field of play, gradually offering a vista experience,??informs Satish.

The stadium has many interesting features:

  • Each aspect of the stadium, like ease of entry and seamless movement of 1,10,000 spectators, positioning of each tier and placement of the pillars, has been meticulously planned.

  • The 30 m cantilevered roof gives the stadium an impressive and aesthetic look that has been designed on a spoked wheel concept, comprising a steel truss outer compression ring and radial and circumferential cables with a fabric cover.

  • It is the first Indian stadium to have as many as 11 different pitches with the same soil used for both the playing and practice pitches.

  • It is the first stadium with four sets of dressing rooms for the players, each with an in-built gymnasium and other facilities.

  • It is the first stadium in India with LED lights that are uniquely designed and placed in clusters to eliminate shadows of players on the ground.

  • The stadium?? state-of-the-art drainage system can remove rainwater within 30 minutes of the rain stopping.

The stadium has the distinction of being the only cricket stadium in the country to be awarded the Gold Green Building rating by the Indian Green Building Council (IGBC). The award recognises the various green features of the stadium, like the 100 per cent LED lighting to reduce energy consumption, rainwater harvesting capacity of 3.2 million litre per day, potable water saving of 1.2 million litre every year and onsite sewage treatment plant of 1 mld capacity to treat and reuse 100 per cent wastewater for landscaping and flushing requirements.

Machinery and materials used

??ithout equipment, lifting tools and tackles, precast and structural erection was a dream!??says Satish. Some major equipment used included self-propelled modular trailers, crawler cranes in various sizes and 52 hydraulic jacks to lift the cable net structure for the roof (all at a time).

Specially designed self- compacted concrete (SSC) was used to avoid the use of vibrators and to assure quality. A special type of cable net was used on the roof that did not have any mechanical cantilever structure; the PTFE fabric was placed in a 30 m cantilever.

Safety measures

At peak time, L&T had almost 4,500 workmen onsite in addition to over 150 engineers, designers and architects. To ensure the safety of workmen and employees while working at heights and in precariously positioned spaces and safe crane movement along the high-tension line, the following measures were taken:

  • A safety height simulation with BIM 360 modelling was developed to monitor and control the height at which work was happening at the upper bowl.

  • Fall protection at a height of 30 m with CCTV monitoring was installed.

  • Fire load calculations were done at all facilities with independent assessment and fire-fighting equipment installed as per the fire load.

  • The entire site was monitored using CCTV cameras and the footage helped the team to monitor safety measures by zooming into certain sections to check safety railings, safety nets on the staging and other aspects.

How technology helped with the construction challenge!

The elliptical or oval shape of the stadium posed certain engineering challenges as the precast erection had two radii. Coordination of the MEP (mechanical, electrical and plumbing) works with the civil and structural works was a huge task to address. The team used building information modelling (BIM) software, SYNCRO, to execute this successfully.

– PRAHARSHI SAXENA

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Concrete

UltraTech Cement FY26 PAT Crosses Rs 80 bn

Company reports record sales, profit and 200 MTPA capacity milestone

Published

on

By

Shares

UltraTech Cement reported record financial performance for Q4 and FY26, supported by strong volumes, higher profitability and improved cost efficiency. Consolidated net sales for Q4 FY26 rose 12 per cent year-on-year to Rs 254.67 billion, while PBIDT increased 20 per cent to Rs 56.88 billion. PAT, excluding exceptional items, grew 21 per cent to Rs 30.11 billion.

For FY26, consolidated net sales stood at Rs 873.84 billion, up 17 per cent from Rs 749.36 billion in FY25. PBIDT rose 32 per cent to Rs 175.98 billion, while PAT increased 36 per cent to Rs 83.05 billion, crossing the Rs 80 billion mark for the first time.

India grey cement volumes reached 42.41 million tonnes in Q4 FY26, up 9.3 per cent year-on-year, with capacity utilisation at 89 per cent. Full-year India grey cement volumes stood at 145 million tonnes. Energy costs declined 3 per cent, aided by a higher green power mix of 43 per cent in Q4.

The company’s domestic grey cement capacity has crossed 200 MTPA, reaching 200.1 MTPA, while global capacity stands at 205.5 MTPA. UltraTech also recommended a special dividend of Rs 2.40 billion per share value basis equivalent to Rs 240.

Continue Reading

Concrete

Towards Mega Batching

Optimised batching can drive overall efficiencies in large projects.

Published

on

By

Shares

India’s pace of infrastructure development is pushing the construction sector to work at a significantly higher scale than previously. Tight deadlines necessitate eliminating concreting delays, especially in large and mega projects, which, in turn, imply installing the right batching plant and ensuring batching is efficient. CW explores these steps as well as the gaps in India’s batching plant market.

Choose well

Large-scale infrastructure and building projects typically involve concrete consumption exceeding 30,000-50,000 cum per annum or demand continuous, high-volume pours within compressed timelines, according to Rahul R Wadhai, DGM – Quality, Tata Projects.

Considering the daily need for concrete, “large-scale concreting involves pouring more than 1,000–2,000 cum per day while mega projects involve more than 3,000 cum per day,” says Satish R Vachhani, Advanced Concrete & Construction Consultant…

To read the full article Click Here

Continue Reading

Concrete

Andhra Offers Discom Licences To Private Firms Outside Power Sector

Policy allows firms over 300 MW to seek distribution licences

Published

on

By

Shares

The Andhra Pradesh government will allow private firms that require more than 300 megawatt (MW) of power to apply for distribution licences, making the state the first to extend such licences beyond the power sector. The policy targets information technology, pharmaceuticals, steel and data centres and aims to reduce reliance on state utilities as demand rises for artificial intelligence infrastructure.

Approved applicants will be able to procure electricity directly from generators through power purchase agreements, a change officials said will create more competitive tariffs and reduce supply risk. Licence holders will use the Andhra Pradesh Transmission Company (APTRANSCO) network on payment of charges and will not need a separate distribution network initially.

Licences will be granted under the Electricity Act, 2003 framework, with the Central and State electricity regulators retaining authority over terms and approvals. The recent Electricity (Amendment) Bill, 2025 sought to lower entry barriers, enable network sharing and encourage competition, while the state commission will set floor and ceiling tariffs where multiple discoms operate.

Industry players and original equipment manufacturers welcomed the policy, saying competitive supply is vital for large data centre investments. Major projects and partnerships such as those involving Adani and Google, Brookfield and Reliance, and Meta and Sify Technologies are expected to benefit as capacity expands in the state.

Analysts noted India’s data centre capacity is forecast to reach 10 gigawatts (GW) by 2030 and cited International Energy Agency estimates that global data centre electricity consumption could approach 945 terawatt hours by the same year. A one GW data centre needs an equivalent power allocation and one point five times the water, which authorities equated to 150 billion litres (150 bn litres).

Advisers warned that distribution licences will require close regulation and monitoring to prevent misuse and to ensure tariffs and supply obligations are met. Officials said the policy aims to balance investor requirements with regulatory oversight and could serve as a model for other states.

Continue Reading

Video Thumbnail

    SIGN-UP FOR OUR GENERAL NEWSLETTER


    Trending News

    SUBSCRIBE TO THE NEWSLETTER

     

    Don't miss out on valuable insights and opportunities to connect with like minded professionals.

     


      This will close in 0 seconds