Connect with us

Concrete

The World’s Largest Cricket Stadium!

Published

on

Shares

India is home to one of the most remarkable landmarks in the world! Located near the banks of Sabarmati River, the Narendra Modi Stadium in Ahmedabad, Gujarat, is the world?? largest cricket stadium and the second-largest stadium overall. First constructed in 1982, it had a seating capacity of about 35,000 spectators. The stadium can now accommodate over 110,000 cricket fans, surpassing the Melbourne Cricket Ground, which has the capacity to accommodate 100,000 spectators.

Initial brief

??&T?? brief was to construct a new stadium on the footprint of the older stadium with three times more capacity,??shares MV Satish, Whole Time Director & Senior Executive Vice-President – Buildings, L&T Construction. ??he facility also had to feature four dressing rooms, a clubhouse with 50 deluxe rooms and five suites, six indoor pitches, two outdoor practice grounds with pavilions and a main ground lit entirely with LED lights.??The mandate for this design-and-build tender from the client, the Gujarat Cricket Association, was awarded in 2016 and the project was completed in time for the ??amaste Trump??event in February 2020.

Overcoming design challenges

??ize and scale were the biggest challenges,??says Satish. ??he task of constructing an elliptical or oval-shaped stadium began with the detailed design for architecture, structure and allied services developed by the company?? in-house team of designers and engineers?? Myriad challenges were faced during project execution:

  • To speed up construction, precast technology was adopted. The entire superstructure of the stadium is made up of huge, unequally shaped ????columns (30 m in height, 2.7 m in width) weighing some 285 tonne. These were all precast as one piece and transported and erected at an extremely logistically challenged project site.

  • Prestressed cables and PTFE fabric were used for the steel roof structure. The roof has 1,000 m perimeter length, 10.5 m height truss and 30 m cantilever, and is provided at an elevation of about 40 m from ground level. The fabric design and execution teams had to interface for perfect execution.

  • The site is located 3.9 km from the runway of Ahmedabad airport. The permissible height for structures within a 4 km radius was only 45 m whereas the stadium rose to 51 m. The matter had to be taken up with the Airports Authority of India (AAI) to get the design approved without changes.

  • The site had obstructions on three sides with 1.3 km of the total 2.7 km boundary conflicting with an abutting residential colony, while there was a high-tension 132 kV wire that stalled 25 per cent of the construction on the other side, until it was shut off by the Gujarat Energy Transmission Corporation (GETCO).

Special features

To give spectators a 360? unobstructed view of the field of play and the boundary line from any given location on the podium required much detailing and precision in space planning and engineering. The appointed architects, Populous, developed an innovative design to accomplish this. ??s you climb to the upper seating bowl, you experience a panoramic view of the field of play, gradually offering a vista experience,??informs Satish.

The stadium has many interesting features:

  • Each aspect of the stadium, like ease of entry and seamless movement of 1,10,000 spectators, positioning of each tier and placement of the pillars, has been meticulously planned.

  • The 30 m cantilevered roof gives the stadium an impressive and aesthetic look that has been designed on a spoked wheel concept, comprising a steel truss outer compression ring and radial and circumferential cables with a fabric cover.

  • It is the first Indian stadium to have as many as 11 different pitches with the same soil used for both the playing and practice pitches.

  • It is the first stadium with four sets of dressing rooms for the players, each with an in-built gymnasium and other facilities.

  • It is the first stadium in India with LED lights that are uniquely designed and placed in clusters to eliminate shadows of players on the ground.

  • The stadium?? state-of-the-art drainage system can remove rainwater within 30 minutes of the rain stopping.

The stadium has the distinction of being the only cricket stadium in the country to be awarded the Gold Green Building rating by the Indian Green Building Council (IGBC). The award recognises the various green features of the stadium, like the 100 per cent LED lighting to reduce energy consumption, rainwater harvesting capacity of 3.2 million litre per day, potable water saving of 1.2 million litre every year and onsite sewage treatment plant of 1 mld capacity to treat and reuse 100 per cent wastewater for landscaping and flushing requirements.

Machinery and materials used

??ithout equipment, lifting tools and tackles, precast and structural erection was a dream!??says Satish. Some major equipment used included self-propelled modular trailers, crawler cranes in various sizes and 52 hydraulic jacks to lift the cable net structure for the roof (all at a time).

Specially designed self- compacted concrete (SSC) was used to avoid the use of vibrators and to assure quality. A special type of cable net was used on the roof that did not have any mechanical cantilever structure; the PTFE fabric was placed in a 30 m cantilever.

Safety measures

At peak time, L&T had almost 4,500 workmen onsite in addition to over 150 engineers, designers and architects. To ensure the safety of workmen and employees while working at heights and in precariously positioned spaces and safe crane movement along the high-tension line, the following measures were taken:

  • A safety height simulation with BIM 360 modelling was developed to monitor and control the height at which work was happening at the upper bowl.

  • Fall protection at a height of 30 m with CCTV monitoring was installed.

  • Fire load calculations were done at all facilities with independent assessment and fire-fighting equipment installed as per the fire load.

  • The entire site was monitored using CCTV cameras and the footage helped the team to monitor safety measures by zooming into certain sections to check safety railings, safety nets on the staging and other aspects.

How technology helped with the construction challenge!

The elliptical or oval shape of the stadium posed certain engineering challenges as the precast erection had two radii. Coordination of the MEP (mechanical, electrical and plumbing) works with the civil and structural works was a huge task to address. The team used building information modelling (BIM) software, SYNCRO, to execute this successfully.

– PRAHARSHI SAXENA

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Concrete

JSW Cement Commissions 1 MTPA Unit in Rajasthan

Rajasthan grinding capacity rises to 3.50 MTPA after commissioning

Published

on

By

Shares

JSW Cement has commissioned an additional 1 MTPA cement grinding unit in Nagaur, Rajasthan, taking the company’s total cement grinding capacity to 25.1 MTPA. The commissioning was announced on Tuesday, October 6.

The company said the new unit had increased the total cement grinding capacity at its Rajasthan plant to 3.50 MTPA. The expansion adds to JSW Cement’s production infrastructure as it continues to build capacity across its operating network.

The company’s total clinker manufacturing capacity, including capacity at its joint venture JSW Cement FZC, stands at 9.74 MTPA. Clinker is an intermediate material used in cement production, and its availability supports the company’s grinding operations.

JSW Cement is also pursuing a proposed merger of its listed subsidiary Shiva Cement with the company. The scheme, approved by the boards of the respective companies, involves issuing five fully paid-up JSW Cement equity shares for every 41 shares held by Shiva Cement shareholders other than JSW Cement.

The arrangement remains subject to shareholder and regulatory approvals. JSW Cement currently holds 66.23 per cent of Shiva Cement’s paid-up equity share capital, and the shares held by JSW Cement in the subsidiary will be cancelled under the proposal without any issue of JSW Cement shares against that holding.

The scheme has an appointed date of April 1, 2026, and the company has indicated that completion could take 12 to 14 months, depending on the receipt of approvals. These include clearances from stock exchanges, the Securities and Exchange Board of India, the National Company Law Tribunal and other applicable authorities, along with approvals from shareholders and creditors where required. JSW Cement shares closed at Rs. 113.15 on the BSE, up Rs. 2.05, or 1.85 per cent.

Continue Reading

Concrete

Wonder Cement appoints Mahesh Singh as VP Corporate Brand Communication 

Published

on

By

Shares

Singh brings 20+ years of brand and marketing experience, and will lead integrated corporate brand communication initiatives at Wonder Cement 

New Delhi

Wonder Cement, a leading cement manufacturer, has appointed Mahesh Singh as Vice President – Corporate Brand Communication. In his new role, he will oversee corporate brand strategy and communication, including digital and performance marketing, public relations, trade, events, exhibitions, sports and experiential marketing. 

Singh brings over two decades of experience across marketing and communications, with roles spanning the automotive industry, agencies and entrepreneurship. He spent more than a decade with Honda Motorcycle & Scooter India, working across integrated communication, media, digital, retail and consumer engagement. His stint also included helping build the company’s digital marketing capabilities. 

He moved to dentsu X India as Vice President – Strategy & Planning, working across categories such as automotive, auto components, electric vehicles, FMCG, consumer electronics, BFSI, apparel and brand consulting. His responsibilities included media and marketing strategy, product launches, content, performance marketing and consumer activations. 

Singh subsequently took an entrepreneurial route with Radiant Brands before joining Shriram Ltd (SPR Autotech) as Head – Marketing & Communications. There, his remit included brand and corporate strategy, communications, PR and ORM, retail identity, loyalty programmes and events. 

At Wonder Cement, Singh will be responsible for bringing together the company’s corporate brand communication initiatives across digital, performance marketing, PR, trade, sports and experiential platforms. The role will focus on creating an integrated approach to communication across consumers, trade partners and other key stakeholders. 

The appointment brings to Wonder Cement a marketer whose career has spanned the brand, agency and entrepreneurial sides of the communications ecosystem. 

Wonder Cement, part of the RK Group, is a cement manufacturer with roots in Rajasthan and a focus on quality, trust and transparency. The company has grown to six manufacturing plants, and a cement capacity of 21.5 MTPA. With more than 2,000 employees and a network of over 5,000 dealers, its operations span manufacturing, distribution and customer engagement, with a focus on consistent product quality and efficient execution. 

Continue Reading

Concrete

JSW Cement commissions additional 1 MTPA grinding unit in Rajasthan

The Nagaur expansion takes JSW Cement’s total grinding capacity to 25.10 MTPA.

Published

on

By

Shares



JSW Cement has commissioned an additional 1 million tonne per annum (MTPA) cement grinding unit at its Nagaur Integrated Plant in Rajasthan. The commissioning takes the company’s total cement grinding capacity to 25.10 MTPA. 
JSW Cement’s total clinker manufacturing capacity, including its joint venture JSW Cement FZC, now stands at 9.74 MTPA.
The company began operations in North India in March 2026 with the Nagaur Integrated Plant, comprising a 3.30 MTPA clinkerisation unit and a 2.50 MTPA cement grinding unit. With the latest expansion, the plant’s total grinding capacity has increased to 3.50 MTPA.
The additional capacity will cater to cement demand across Rajasthan, Haryana, Punjab and the National Capital Region (NCR). The expansion has been funded through a combination of equity and long-term debt.
During the quarter ended September 30, 2026, JSW Cement also commissioned an Alternate Fuel Handling System and a Waste Heat Recovery System (WHRS) at the Nagaur plant.
Nilesh Narwekar, CEO, JSW Cement, said the additional grinding capacity was a strategic priority for the company’s expansion in North India. He added that the Alternate Fuel Handling System and WHRS were expected to reduce production costs.

Continue Reading

Video Thumbnail
▶

    SIGN-UP FOR OUR GENERAL NEWSLETTER

    Trending News

    SUBSCRIBE TO THE NEWSLETTER

     

    Don't miss out on valuable insights and opportunities to connect with like minded professionals.

     


      This will close in 0 seconds