Connect with us

Concrete

IT enables cost-effective clinkerisation at Samrat Cement plant

Published

on

Shares

The cement Industry in Nepal mainly depends on clinker received from Indian cement plants, which is then put into the grinding process in Nepal before sending into the market. One of the biggest challenges for Nepal-based cement companies is the ever-increasing cement manufacturing cost due to surges in the cost of clinker and other raw materials. Availability of resources is another big challenge. Hence, having a clinkerisation plant locally is becoming a need for them to survive in this sector.

Samrat Cement was facing the same challenge. The company came into the cement sector in 2013-14 with their grinding and packing unit at Lamahi-District Dang in Nepal with a vision to build a brand with enhanced quality cement. After establishing itself as a strong brand in Nepal, the company?? vision was to own a clinkerisation plant to cope with cement demand and to survive with manufacturing costs.

Conceptualisation of Project

To meet its vision, Samrat cement awarded a 4000 TPD Clinkerisation Plant to KHD Humboldt Wedag Indiain 2018. The first land excavation started in November 2018, and the entire project was completed in December 2020 with the first production of clinker in January 2021. As added by Basudev Pandeya, Managing Director of Samrat Cement, clinkerisation plant was conceptualised on the following basis.

  • The cost of clinkerisation has to be lower down about 20 to 25 per cent from purchased clinker.

  • The project must be conceptualised in such a manner that the co-generation to be capable to cater the power requirement of the total clinkerisation plant excluding Raw Material grinding.

  • During the selection of clinkerisation plant technology suppliers were called and the best technology was selected.

The main performance parameters are as under:

  • Clinkerisation plant capacity between 3500-4500 TPD to get an optimum range of Co-generation and heat-saving benefits.

  • Raw Material Grinding: KHD Roller Press capacity 345 tph with a specific power of 11.75 Kwh/t Raw meal.

  • KHD High-efficiency cyclone 5 stage Pre-heater (First installation) with a Pressure drop of 300 mmwg at PH fan Inlet and lowest heat consumption.

  • Total Specific power consumption from crusher to Clinkerisation as 43-45 kwh/t.

  • Selection of Roller Press in Raw material grinding enables low heat requirement hence more co-generation possible.

  • Waste Heat recovery plant with hot air

Fast track project with a Target time of completion of 18-24 months

IT Solution to meet the challenges

Based on the above consideration, KHD deployed an energy-efficient grinding machine, Roller Press (RP 16-170/180, Roller surface- CHF), in a closed circuit with V-separator (VS 96/20) dynamic separator (SKS ??LC 3500).

The advantage of this system is that higher capacity requirements are met with lower power consumption.

For Pyro-processing Line, new generation Preheater consists of newly developed High-Efficiency series HE cyclones (PH- 90HE72), Pyro top, Low NOx PYROJET Kiln Burner, 3 station rotary kiln (4.2 m dia x 65 m long), IKN cooler with 90M2/effective cooler area.

The implementation also included other equipment — Limestone crusher-stacker- Reclaimer (Make- Tenova Takraf, 650 TPH), Coal Crusher-Stacker ??eclaimer (Make- Lepton, 150 TPH) & coal mill (VRM-make Pfeiffer, 35 TPH).

Cost-analysis and decision-making

Pandeya said, ??xecuting a 1.5 million tonne per annum cement project at a hilly area like Nepal was never an easy task and required many resources and committed teamwork, further we faced a challenge when it falls during pandemic duration for about 8-9 months hence completing this project within two years is really a success story.??He added further that it would not be possible without the professional skills of the Samrat Team and the professional and enriched experience of KHD Humboldt Wedag India.

Talking about the plant location, the clinkerisation unit of Samrat Cement is located at Satbaria nearby Lamahi Town on verge of the National highway connecting Butwal-Nepalgunj, which is most favourable for a clinkerisation unit because the raw materials are available within a short distance and transportation of product and materials to their destination becomes very easy via national highway.

Plants in Nepal usually require a DG set to run clinkerisation or a UPS of 5-6MW capacity. It is noteworthy that plants, where it is required to have DG sets to run on a continuous basis, will be about three times costlier as compared to the cost of Grid power/co-generated power.

Samrat Cements wanted to go for a better solution, so they finalised on KHD five-stage pre-heater mainly to ensure the co-generation up to 30 to 35 Kwh/t clinker is met. This means there was no need to have any UPS or DG set to continue for the clinkerisation plant.

Pandeya further explains that one side it may look that this decision is costlier in terms of specific heat consumption which is about 20 Kcal/kg as compared with six stage pre-heater technology but on the other hand, the KHD high-efficiency pre-heater solution has its advantage with specific power saving of three units in PH fan and co-generation of additional three units at Pre-heater.

Specific power consumption has about one-third of the cost than that generated by DG sets. (Grid Power costs about 8 to 10 NPR/unit whereas DG generated power costs about 24-27 NPR/unit) so a total of six units saving gives a clear-cut monetary term advantage of about double as it lost in extra heat in five-stage pre-heaters in comparison to 6 stage pre-heater. [Consideration 27 NPR/kwh cost of power with DG set, 15,000 NPR/T landed cost of South African coal, 710 kcal/kg.cl heat consumption, 5500 kcal/kg heat value]

Benefits of a 5 stage Pre-heater

Samrat Cements believed that having a five-stage pre-heater was a wise decision as many plant sites including Nepal do not have strong soil, which may not be suitable for a pre-heater height of more than 125 m. Hence, for higher capacity kiln lines, it may require going for twin string of preheater tower, which has an impact of 20 per cent in civil cost. Below are the advantages.

Planning and execution

Clinkerisation plant was sequenced to start with Limestone crusher along with stacker reclaimer unit and this dc was achieved one month before the kiln light-up. A raw mill that is equipped with roller press was started 15 days before kiln light-up as the roller press circuit does not require hot gas during start-up as compared to VRMs where it is mandatory. This is how the company saved on the cost of Hot air generator.

Around 5000 tonnes of raw meal were grounded with roller press operated in finish mode and kept ready in raw meal silo. Coal mill was started along with kiln light-up and clinker was achieved very fast within 72 hours from kiln start-up.

As per plant operating personnel, the roller press operation in raw material grinding is found to be very simple and trouble-free. Moreover, it is energy efficient.

So far, the total clinkerisation power best achieved is 42.4 kwh/t (Table1). However, the plant started just a few months ago and the company sees great potential to further optimise below 40kwh/t.

Roadmap

Samrat Cement, Nepal is towards a mission of achieving manufacturing cement with the lowest energy consumption and at an economic cost. Producing green cement, minimising carbon emission, energy efficiency, using alternative fuels, and saving water are some of the targets set by the company in near future. Below is a detailed roadmap.

  • Producing green cement with a minimum carbon footprint and saving water. Hence waste heat recovery and roller press technology were given priority.

  • Commissioning of waste heat recovery system, which will cover almost all power consumption of pyro-section excluding some intermediate departments.

  • Expected pay-back period is 2.5 to 3 years for WHRS when compared with DG power.

  • Waste heat recovery system is expected to get commissioned by October 2021.

  • Clinker grinding system where ball mill of 3.4 m x 10 m is getting upgraded with KHD roller press, which will increase the capacity of clinker grinding up to 225tph and specific power shall be 23-25 kwh in finish mode.

  • Samrat cement team added further that total specific power consumption after cement mill upgradation is anticipated as 63 Kwh/t of PPC (From crusher to cement grinding), which will be a benchmark to the cement industry.

  • Usage of alternative fuels in pyro process to consume solid waste produced by the community.

Conclusion

The company is optimistic about achieving specific power consumption for Clinkerisation below 40 kwh/t and total cement production below 60-62 Kwh/t with 700 kcal/kgcl heat consumption. After a successful implementation of this project, the company is hopeful to achieve milestones in near future too.

  1. Waste Heat recovery system (WHRS) with 6 stage Pre-heater have a potential of cogeneration about 28 units/T clinker which needs a UPS to absorb power fluctuation/ switching from grid to DG sets. Hence an additional cost of UPS rating 6-7 MW is huge along with a cumbersome job to maintain UPS batteries. Whereas 5 stage preheaters have the potential for above as 32-35 kwh/t clinker. Hence total clinkerisation plant excluding either Raw Mill can be operated with its own generated power by WHRS.

  2. Pre-heater exit Pressure is lowest among all the plants nearby countries as it found only 250 mmwg at fan inlet while operating without WHRS, which means after WHRS operation it may reach to 300-320 mmwg.

  3. Pre-heater exit pressure is directly linked with Pre-heater fan power which is in the range of 3.5-3.9 Kwh/t.

4. Raw Mix Burnability is found to be easy burning and the combination of Limestone and Clay enriched with Silica and Alumina reacts well and lowers the Pre-heater temperature to 280-290 Deg.C in 5 Stage Pre-heater.

Concrete

Cement Prices To Hold Steady Amid Monsoon Slump

Centrum report says demand weakness will limit hikes

Published

on

By

Shares

Centrum, a financial services firm, has reported that cement prices are likely to remain largely unchanged in July as weak demand during the monsoon season constrains pricing power. The report noted that construction activity remained subdued in the first quarter of fiscal year 2027 owing to labour shortages and slower execution of government projects. While June showed some volume recovery driven by delayed monsoons and quarter end sales, dealers are cautious about sustaining any price increases.

The analysis suggested that seasonal slowdown related to monsoon will prolong demand and pricing challenges through the second quarter. Dealers saw most recent attempts at price hikes as protective measures rather than genuine shifts in market fundamentals. They signalled that pockets of demand in select regions could prompt isolated adjustments but that broad based increases were unlikely while construction activity remained weak. Market participants therefore expected a cautious stance on pricing.

The report highlighted that despite intermittent recovery in shipments during June, the underlying demand trajectory remained muted as monsoon hampered site level activity and logistics. Commercial builders and retail dealers both reported constrained order books and slower payment cycles, which in turn reduced room for margin expansion among manufacturers. Analysts noted that unless government project execution accelerates markedly, demand improvement would be gradual. Price setters were thus likely to focus on protecting market shares rather than pursuing aggressive increases.

Market watchers said the near term outlook would be shaped by monsoon progress and fiscal spending patterns, with any acceleration in public works offering the most tangible support. Traders expected that regional variations would persist and that trade flows between surplus and deficit centres would determine local price movements. The report concluded that stakeholders should prepare for a period of subdued pricing until demand signals strengthen.

Continue Reading

Concrete

Cement Prices Set To Stay Under Pressure In July

Monsoon and weak demand keep prices under strain

Published

on

By

Shares

A report by Centrum said cement prices are expected to remain largely flat in July as the monsoon and weak demand weigh on the sector. The report said demand during the first quarter of FY27 remained range-bound and below expectations, with dealers across markets pointing to subdued construction activity, labour shortages, elections, heatwaves and slower execution of government projects as key reasons. It noted that some recovery was witnessed in June due to delayed onset of the monsoon and quarter-end volume push.\n\nDealers across most markets do not expect any meaningful price increases in July, the report said, adding that attempts to raise prices in some markets are aimed at defending existing levels rather than achieving significant gains. The sharp correction following the rollback of April hikes has largely played out across most regions, limiting scope for further immediate increases. Seasonal slowdown in construction activity during the monsoon is expected to continue affecting demand and pricing in the coming months.\n\nCentrum indicated that pricing pressure is likely to persist through the second quarter of FY27 as monsoon-related softness continues. Dealers remain cautious about sustainability of any price rise attempts and do not rule out further weakness during the peak monsoon period. The combination of subdued demand and seasonal factors is likely to constrain the industry’s ability to raise prices in the near term. While June saw some improvement in volumes because of delayed rains and quarter-end sales efforts, the broader demand environment remains challenging.\n\nCement companies are therefore expected to focus on maintaining current price levels rather than pursuing aggressive increases as the sector navigates weak demand and seasonal headwinds. The report suggested that unless demand conditions improve significantly, limited scope will exist for meaningful price recovery. Market participants remain watchful for any shifts in execution of infrastructure projects or construction activity that could alter the outlook.

Continue Reading

Concrete

TARIL Secures Ultra Mega Transformer Order From PGCIL

Order for manufacturing transformers to be delivered in 30 months

Published

on

By

Shares

Transformers and Rectifiers (India) Limited has received Notifications of Awards from Power Grid Corporation of India Limited (PGCIL) for multiple contracts to manufacture transformers and undertake associated works. The company submitted the disclosure to BSE and the National Stock Exchange under Regulation 30 of the SEBI Listing Regulations. The submission cited security code 532928 and trading symbol TARIL, and the filings cite the award reference and confirm execution in accordance with the terms and conditions stipulated in the notifications.

The contracts are described as an Ultra Mega Order under the company classification, indicating a value at or above Rs 10 billion (bn) on conversion. The filing identifies the contracts as domestic orders and specifies a scheduled delivery period of 30 months. The scope covers manufacturing of transformers of various ratings together with all associated work. The order size places it in the highest project classification defined in the company’s disclosure.

The disclosure states that the promoter group and group companies have no interest in the awarding entity and that the contracts do not constitute related party transactions. The company noted that the awards will be executed in the normal course of business and not fall within related party transactions. The document reiterates that the company is committed to delivering high quality products and services and has established itself as a leading manufacturer of transformers in the country over time.

Chief Financial Officer Mehul Shah authorised the filing and requested the exchanges to take the information on record, with the company providing the requisite filing reference in its submission. The company indicated that the orders will be executed as per the notifications of awards and the applicable regulatory framework. The original filing is available on the stock exchange portal at the provided link.

Continue Reading

Video Thumbnail
â–¶

    SIGN-UP FOR OUR GENERAL NEWSLETTER


    Trending News

    SUBSCRIBE TO THE NEWSLETTER

     

    Don't miss out on valuable insights and opportunities to connect with like minded professionals.

     


      This will close in 0 seconds