Many plant managers and engineers never get started with a reliability programme because the task seems so challenging. This integrated three-step process includes a System Review, Historical Review and Budget Review. Each step has multiple key components that must be considered when implementing a unit specific strategy, writes Shridhar Nambi, MD, Greenesol Power Systems.

STEP-1: SYSTEM REVIEW

Age of the unit Facilities built in the 1960s and ’70s experience damage related to the obvious number of hours of operation; however, they were designed with heavier wall thickness in both tubing and header components. As a result, these units tend to have longer life expectancies than some of the newer facilities. Facilities that were built in the 1980s pushed the limits with the do more with less approach. Tubing and headers were supplied with thinner walled components, conserving costs on construction, but ultimately reducing the service life of the critical components. Modern facilities are being constructed to adapt to the thermal cycling that has become a part of the energy culture of today and are experiencing earlier than expected failures. Many of these failures are the result of exotic materials that are being used which have not been in service long enough to know the true behavior of the material under the thermal and mechanical stresses of cycling a unit.

Design of the unit

Some boiler units clearly have inherent design flaws. Various design flaws include the placement of the burners in the furnace, how the tubing/headers are supported and/or the use of water guns or soot blowers. Understanding the inherent design flaws of a specific unit will help a company become proactive in their approach to preventative maintenance and ascertain areas to target for remaining useful life determinations.

Materials

Understanding the materials specific to a unit and recognising the inherent concerns of those materials (weld ability, resistance to elevated temperatures and pressure, heat transfer ability) will enable facilities to be more progressive in their pursuit to preventing service related damage.

STEP – 2: FAILURE ANALYSIS

The ability to identify and track the locations of a tube failure and its root cause is essential to comprehensively reducing forced outages. Once the root cause of the failure is properly identified, a long term plan can be implemented to ensure the failures/leaks have been rectified. Proper and current documentation is critical to managing failures and leaks and can be done in real-time with the use of a data management program such as the 4-SYTE System Strategy. Most common causes of failures have been seen to be stress rupture, water-side corrosion, fire-side corrosion, erosion, fatigue, The most likely failures can occur in water wall, economiser and superheater or reheater tube circuits.

Primary failure mechanisms are the processes that degrade the tube and produce a failure. Each failure mechanism may include several circumstances such as poor fuel quality, equipment malfunction or improper operation. Each would be considered a root cause since they have created the conditions for a failure mechanism to exist. Verification of the root cause is a vital activity in a failure investigation and is necessary to assure the correction of a failure problem. Secondary failure mechanisms such as adjacent tube washing or adjacent tube impact can produce a tube failure and are always a concern after an initial failure.

Modifications

At times inherent deficiencies of a unit design will be identified. As a result, the unit may undergo design modifications which can resolve the original design flaw concerns, but ultimately can create other issues such as steam flow restrictions and temperature excursions etc. Additionally, as part of the clean air initiatives currently underway, many units are being modified to burn alternative fuels. Recognising what modifications have transpired in a specific unit can lend perspective into potential side effects which may be occurring as a result of those modifications.

Replacements

As an aging plant begins to experience repeated failures, sections of tubing and other critical components will require replacement. These replaced sections will have fewer hours of operation and therefore will not need to be considered for inspection on the same schedule as original equipment within the unit. This observation is particularly unit specific and is a major basis for why a cookie-cutter approach to inspection/maintenance is ineffective and can lead to squandering of precious budget funding inspecting equipment that has not yet reached a point in its life cycle to require examination.

Operational changes

Most power generation facilities were designed on the assumption that they would be operated in a base-load mode or infrequently cycled. However, in response to local power market conditions and the terms of their power purchase agreements, many plants are now cycling their units more frequently than designers had intended. This results in greater thermal stresses, more pressure cycles, and therefore more cyclic fatigue damage and overall faster wear and degradation to the critical components due to both mechanical and corrosion processes.

As a general comment, cycling service has an adverse effect on the life expectancy of a unit. This is due to the fact that cycling results in fatigue loading (alternating cyclic stresses); whereas base load operation results in creep (sustained stresses). Depending on the severity of the stresses, and the number of cycles, fatigue loading can result in cracking, particularly at restraint locations.

Upsets

When a unit trips and is brought offline suddenly or experiences a water hammer event, an immense amount of thermal and mechanical fatigue can be introduced to the involved components. It is beneficial to understand if a unit has experienced any major upsets during its life cycle in order to determine if evaluating areas that wouldn’t normally come under the microscope is necessary. This is similarly unit specific and would be comparable to the considerations you would evaluate if you were purchasing a used car. Just as the purchaser would investigate any past maintenance troubles or collisions of the vehicle prior to purchasing, plant managers must consider the history of their units prior to determining the inspection prioritisation of their critical components.

Operational training

Often, the operators of units are responding to directives from a senior authority to bring the unit online or offline to meet the load requirements and capacity. Understanding the effects of ramping constraints in both unit commitment and economic dispatch is imperative. Operators can have a tremendous effect on the life expectancy of a unit simply by recognising the effects of proper ramp rate execution. Operators have direct control of the temperature of the unit; therefore proper unit specific training can add years to the life of the unit.

STEP – 3: DETERMINING REMAINING USEFUL LIFE

Determining the remaining useful life of critical components/tubing will allow for proper budgeting for replacements. Additionally, as systems begin to reach the end of their life cycle, more failures will inevitably begin to occur. Understanding when to cut your losses and replace sections will improve reliability. Many factors can affect the life expectancy of key components in a boiler including water chemistry, fuel type and quality, thermal cycles, materials, temperature excursions, inadequate heat transfer and flow rate. Understanding key factors associated with a specific unit that can ultimately contribute to shortening the life expectancy is paramount to predicting remaining useful life of critical components.

Prioritisation: inspection, repairs, replacement

The ability and necessity to develop a plan of action that includes prioritisation for inspection, repairs and/or replacements established from the unit specific design and historical operation will dramatically improve the budgetary process. Allotted funds will be used in an effective manner and outage planners will have the ability to provide back- up documentation required to warrant the necessity for such funding during the company fiscal budget planning process.

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Concrete

Cement Makers Reaffirm Commitment to Sustainable Growth

Published

on

By

Shares

World Environment Day spotlight on innovation and circularity

On World Environment Day, the Indian cement industry reiterated its commitment to supporting India’s climate ambitions through sustainable manufacturing, resource efficiency and the adoption of cleaner technologies.

The Cement Manufacturers’ Association (CMA) said the sector remains aligned with the Government of India’s Net Zero commitments and is accelerating efforts to reduce its environmental footprint while supporting the country’s infrastructure and development agenda.

Parth Jindal, President, CMA and Managing Director, JSW Cement, said the industry is increasingly adopting cleaner technologies, improving energy efficiency and expanding the use of alternative fuels and raw materials. He also highlighted the growing importance of circular economy practices, where industrial by-products and waste streams from one sector are utilised as resources in another.

“The Indian Cement Industry is aligned to the Government’s commitments on carbon mitigation and is accelerating the adoption of cleaner technologies, resource efficiency and circular economy practices while actively exploring the potential of Carbon Capture, Utilisation and Storage (CCUS) as a critical pathway for deep decarbonisation,” said Jindal.

He added that coprocessing industrial waste and by-products helps conserve natural resources, reduce disposal requirements and lower the environmental footprint across multiple sectors.

According to Jindal, sustainability is no longer limited to manufacturing processes but is increasingly influencing investment decisions, innovation strategies and long-term growth plans within the industry.

Echoing similar views, Dr Raghavpat Singhania, Vice President, CMA and Managing Director, JK Cement, said sustainable development extends beyond emissions reduction and must also focus on responsible resource utilisation and waste minimisation.

“Sustainability in the built environment cannot be measured by emissions alone. It is equally about how efficiently we use resources, how effectively we minimise waste and how responsibly we create the infrastructure that will serve future generations,” said Singhania.

He noted that the cement industry is advancing its sustainability agenda through greater resource efficiency, increased circularity, technological innovation and continuous improvements in manufacturing practices. As a key contributor to India’s infrastructure development, the sector has a critical role to play in balancing economic growth with environmental responsibility.

On the occasion of World Environment Day, industry leaders reaffirmed their commitment to supporting India’s climate goals while delivering the materials required for resilient, durable and sustainable infrastructure.

 

Continue Reading

Concrete

Building a Greener Future Together

Published

on

By

Shares

Environmental sustainability requires immediate action, not just long-term commitments and discussions. Recycling, circular economy practices, and technology-driven waste management can help industries reduce environmental impact while supporting sustainable growth.

Author: Jignesh Kundaria, Director and CEO, Fornnax Technology

World Environment Day serves as an important reminder that environmental sustainability can no longer remain confined to discussions, reports, or long-term commitments. The environmental challenges facing the world today demand immediate, measurable, and collective action. Across industries and communities, waste generation continues to outpace our ability to process it responsibly, placing increasing pressure on ecosystems, natural resources, public health, and the well-being of future generations.

One of the most significant shifts required today is a change in how society perceives waste. Rather than being viewed as a material to be discarded, waste must be recognised as a valuable resource that can contribute to both economic growth and environmental protection when managed through the right technologies and systems. This mindset forms the foundation of the circular economy model that countries across the world are increasingly adopting to reduce landfill dependence, recover valuable materials, and create more sustainable industrial ecosystems.

India has made meaningful progress in strengthening awareness around sustainability, recycling, and environmental responsibility over the past decade. Significant efforts are being made to formalise the recycling sector through improved infrastructure, technology adoption, policy implementation, and broader stakeholder participation. These developments are creating a stronger foundation for responsible waste management and resource recovery across the country.

However, achieving long-term environmental impact requires collaboration from all stakeholders. Industries, policymakers, technology providers, and communities must work together with greater accountability to strengthen recycling ecosystems, encourage responsible waste management practices, and create sustainable outcomes through consistent execution rather than temporary interventions.

As someone closely associated with the recycling industry, I firmly believe that technology will play a decisive role in addressing future environmental challenges. Advanced recycling systems have the potential to recover valuable resources, reduce pollution, minimise landfill burdens, and conserve energy, creating a more sustainable future for generations to come. This belief is deeply reflected in Fornnax’s motto, “Committed to Create a Green Future,” which embodies our commitment to building long-term environmental value through innovation and responsible action.

At the same time, technology alone cannot deliver meaningful change. Real progress requires intent, awareness, participation, and a shared sense of responsibility. Sustainable development can only be achieved when innovation is supported by collective action and a genuine commitment to environmental stewardship.

On this World Environment Day, let us move beyond conversations and take meaningful steps towards creating a cleaner, greener, and more sustainable planet. By embracing innovation, strengthening recycling ecosystems, and acting responsibly today, we can create lasting environmental impact and secure a better future for generations to come.

Continue Reading

Concrete

Dalmia Bharat Acquires Jaiprakash Associates Cement Assets for ₹2,850 Crore

Published

on

By

Shares

Dalmia Cement executed a Business Transfer Agreement with Jaiprakash Associates and Adani Infra, to acquire 5.2 MnTPA of cement capacity across Madhya Pradesh and Uttar Pradesh.

Dalmia Cement (Bharat) announced on May 22, 2026 that it had signed a Business Transfer Agreement with Jaiprakash Associates Limited and Adani Infra (India) Limited for the acquisition of cement plants located at Rewa in Madhya Pradesh and Churk, Chunar and Sadwa in Uttar Pradesh. The deal was struck at an enterprise value of ₹2,850 crore and is expected to close within two weeks of execution.

The acquired assets from Jaiprakash Associates include 5.2 MnTPA of cement capacity and 3.3 MnTPA of clinker capacity. The package also covers 99 MW of thermal power capacity and railway sidings at Rewa, Chunar, and a common siding at Churk. This infrastructure gives the acquisition immediate operational utility beyond just production tonnage.

The transaction has a long backstory. Dalmia Cement had originally entered into a framework agreement with Jaiprakash Associates in December 2022, covering the sale of these business assets along with a long-term clinker supply arrangement. However, before the deal could be completed, Jaiprakash Associates was admitted to insolvency proceedings under the Insolvency and Bankruptcy Code. The earlier agreements could not be consummated as a result.

In an official statement, Puneet Dalmia, Managing Director & CEO, Dalmia Bharat, said, “I am very excited about addition of these assets in our portfolio. This serves as a great strategic fit for Dalmia. It helps us move forward in our journey to be a pan India player and provide a strong head start to serve the high potential markets in Central region. I am optimistic that the expansion potential of these assets along with close proximity with Dalmia’s captive mines will help us create a capacity hub for the future”.

Following the approval of Adani Group’s resolution plan for Jaiprakash Associates under the IBC framework, Dalmia approached the new management to revive discussions. The fresh Business Transfer Agreement was executed to settle all pending disputes, legal proceedings, and arbitration matters arising from the original framework agreement with Jaiprakash Associates.

Expanding market reach

Dalmia added, “Our familiarity with these assets under the earlier tolling arrangement gives us a deep understanding of the facilities and helps us establish strong connect with channel partners and vendors. We believe that this will help us in faster ramp up of capacities and quicker inroads into the market. As we look forward, I am very confident that we will be able to leverage the strengths of Dalmia to operate these assets in a manner where we can maximise value creation for all our stakeholders.”

With the addition of these plants, Dalmia Bharat’s total installed cement capacity will rise to 54.7 MnTPA upon consummation. The company has further expansion projects underway at Belgaum, Pune, and Kadapa, which are expected to take overall capacity to 66.7 MnTPA by Q2 to Q3 FY28.

The Central India location of the Jaiprakash Associates plants gives Dalmia Bharat faster access to markets in Madhya Pradesh and Uttar Pradesh than a greenfield build would have allowed. The company also cited debottlenecking and brownfield expansion as near-term opportunities at the acquired sites. Dalmia Bharat said the assets were expected to contribute positively to EBITDA and overall returns, given the pricing environment in the region and the company’s cost structure.

Continue Reading

Video Thumbnail

    SIGN-UP FOR OUR GENERAL NEWSLETTER


    Trending News