Maximising Kiln Potential through KHD’s Unique Upgradation Concepts

Published

on

Shares

Turnaround story of Dalmia Cement, Kalyanpur Works (DDSPL)

Mr. S. K. Gupta†, Executive Director – Projects
† Dalmia Cement Bharat Limited

Mr. A. K. Dembla††, President & Managing Director
Mr. Sitaram Sharma††, Director – Parts & Services
†† Humboldt Wedag India Pvt. Ltd.

  1. Introduction:
    India is the second largest cement producer in the world and accounts for over 7 per cent of the global installed capacity. We are witnessing a consistent increase in cement capacity demand over the years. The Indian cement industry has made remarkable strides in technological upgradation and assimilation of latest technology. Presently, more than 98 per cent of the total capacity in the industry is based on modern and environmental friendly process technologies. The appetite for continuous modernisation and technological upgradation with state-of-the-art solutions is on upward trend to achieve enhanced productivity, improved energy efficiency, environmental and quality standards. The installed capacity of Indian cement industry is expected to reach 550-600 million tonnes per annum (MTPA) by 2025.
    Apart from building new production lines to increase the capacity, there is enormous scope for upgradation and modernisation of existing set-ups. Utilisation of existing kiln to its maximum potential is an art. This concept not only enhances clinker production but also significantly contributes in improving the overall operational efficiency.
    The reduced thermal and electrical energy demands will aid in reducing the carbon footprint of existing plants.
    To cater market demands in this area, KHD, a pioneer in this field offers extensive modernisation solutions which includes PH cyclones modification, optimised dip tubes, suitable riser ducts, high efficiency top cyclones, new generation clinker cooler, cooler plates, state-of-art Low NOx-AF calciner solutions etc. in Pyro section and latest generation separators, milling parts etc. in Grinding section. KHD’s experience in this area is unparalleled and hence established as one of the leading technological solution provider to modernize existing cement plants.
  2. Background:
    Dalmia Cement (Bharat) Limited (DCBL), one of the top 5 cement producers in India, has acquired Kalyanpur Cements under the subsidiary name DDSPL in 2018. Within short period after takeover, DCBL has set an immediate target to enhance the clinker production. As the plant was originally supplied by KHD in 80’s, DCBL has approached KHD for the revamping of existing Pyroprocess and Raw material grinding sections and subsequently awarded a contract to complete the machinery supplies within 7 months on EP basis.
  3. Snapshot of Plant Performance before modification:
    Before the takeover of DCBL, the Kalyanpur Cements was almost locked-down without active clinker and cement production to market. However, DCBL has restarted the plant after takeover.
    Subsequently DCBL has asked KHD to audit the plant to identify debottlenecking areas in both Raw grinding and Pyroprocess systems with prime target to enhance clinker production and further possibilities of improving energy efficiency.
    KHD’s technical audit team has performed a
    detailed plant audit and established following operating parameters for Pyroprocess and Raw grinding systems.
  4. Implementation of KHD’s Modernisation solutions:
    Looking in to the debottlenecking areas identified after the detailed plant audit study, KHD has proposed and implemented the following modifications.

PYROPROCESS SYSTEM:
Taking in to account the existing kiln size and its maximum potential and also considering the layout feasibility in upstream and downstream sections such as Preheater and Cooler sections, the following modifications were proposed and subsequently implemented after several rounds of technical deliberations with DCBL team.

  • Kiln feed section has been modified partially to cater the capacity requirement of Preheater section. As part of modification, blending silo extraction gates were replaced with higher capacity and new bucket elevator is installed to feed material from silo bottom to kiln feed bin which is configured in Preheater building. Necessary modifications in material handling equipment such as Air slide etc. are incorporated.
  • In preheater, the existing top cyclones were replaced with bigger size latest design twin cyclones keeping in view the capacity enhancement requirement and also to improve the overall collection efficiency of PH system.
  • A new bigger In-Line Calciner (PYROCLON-R with PYROTOP) is installed outside the PH building as shown in 3D drawing to increase the retention time at enhanced clinker production and also to take care of solid AF utilisation
  • in future.
  • KHD’s tubular calciner design aptly suitable for solid AF utilisation due to sufficient velocities, high retention time and good mixing of tertiary air in to gases from kiln stream. Besides the retention time in the calciner, turbulence is the most important criterion for assuring good fuel conversion. To create turbulence, the PYROCLON® calciner is equipped with the so-called PYROTOP® compact. This compact mixing chamber is installed at the reversal point of the calciner and ensures that there is perfect mixing at this point between the residual oxygen, the burning particles, pre-calcined meal and the waste gas. Theoretical studies and practical experience from converted plants prove the effectiveness of this mixing in, achieving better burnout and correspondingly lower CO emissions.
  • KHD’s latest generation PYROBOX® calciner firing system is also installed for improved calcination. The PYROBOX® is a sturdy and simple solution for the combustion of pulverised or granular fuels like coal dust, petcoke or dried sewage sludge. The PYROBOX® enables a pre-mixture of fuel and meal. This ensures fast ignition on the hot material, direct heat transfer and therefore a more even heat profile in the calciner with benefits regarding improved combustion and refractory service time will be achieved. The special design of the PYROBOX® burners requires no additional primary air.
  • In addition, custom made solutions such as new optimised dip tubes (immersion pipes with improved geometry), PH cyclones inlet area & height increase, raw meal pipes diameter increase along with compensators and flaps, meal inlet boxes with splash plates, kiln riser modification etc. are implemented considering plant specific conditions.
  • A new bigger PH fan of suitable specifications is also installed with motor and VFD to take care of enhanced clinker production.
  • To increase kiln speed, a new kiln main gearbox is also installed with suitable reduction ratio. The suitability of kiln critical components has been checked for
  • higher clinker production through detailed stress analysis matrix.
  • By retaining the outer skeleton of existing grate cooler housing the complete moving grate has been replaced with new generation cooler plates along with new fans of adequate capacity.
  • Fine coal dosing system is suitably upgraded with latest generation weighing & dosing systems (Coriolis feeders) for both kiln as well as calciner firing applications.

RAW MATERIAL GRINDING SYSTEM:
As the existing raw material grinding capacity is not adequate, following modifications are implemented to enhance the raw grinding capacity to cater the requirement of Pyroprocess system.

  • Existing Roller Press (RP) speed has been increased from 1.4 m/s to 1.6 m/s by installing bigger motors of 2 x 900 kW. Also, existing RP hydraulics and ROLCOX® software are upgraded.
  • New V-separator (static) for primary classification and drying purposes, and SKS-separator (dynamic) for final product classification are integrated with existing roller press in finish mode.
  • For close circuiting of above machines, new bucket elevators are installed for handling and recirculation of V-separator and Roller press discharge material.
  • Two set product collection cyclones are installed along with one SKS circulating fan.
  • To handle increased gas volume requirement, the existing kiln bag house (BH) was upgraded to 361,000 m3/h and new bigger BH fan of 420,000 m3/h @ 40 mbar is installed.
  1. Performance after upgradation:
    After implementation of above proposed modifications in meticulous manner, the overall performance of the plant is very much satisfactory and all the performance guarantees for both the sections have been achieved successfully. The snapshot of performance guarantee (PG) test results are summarised in below table.
    All the performance parameters guaranteed as per contract are successfully demonstrated for specified PG test duration.
    For KHD, it’s an immense pleasure to successfully revamp an old plant installed almost 35 years ago and to establish all the performance parameters which are quite close to the modern plants.
    This success story is a perfect example on how an old plant can still be modernised subject to layout feasibility, with marginal capital expenditure to enhance productivity and also improve
    energy efficiency.
  2. Conclusion:
    The scope for utilisation of existing equipment to its full potential is an area which can enhance not only the production but also provides additional benefits in terms of improvement in operational efficiency. KHD through its unique and customised modernisation solutions can improve the existing system productivity. The capacity enhancement by this concept will not only reduce the capital expenditure per ton of clinker produced but benefits can be materialised much earlier than an independent green field project. KHD as your partner is
    always willing to extend support in modernising existing plants with state-of-art, environmental friendly technologies.

Gist of tangible gains achieved in Pyroprocess system after upgradation:

  • Production increase of around 61 per cent from base line value.
  • Specific heat consumption reduction by more than 100 kcal/kg clinker.
  • Approx. 2.8 kWh/t cli saving in specific power consumption.
  • Significant NOx reduction after conversion to PYROCLON® R type calciner

Gist of tangible gains achieved in Raw grinding system after upgradation:

  • Production increase of around 68 per cent from base line value.
  • 1.34 kWh/t raw meal saving in specific power consumption.

(Communication by the management of the company)

Concrete

Lokesh Lays Stone For Rs 31 Billion Cement Unit In Kadapa

Line-2 expansion to make Kadapa a major cement hub

Published

on

By

Shares



Andhra Pradesh Education and IT Minister Nara Lokesh on Wednesday laid the foundation stone for the Line-2 expansion of Dalmia Bharat Cement at Chinnakomerla village in Mylavaram Mandal in Kadapa district. The project carries an investment of Rs 31 billion (bn) and is slated for completion by the third quarter of the financial year 2028. The expansion is intended to boost industrial growth and employment generation across the Rayalaseema region.

Once commissioned, the Kadapa facility will become Dalmia Bharat’s largest integrated cement manufacturing ecosystem in southern India, creating over 1,000 direct and indirect jobs and opening new business avenues for regional micro, small and medium enterprises and transport operators. Lokesh said the expansion signalled growing corporate confidence in the state and reflected the practical ease of doing business that secured repeat investment.

He placed the project within the government’s wider economic targets and recalled the Yuvagalam padayatra commitment to generate two million (mn) jobs within five years, noting that the state would cultivate talent while industry created opportunities. Lokesh highlighted Andhra Pradesh’s competitive pursuit of major manufacturing accounts, mentioning past successes and a personal initiative to engage global investors when persuading them to anchor expansion in the state.

The plant will leverage Kadapa’s abundant limestone reserves to scale production and sustainability. Clinker capacity is planned to rise from two point five million tonnes per annum (mn tpa) to six point one mn tpa, while overall cement output will increase from three point six mn tpa to nine point six mn tpa. The unit is designed to operate on over eighty per cent renewable energy and deploy waste heat recovery, zero liquid discharge, water recycling and advanced AI systems to optimise efficiency. Industries Minister TG Bharat, BC Welfare Minister S. Savitha and Jammalamadugu MLA C. Adinarayana Reddy attended the ceremony.

Continue Reading

Concrete

Cement Prices to Stay Flat in Q2 FY27 as Costs Squeeze Margins

HDFC Securities warns monsoon slowdown and higher fuel costs

Published

on

By

Shares



HDFC Securities has said the cement industry is unlikely to register a sequential increase in prices in Q2 FY27 as monsoon-related demand moderation coincides with rising fuel and packaging costs that will squeeze margins. The brokerage observed that price gains remained modest, with increases of two to three per cent quarter-on-quarter across regions, and noted subdued offtake in May with improvement in June as a delayed monsoon supported construction activity. The brokerage added that modest pricing gains so far have been insufficient to offset the input cost escalation.

The report stated that input cost pressures intensified in Q1 FY27 owing to the West Asia conflict, which pushed up coal and pet coke prices and is expected to keep fuel costs elevated, with a likely peak in Q2 FY27. It assessed that total variable costs, including packing, could rise by around Rs 150 per t quarter-on-quarter and that lower offtake and seasonal operating deleverage could further raise operating expenditure by about Rs 50 per t quarter-on-quarter.

Overall, cement prices were estimated to remain flat in Q2 FY27 as monsoon-led demand weakness offsets limited upside in realisation, and rising fuel costs alongside seasonal deleverage were expected to compress industry margins by over Rs 100 per t quarter-on-quarter to below Rs 880 per t. The brokerage indicated that the combined impact of energy inflation and higher packing expenditure would be the principal drivers of margin contraction in the near term. HDFC Securities projected a recovery in margins in H2 FY27 should the West Asia turmoil subside and energy and packing costs cool off.

The brokerage expressed optimism on long-term demand fundamentals and said improving realisation together with an anticipated cost cool-off should support a margin rebound from H2 FY27 onward, underpinning favourable industry prospects over the medium term. Its outlook rests on monsoon normalisation and a decline in imported fuel prices in the second half of the fiscal year.

Continue Reading

Concrete

Dalmia Bharat Begins Rs 31 Bn Green Cement Unit in Kadapa

New Andhra Pradesh plant to add 9.6 MTPA cement capacity by FY28

Published

on

By

Shares



Dalmia Bharat Limited recently laid the foundation stone for its second manufacturing unit at Kadapa in Andhra Pradesh. The company will invest Rs 31 billion in developing the next-generation integrated cement manufacturing facility.
The foundation-laying ceremony was attended by Nara Lokesh, Andhra Pradesh Minister for Information Technology, Electronics and Communications, Real-Time Governance and Human Resources Development, along with Puneet Dalmia, Managing Director and Chief Executive Officer, Dalmia Bharat, senior government officials and company representatives.
Scheduled to be commissioned by the third quarter of FY28, the Kadapa unit will become Dalmia Bharat’s largest integrated manufacturing facility in southern India. It will have a clinker production capacity of 6.1 million tonnes per annum and a cement manufacturing capacity of 9.6 million tonnes per annum.
The facility is designed to produce what the company describes as one of the world’s greenest cements. It is also expected to generate approximately 1,000 direct and indirect employment opportunities while supporting local MSMEs, transporters, contractors and service providers.
Lokesh said the investment reflected Dalmia Bharat’s confidence in Andhra Pradesh and aligned with the state’s objective of promoting sustainable industrialisation, job creation and technology-led economic growth.
Puneet Dalmia said the project represented the company’s long-term vision of developing low-carbon cement manufacturing assets. He added that the facility would establish new benchmarks in operational efficiency and sustainability while supporting India’s infrastructure and environmental goals.
Dalmia Bharat will also expand its regional community development programmes in education, healthcare, skill development and welfare through its DIKSHa and Gram Parivartan initiatives.
The company currently has an installed cement manufacturing capacity of 54.7 million tonnes across 19 manufacturing units in 12 states. It is also the first cement company globally to commit to the RE100, EP100 and EV100 initiatives.

Continue Reading

Video Thumbnail

    SIGN-UP FOR OUR GENERAL NEWSLETTER


    Trending News

    SUBSCRIBE TO THE NEWSLETTER

     

    Don't miss out on valuable insights and opportunities to connect with like minded professionals.

     


      This will close in 0 seconds