Connect with us

Concrete

Emerging trends in precast is indicative of way forward

Published

on

Shares

Prashant Jha, Chief RMX, Nuvoco Vistas

What are the emerging trends in precast?
Depending on the load-bearing structure of the building, some of the emerging trends in precast systems are:
Large-panel systems: The designation "large-panel system" refers to multistory structures composed of large wall and floor concrete panels connected in the vertical and horizontal directions so that the wall panels enclose appropriate spaces for the rooms within a building.

Frame systems: Precast frames can be constructed using either linear elements or spatial beam-column sub-assemblages. Precast beam-column sub-assemblages have the advantage that the connecting faces between the sub-assemblages can be placed away from the critical frame regions; however, linear elements are generally preferred because of the difficulties associated with forming, handling, and erecting spatial elements.

Slab-column systems with shear walls: These systems rely on shear walls to sustain lateral load effects, whereas the slab-column structure resists mainly gravity loads. There are two main systems in this category:

  • Lift-slab system with walls
  • Prestressed slab-column system

Modular system: In case of smaller single units, this system is helpful. Some of the advantages are;

  • Entire unit is cast in a factory and installed at site.
  • Suitable for toilet blocks or individual rooms
  • Monolithic casting guarantees waterproofing at junctions

In precast, which segment do you cater to the most?
Nuvoco has contributed and provided solutions to the Infrastructure, mainly Mass Rapid Transit System such as the Noida Metro and the Mumbai Metro projects.

Noida metro project: Nuvoco supplied 243,700 CuM of concrete for Noida Metro, for its NC 01 -elevated viaduct and 8 elevated stations, and NC 02 – elevated viaduct and 7 elevated stations. 3 dedicated captive plants were set up for the project with a concrete output of 250 CuM/hr, with one plant for the casting of U girders. The main challenges included on time productivity, de-shuttering and lifting of the precast modules, controlling the temperature and shrinkage, and aesthetic finish. Each of the girders were with the specification of 5 m wide, 27 m long, with a height of 1.8 m, a thickness of 150 – 200mm, and a volume of 50 – 60 CuM. This was pre-stressed, using 52 to 109 cables as per design. Nuvoco used its high performance early strength concrete, Robuste, of M55 Grade, for the project, ensuring the U Girders achieved a strength of 12 – 14 Mpa at 12 hrs for early de-shuttering. As a result, it successfully erected 200 U-shaped girders in May 2016.

Mumbai metro project: The Mumbai Metro Line – 3, connecting Cuffe Parade to SEEPZ, with 26 underground stations and one at-grade station. The requirement was for package 4, that comprised the three underground stations. Nuvoco set up a captive plant at the site, along with a transit mixer, for the production of 2,48,000 CuM of concrete. This was used for the construction of 6082 m twin bored tunnels with a diameter of 5.80 m. The tunnel sections are 1.4 m long, 1 m wide, and 275 mm in height, with a volume of 1.4 m3. Precast was used to provide a protective lining and reinforcement to the structure. The primary challenge was supplying high early strength concrete of 12 Mpa at 12 hrs without steam curing for de-shuttering. Insert. The project also needed to ensure extremely low Chloride penetration and migration to offer a service life of 150 Years, along with controlled shrinkage, and a customised aesthetic finish. Nuvoco has been able to address these needs by using a combination of two of its products, Instante and Robuste, of M50 Grade.

The industry took a leap with smart products in cement. Can you elaborate on the smart product portfolio of Nuvoco?
Nuvoco’s offers 14 ready-mix concrete products and their variants. They can be customised to suit any specific construction need and provide multiple benefits. Our concrete flagship brands encompass:

  • Agile, the self-compacting and self-consolidating concrete with a high-quality surface finish
  • Artiste, a range of decorative concrete that combines freedom of design with low maintenance and high durability.
  • Xlite, the low-density concrete that reduces structural weight and lowers thermal conductivity.
  • InstaMix, our ready-to-use bagged concrete and mortar offerings are designed to deliver cost-effective, easy-to-use construction solution in any location.

– RENJINI LIZA VARGHESE

Quote from Dalmia Cement for World Environment Day

Mahendra Singhi, MD & CEO, Dalmia Cement Bharat Limited, who is best known for being an avid advocate of sustainability, said, "The recent crisis, which impacted the entire world, has brought several dramatic changes to the environment from the past two months with a steep fall in global carbon emissions. We have to now explore how – as per our conscious low consumption practices – we can ensure that this reduction is not transient but results in low carbon economy. This crisis has further made all of us to realise that nature is a source of solace, an inspiration, and a teacher and the utmost need to protect it. This Environment Day, let us all come together and commit ourselves to simplest lifestyles as nature tends to act in the simplest way. I believe we still have the opportunity to reshape and redesign our world in a more. Sustainable way and I urge all global players, to not only work towards creating a greener environment, but also healthy lifestyles for all."

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Concrete

30-Day Traffic Diversion In Place For CC Road Works In Madhapur

Diversions in place from May 16 for cement concrete road works

Published

on

By

Shares

The Cyberabad Traffic Police issued a traffic advisory as road works begin for the laying of a cement concrete (CC) road from Jaya Shankar Statue to RRR Restaurant at Parvathnagar in Madhapur limits. The advisory indicated that traffic diversions will be in place for 30 days from May 16 to ensure the smooth flow of vehicles and to minimise congestion on the affected stretch. The measure aims to balance uninterrupted construction activity with the movement needs of commuters.

Traffic moving from Toddy Compound towards Parvathnagar village will be diverted at Parvathnagar junction towards Sunnam Cheruvu and the 100 feet road. Local motorists and public transport operators have been advised to follow the diversionary route as directed by traffic personnel on duty. Alternate routes and signage have been planned to mitigate delays and to manage peak hour congestion.

Police officials said the diversion had been planned to facilitate uninterrupted road works while maintaining traffic movement in the area. Commuters were urged to plan their travel accordingly and to cooperate with traffic staff managing the stretch. Authorities indicated that enforcement of diversions would be active and that violations could attract penalties.

The 30 day schedule is intended to allow contractors to complete the laying and curing phases with minimal interruption to vehicular flow. Residents and businesses in adjacent localities have been advised to factor the diversion into deliveries and travel plans. The traffic police promised continuous monitoring of the works and the operational diversions and emphasised that temporary inconvenience was necessary for longer term improvement of the road network. Traffic personnel will be stationed at key junctions and additional signage and temporary markings will be displayed to guide motorists and pedestrians through the revised alignments while public transport services will follow the diversion where feasible and operators have been asked to adjust timetables to minimise disruption.

Continue Reading

Concrete

HeidelbergCement India Receives Consent For Khandwa Grinding Unit

Consent granted by Madhya Pradesh Pollution Control Board

Published

on

By

Shares

HeidelbergCement India (HeidelbergCement India) has received regulatory consent to establish a cement blending and grinding unit at Village Dongaliya, Tehsil Punasa, District Khandwa in Madhya Pradesh. The consent was granted by the Madhya Pradesh Pollution Control Board under the Water (Prevention & Control of Pollution) Act, 1974 and the Air (Prevention & Control of Pollution) Act, 1981 and is dated 17 May 2026. The company disclosed the development in a filing made under Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015.

The project plan envisages procurement of long term availability of fly ash and the allotment of land on lease for setting up the unit. The proposed facility is described as a blending and grinding installation which will process cementitious materials sourced from nearby operations and suppliers. Company filings state the measures required to secure raw material logistics and statutory compliance before commencing construction.

The addition of a grinding unit in Khandwa is intended to strengthen regional supply and improve logistical efficiency by reducing haulage distances for finished product. The unit is expected to complement existing capacities in central India and to offer flexibility in product mix through blending operations. The reliance on fly ash as a supplementary cementitious material will necessitate long term supply agreements with thermal power producers and coordination with waste utilisation policies.

The disclosure to the regulator and to the stock exchanges follows standard corporate governance practice and aims to keep investors apprised of capital expenditure initiatives. The company indicated that subsequent permits and clearances would be sought in accordance with applicable environmental and land use rules. The project is presented as part of HeidelbergCement India’s broader strategy to optimise capacity distribution and to respond to regional demand dynamics.

Continue Reading

Concrete

PROMECON introduces infrared-based tertiary air measurement system for cement kilns

Published

on

By

Shares

The new solution promisescontinuous, real-time tertiary air flow measurement in cement plant operations.

PROMECON GmbH has launched the McON IR Compact, an infrared-based measuring system designed to deliver continuous, real-time tertiary air flow measurement in cement plant operations. The system addresses the longstanding process control challenge of accurate tertiary air monitoring under extreme kiln conditions. It uses patented infrared time-of-flight measurement technology that operates without calibration or maintenance intervention.

Precise tertiary air measurement is a critical requirement for stable rotary kiln operation. The McON IR Compact is engineered to function reliably at temperatures up to 1,200°C and in the presence of abrasive clinker dust. Its vector-based digital measurement architecture ensures that readings remain unaffected by swirl, dust deposits or drift. Due to these conditions conventional measurement systems in pyroprocess environments are often compromised.

The system is fully non-intrusive and requires no K-factors, recalibration or periodic readjustment, enabling years of uninterrupted operation. This design directly supports plant availability and reduces the maintenance overhead typically associated with process instrumentation in high-temperature zones.

PROMECON has deployed the McON IR Compact at multiple cement facilities, including Warta Cement in Poland. Plant operators report that the system has aided in identifying blockages, optimising purging cycles for gas burners, and supplying accurate flow data for AI-based process optimisation programmes. The practical outcomes include more stable kiln operation, improved process control, and earlier detection of process disturbances.

On the energy side, real-time tertiary air data enables reduction in induced draft fan load and helps flatten process oscillations across the pyroprocess. This translates to lower fuel and energy consumption, fewer unplanned shutdowns, and a measurable reduction in NOx peaks. This directly reflects on the downstream cost implications for plants operating SCR or SNCR systems for emissions compliance.

Continue Reading

Video Thumbnail
â–¶

    SIGN-UP FOR OUR GENERAL NEWSLETTER


    Trending News

    SUBSCRIBE TO THE NEWSLETTER

     

    Don't miss out on valuable insights and opportunities to connect with like minded professionals.

     


      This will close in 0 seconds