The Atal Tunnel in Himachal Pradesh was inaugurated by Prime Minister Narendra Modi last year on October 3. The 9.02 km tunnel is the world?? longest road tunnel at an altitude of 3,000 m (10,000 ft) above sea level. Passing under the Rohtang Pass in the eastern Pir Panjal range, it connects Manali with Lahaul and Spiti valley, and subsequently with Leh, throughout the year. It has reduced the distance by 46 km and travel time by five hours.

The Atal Tunnel was envisaged in 1983 by the Government of India to provide all-weather connectivity between Manali and Leh. In 2002, then Prime Minister Atal Bihari Vajpayee declared the construction of Rohtang Tunnel and laid the foundation of the approach road to the tunnel. The Border Roads Organisation (BRO) subsequently engaged RITES the same year to undertake studies. The contract was finally awarded to Strabag-Afcons JV (SAJV) in September 2009.

The Atal Tunnel is horseshoe shaped, with a single tube and two lanes. It boasts many firsts, including the deployment of the Rowa Conveyor System.

Working at inverted levels

The Rowa Conveyor System was deployed to facilitate working at inverted levels. This offered various advantages, as Sunil Tyagi, Project Manager, Atal Tunnel Project, lists:

  • Activities were carried out side by side without hampering other activities in the tunnel with due care to manpower safety.

  • Unnecessary transportation of muck for dumping was eliminated and generation of harmful gases in the tunnel reduced.

  • Shifting the muck on the conveyor belt from the inbuilt crusher to the outside of the tunnel helped reduce the number of machines, equipment and transport, lowering vehicle pollution. This provided clean and healthy conditions in the tunnel for workers.

  • The time cycle of all activities was reduced, so the workers spent less time inside the tunnel.

  • Precast members were placed using an EOT crane mounted on Rowa.

Point of escape

This is one of the few tunnels in the world, and the first in India, that has been built with an emergency escape below the pavement level. The clear dimensions of the escape tunnel are 3.6 m ? 2.2 m.

Having the emergency escape tunnel within the main tunnel eliminated the need to build an additional, parallel escape tunnel. ??n the Atal Tunnel, passages have been provided to access the escape tunnel at every 500 m, where a stairway leads to the escape route,??shares Tyagi. ??n times of any adversity in the main tunnel, this escape tunnel can be used by personnel to evacuate people.

Drill and blast

The New Austrian Tunnelling Method (NATM) was adopted during excavation. As Tyagi says, ??his method was useful in complex and diverse geological conditions, where forecasting of the rock mass was difficult owing to the rapidly changing geology.??He adds that in this method, the surrounding soil or rock mass of tunnel is integrated into the overall support structure, and the rock is activated to a load-bearing ring around the tunnel. Every deformation of the excavation is measured.

NATM requires the installation of sophisticated measurement instrumentation that is embedded in the excavated surface, such as optical targets, load cells and multipoint borehole extensometers. As NATM is based on monitoring measurements, changes in the support and construction method are possible during the execution phase.

The challenge

There were several challenges faced during the construction of the tunnel. Heading excavation through the Seri Nalla Zone was the biggest one. ??lthough the Nalla we encountered was of a mere length of 526 m, the excavation took around four years to complete,??reveals Tyagi. ??he project team put their energies into getting over this stretch during heading operations, as successful execution of the tunnel was totally dependent on its excavation.??/p>

Seri Nalla consisted of a sheared, weathered rock mass, mostly river-borne material with heavy water ingress, as high as 127 litre per sec. The face of the tunnel literally used to flow like a river of mud and boulders. Securing the face under these circumstances and excavating further was a huge task. ??he brave and skilled efforts of our workforce helped overcome this extremely challenging geology,??he adds.

Successful execution of the Seri Nalla heading boosted the morale of the execution team and ??hereafter, we were able to excavate the tunnel in the heading drive at a much accelerated speed,??says Tyagi. The maximum heading achieved in a month after completion of Seri Nalla was 217 m.

Surviving the pandemic

Construction commenced in 2010, and the Atal Tunnel was launched in 2020. The question remains: How did the project survive the pandemic months? One of the significant challenges faced during the pandemic was availability of raw materials at site. Cement and steel factories were closed in the lockdown, thus limiting supplies substantially. ??ontinuous discussions were held with the management of these factories to start the required production, so that our demands could be met,??says Tyagi. ??e are grateful for a favourable response from them, which certainly helped achieve project timelines as per schedule.??/p>

The tunnel has consumed 14,508 metric tonne (mt) of steel and 237,596 mt of cement. Almost 14 lakh cu m soil and rock was excavated during construction. As the project is of immense national importance, efforts were made by all stakeholders to restart work with minimal time loss. ??e were able to get a go ahead for the commencement of project-related activities from April 2, 2020, by the local district administration on the condition that the strict COVID protocols laid down by the government shall be adhered to,??confirms Tyagi. The work was started with minimum staff and workers, and only critical works for project completion were taken up initially.

Safety first!

The unique and marvellous tunnel is the outcome of over 1,000 workmen and 150 engineers working tirelessly and efficiently in extreme weather conditions. Safety was given primary importance, which led to the achievement of more than 28 million safe man hours till the end of the project. Prescheduled training programmes were conducted during the project period; these focused on each and every activity and aspect of construction. Training was conducted even during peak working periods.

Almost every month, safety motivational sessions were conducted for workers and awards and appreciation certificates presented to further motivate them to do their best while ensuring all safety protocols and practices were followed. Hazard identification and risk assessment were carried out regularly for all activities.

Secret to success

??eamwork and integrity among staff and workers made this project successful,??says Tyagi. Working under harsh conditions, countering extreme climatic challenges ranging from harsh winters, heavy snowfall and avalanches to cloudbursts, the team did not lose hope and remained focused on the ultimate goal.

Indeed, all the young engineers who got the opportunity to work on this project have gained enormous knowledge and have become national assets. Work in the project included open excavation, underground excavation, precast concreting, cast-in-situ concreting, building works in the form of portal buildings, structural steel fabrication, ground anchoring to the tune of 4,000 kN and PQC works inside the tunnel, providing extensive experience to one and all.

Project: Atal Tunnel, Rohtang, Himachal Pradesh

Project value (civil works): Rs 26 billion

Client: Border Roads Organisation (BRO)

Contractor: Strabag-Afcons Joint Venture (SAJV)

Highest altitude (north portal): 3,017 m

Lowest altitude (south portal): 3,060 m

Tunnel type: Single-tube, double-lane, horseshoe shaped

Tunnel length: 9.02 km

Finishes width of road level: 11.4 m

Overhead clearance: 5.525 m

Tunnels: 18

Egress tunnel dimensions: 3.6 m (W) x 2.25 m (H)

Precautions for avalanche emergencies

There was a constant avalanche threat with over 20 avalanche areas surrounding the tunnel portals.

  • A rescue team was deployed at site for constant monitoring of now conditions.

  • The team provided directions and instructions for safe movement of staff and worker vehicles from Solang Valley to the site location.

  • The rescue team took care of route planning for the movement of vehicles, ensuring safe movement.

  • RICCO chips were provided to all individuals, so that in case of an avalanche the trapped person could be rescued by the sensor tracking system.

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Concrete

Dhanekula Institute Signs MoU with Adani Cement

Agreement to expand internships, industrial visits and practical learning

Published

on

By

Shares

The Department of Civil Engineering at Dhanekula Institute of Engineering & Technology, Ganguru, organised an industrial interaction programme under the Adani FutureX Programme on Thursday. The programme focused on strengthening engagement between the institute and the cement industry while giving students greater exposure to professional practices.

Yedukondalu, technical head for Andhra Pradesh and Telangana at Adani Cement, delivered a technical lecture on concrete as a man-made material. The session covered the importance of concrete in construction, its properties and applications, and its significance in modern infrastructure development.

The lecture also addressed the role of quality cement and suitable concrete technology in supporting durable and sustainable construction. The discussion connected classroom learning with the technical considerations involved in infrastructure projects and construction practices.

A key part of the programme was the signing of a memorandum of understanding (MoU) between the Department of Civil Engineering and Adani Cement under the Adani FutureX Partnership Agreement. The agreement is intended to strengthen industry-academia collaboration through opportunities for student internships and industrial visits.

The initiative is expected to provide students with practical exposure, improve their understanding of industrial practices and help bridge the gap between theoretical knowledge and real-world applications. Dhanekula Institute Chairman Dhanekula Ravindranath Tagore, Secretary Dhanekula Venkata Bhavani Prasad and Director DKRK Ravi Prasad supported the initiative, with the institute leadership highlighting the importance of industry-institution interaction in enhancing students’ technical employability.

Continue Reading

Concrete

JK Lakshmi Cement Begins Rs. 110 bn Assam Plant Project

Project Kamakshi will produce 2.5 mn t of cement annually by FY2029.

Published

on

By

Shares

JK Lakshmi Cement has laid the foundation stone for Project Kamakshi, its first integrated cement manufacturing facility in Assam, marking the company’s entry into Northeast India. The groundbreaking ceremony took place at Umrangso village in Dima Hasao district in the presence of Assam Chief Minister Himanta Biswa Sarma.

The project involves an investment of Rs. 110 bn, including the mining lease. It will have annual cement production capacity of 2.5 mn t and a 1 mn t clinkerisation unit, with completion scheduled for FY2029.

The facility is expected to create more than 2,000 jobs and will primarily serve the growing Northeast market. It will also include dedicated railway sidings for transporting raw materials and finished cement, supporting supply chain reliability and regional distribution.

Chairperson and Managing Director Vinita Singhania said the project represented the beginning of a long-term relationship with Assam and the wider Northeast. She said the plant would help provide locally produced cement, employment and dependable supplies as the region’s infrastructure development accelerated, while enabling the company to grow alongside the communities it serves.

The investment supports JK Lakshmi Cement’s strategy of expanding into high-growth markets beyond its established presence in Northern, Western and Eastern India. The company expects the project to contribute to regional economic development and infrastructure growth while pursuing its long-term objective of achieving net-zero emissions by 2047.

Continue Reading

Concrete

Kshatriya Engineering College Signs MoU with Adani Cement

Agreement to provide students with industrial exposure and training

Published

on

By

Shares

The civil engineering department of Kshatriya Engineering College in Nizamabad has signed a memorandum of understanding (MoU) with Adani Cement to provide students with industry-oriented training and practical exposure. The agreement is intended to connect classroom learning with workplace requirements in the construction sector.

Under the partnership, students will receive opportunities to take part in industrial visits and internships. The arrangement will also include guest lectures by industry experts and guidance on live projects, allowing students to gain first-hand understanding of industry practices and emerging construction technologies.

College secretary and correspondent Aljapur Devender said the initiative was designed to bridge the gap between academic instruction and industry expectations. He said the collaboration would help students develop practical skills and improve their employment prospects after completing their studies.

Principal Dr Katakam Srinivas said exposure to industrial practices was important for civil engineering students and would complement their academic learning. He said the MoU would support the development of their technical knowledge and confidence through greater familiarity with professional work environments.

Administrative officer B. Narender said the collaboration would familiarise students with modern construction technologies, quality standards and project management practices. Civil engineering department head N. Deepika said the agreement would help students understand recent developments in the construction sector and prepare for professional careers. The college said the partnership would give learners a broader view of the processes and standards followed in the industry, while helping them relate their academic studies to practical project requirements.

Continue Reading

Video Thumbnail
▶

    SIGN-UP FOR OUR GENERAL NEWSLETTER

    Trending News

    SUBSCRIBE TO THE NEWSLETTER

     

    Don't miss out on valuable insights and opportunities to connect with like minded professionals.

     


      This will close in 0 seconds