Anupam Agrawal, Senior Executive Director, Dalmia Cement; and Shailesh Agarwal, Partner, Consulting (Infrastructure Practice) EY India, present a case study of the 3.5 mtpa Dalmia Bharat Cement plant in Karnataka, demonstrating how structured planning enabled the project to achieve sustained high-volume concreting.
The ongoing 3.5 MTPA cement plant project of Dalmia Bharat Cement in Karnataka, India, has achieved a historic milestone in the Indian cement construction sector by sustaining concrete casting volumes exceeding 10,000 m3 for six consecutive months. This unprecedented achievement highlights exceptional engineering execution, disciplined project management, and effective teamwork on site.
Despite external challenges such as festive-season manpower shortages and labour migration during state elections, the project maintained consistent productivity through proactive workforce management, strong leadership presence, and resilient supply chain planning. The sustained high-performance execution enabled adherence to tight project timelines and established a new industry benchmark for large-scale industrial concreting in India.
The project represents a major cement capacity expansion, involving extensive reinforced cement concrete (RCC) works executed under stringent timeline constraints. Given the scale of the project and its strong interdependency with mechanical erection activities, the ability to sustain continuous high-volume concrete placement was identified as a critical success factor.
Traditionally, achieving concrete placement volumes exceeding 10,000 m3 in a single month is considered exceptional within the cement construction industry. Sustaining this level of output consistently over a six-month period, particularly during festival-intensive months such as October, was widely regarded as improbable. Despite these constraints, the project successfully maintained uninterrupted high-volume concreting, thereby challenging conventional productivity benchmarks.
To achieve this objective, the Dalmia Bharat project team established a robust project monitoring and control system through an internal cross-functional team, supported by a Project Management Office (PMO) framework provided by EY. This framework encompassed integrated planning and scheduling, cost control, quality assurance, procurement coordination, and systematic risk management. The structured approach ensured optimal resource utilisation, adherence to aggressive timelines, and compliance with technical and quality requirements across all work fronts.
To mitigate execution risks associated with reliance on a single contractor, the project adopted a multi-vendor execution strategy, engaging four contractors for major concrete works, with M/s Goel Construction executing the largest share of the concreting volume. This approach enhanced execution flexibility, improved productivity, and reduced schedule risk.
Key challenges
Project execution was constrained by a combination of workforce, supply chain, operational, and schedule-related challenges. The primary constraints encountered during the execution phase are summarised as follows:
• Manpower Availability (R1 & R2): The festival season in October resulted in reduced workforce availability, while concurrent state elections led to significant migration of both skilled and unskilled labour, impacting site productivity.
• Supply Chain Continuity (R3): The project was highly dependent on the uninterrupted supply of critical materials, including aggregates, reinforcement steel, formwork systems, and construction equipment. Any disruption posed a direct risk to planned concreting cycles.
• Equipment Reliability (R4): Sustained high-volume concreting operations increased the likelihood of equipment fatigue and breakdowns, necessitating enhanced maintenance planning and standby arrangements.
• Schedule Constraints (R5): The project was governed by aggressive timelines with minimal float. Any delay in civil works had the potential to adversely affect downstream mechanical erection and commissioning activities, leaving little tolerance for schedule slippage.
Risk matrix and rating
Risk Description Category Risk Level
1 Festive season manpower shortage Workforce High
2 Labour migration due to state elections Workforce High
3 Disruption in material and equipment supply Supply Chain Medium
4 Equipment breakdown due to continuous operations Operations Medium
5 Tight timelines with minimal schedule float Schedule Critical
Likelihood High R1 & R2 R5
Medium R3 & R4
Low
Impact-> Low Medium High
Strategy and execution approach
A. ‘All Boots on Ground’ leadership model
A defining element of the project execution strategy was the adoption of the ‘All Boots on Ground’ leadership model, which emphasised continuous senior leadership presence at the project site. This approach enabled real-time decision-making, accelerated issue resolution, and strong alignment across engineering, supervision, and contractor teams. The close on-site leadership engagement ensured that planning objectives were effectively translated into consistent field-level execution and performance.
B. Workforce retention and motivation strategy
To mitigate workforce availability risks arising from festive periods and state elections, a targeted manpower retention and motivation programme titled ‘Kaun Banega Lakhpati’ was implemented. The initiative successfully achieved workforce retention levels of approximately 85 per cent to 90 per cent during high-risk periods, including the month of October. The program contributed to sustained productivity, reduced labour attrition, and enhanced workforce morale and commitment during peak execution phases.
C. Planning and execution framework
Project execution was driven through a structured planning framework comprising monthly micro-level planning, detailed activity breakdowns and critical path method (CPM) analysis. Weekly review meetings facilitated early identification of execution bottlenecks and enabled timely corrective actions. In addition, shift-wise productivity planning ensured optimal utilisation of manpower and construction equipment. Advance availability of approved construction drawings further supported uninterrupted execution across multiple work fronts.
D. Supply chain and logistics management
A proactive supply chain and logistics management strategy was adopted to support sustained high-volume concreting operations. This included advance material forecasting, close coordination with contractors and suppliers, and round-the-clock logistics monitoring. As a result, uninterrupted availability of key construction materials was maintained, and no material-related work stoppages were recorded during the six-month period of high-volume concrete placement.
E. Equipment reliability and maintenance management
To address equipment reliability risks associated with continuous high-intensity operations, comprehensive preventive maintenance plans were implemented for batching plants, concrete pumps, transit mixers and formwork systems. Standby equipment arrangements and rapid-response maintenance teams were deployed to minimise downtime. These measures ensured zero critical equipment failures during peak concreting activities, thereby supporting uninterrupted execution.
Results and outcomes
The integrated application of disciplined planning practices, proactive manpower optimisation strategies, and leadership-driven execution resulted in consistent, measurable, and repeatable performance outcomes throughout the project execution phase.
Key project performance outcomes
• Sustained high-volume concreting: The project successfully achieved concrete placement volumes exceeding 10,000 m³ per month for six consecutive months, demonstrating sustained execution capability under high-intensity operational conditions.
• Festive-period performance: Despite traditionally reduced workforce availability during festive periods, the project maintained productivity during the month of October, achieving concrete volumes in excess of 10,000 m³, thereby surpassing conventional industry expectations.
• Workforce stability: Manpower retention levels of approximately 85 per cent to 90 per cent were maintained during identified high-risk periods, reflecting the effectiveness of workforce motivation and retention strategies.
• Accelerated clinker silo construction: A notable engineering achievement during this phase was the construction of the clinker silo within 12 days (achieved productivity of 2.5 mtr/day), significantly outperforming the prevailing industry benchmark of approximately 20 days (typical productivity of 1.5 mtr/ day). This accelerated execution underscores the effectiveness of integrated planning, synchronised resource deployment, and disciplined on-site execution.
• Equipment reliability: The implementation of preventive maintenance and standby arrangements resulted in zero critical equipment downtime, even during peak concreting operations.
• Industry benchmark establishment: Collectively, these outcomes established a first-of-its-kind benchmark in the Indian cement construction sector for sustained high-volume reinforced cement concrete execution over an extended duration.
Conclusion
The sustained success of the project reinforces a critical insight for large-scale industrial construction: consistent performance is achieved through disciplined systems, visible leadership engagement, and people-centric execution, rather than short-term acceleration measures. The integration of structured planning processes, empowered on-site decision-making, and proactive workforce engagement proved essential in mitigating external disruptions while maintaining execution momentum.
The achievement of sustained concrete placement volumes exceeding 10,000 m3 per month over a continuous six-month period at Project demonstrates the effectiveness of a structured project management framework combined with disciplined execution and leadership-driven site management.
This performance was realised despite significant challenges, including festive-season workforce constraints, labour migration during state elections, and the operational complexities associated with high-intensity construction activities.
About the author:
Anupam Agrawal brings around 34 years of experience in cement and heavy industry. At Dalmia Bharat, he is part of the senior executive bench steering capex transformation and growth across a pan-India footprint, working alongside leadership on efficiency,
expansion and governance.
Shailesh Agarwal works on institutionalising a resilient programme governance layer that supports client organisations in overcoming challenges and achieving business cases within defined budget, including cost and time.
Co- Author (contributions): Nikhil Dixit, Director -Consulting, EY India
You may like
-
From First Mile to Last Mile
-
Fornnax Names Lukas Baur as Authorised Service Partner to Bolster EU Operations
-
Why Traditional ERP Systems Fail in India?
-
Dalmia Bharat Cement launches water repellent cement brand Weather 365 in Eastern India
-
Optimising Cement Logistics Costs
-
Seamless Packaging Means Elevated Branding
Concrete
NCL Industries Approves Rs. 5.95 bn Solar-Wind Investment
NCL Industries also receives preliminary approval for an Odisha cement plant.
Published
17 hours agoon
November 16, 2026By
admin
NCL Industries has approved an investment of Rs. 5.95 bn for Phase 2 and Phase 3 of its 130 MW solar and wind power project in Tuticorin, Tamil Nadu. The approval covers the remaining 80 MW capacity and takes the estimated cost of the entire project to Rs. 9.87 bn.
The company, which manufactures cement, ready-mix concrete and other building materials, had approved the first phase on April 13, 2026. Phase 1 consists of 50 MW and was estimated to cost Rs. 3.92 bn. The project will be financed through a combination of debt and internal accruals.
Separately, the company’s board has granted in-principle approval to pursue a proposal for establishing a cement manufacturing plant in Odisha. NCL Industries plans to approach the Odisha government for project land and will undertake the applications and approvals required for the proposed facility.
The company said the Odisha project remains at a preliminary stage. No land allotment or definitive agreement has been executed, and it has not made any binding commitment to acquire or lease land as of the date of its disclosure.
Further action on the proposed cement plant will depend on applicable regulatory approvals, as well as the company’s additional evaluation and internal approvals. The board’s decision does not therefore represent a final investment commitment for the Odisha facility.
Shares of NCL Industries closed at Rs. 170.40 on the BSE on November 13, 2026, down Rs. 1.85, or 1.07 per cent, from the previous close. The company’s renewable energy expansion is intended to support its power requirements, while the Odisha proposal would add a new manufacturing project to its cement business if approved at a later stage.
Concrete
Cement Makers See Margin Relief as Oil Prices Lower Fuel Costs
Lower fuel costs and higher prices are set to support cement earnings.
Published
17 hours agoon
November 16, 2026By
admin
Cement makers are set to see a significant improvement in profitability in the second half of FY27 as falling global oil prices reduce the cost of key fuels, including petcoke and coal. Higher cement prices are also expected to support earnings, according to a report by Systematix Group.
The cement sector remained resilient in Q2 FY27, with volumes across the companies covered by the brokerage rising 7.2 per cent year-on-year. Higher sales volumes and improved realisations contributed to top-line growth during the quarter, although fuel and packaging expenses remained near-term concerns for manufacturers.
The report said the impact of lower oil prices should gradually appear in fuel costs, though the transmission is likely to be delayed. Petcoke and coal prices generally follow movements in crude oil prices, and the recent decline in global oil prices is expected to provide relief in subsequent quarters rather than immediately.
Cement prices improved towards the end of the second quarter, while price increases implemented during September and October are expected to support realisations in H2 FY27. The combination of stronger selling prices and moderation in energy costs could help offset pressure from fuel and packaging expenses, particularly after the third quarter.
Demand conditions are expected to remain supportive, with infrastructure spending, housing demand and a recovery in construction activity after the monsoon set to drive consumption in the coming months. Demand in eastern markets remained subdued because of prolonged monsoon conditions and flooding, while northern, southern and western markets recorded stronger activity.
The report retained a positive view of the sector, citing resilient demand growth of 8 to 9 per cent, improving pricing discipline and the expected moderation in fuel costs. These factors are expected to support a sharp earnings recovery for cement companies during H2 FY27.
Concrete
ABB Extends Drive Lifespan at ACC Cement Plant Without Production Shutdown
Published
5 days agoon
November 12, 2026By
admin
ABB reconditions 25 drives at ACC’s Jamul cement plant, avoiding 16 tonnes of COâ‚‚ emissions while improving reliability through predictive maintenance.
Chhattisgarh
ABB has signed a multi-year Motion OneCare service agreement with ACC Limited, part of the Adani Group, to modernise ageing industrial drives at its Jamul cement plant in Chhattisgarh, improving operational reliability while avoiding approximately 16 tonnes of carbon dioxide (COâ‚‚) emissions without disrupting production.
Announced on 27 October 2026, the agreement combines scheduled drive reconditioning, digital condition monitoring and energy appraisals to extend equipment lifespan, improve plant uptime and optimise maintenance costs. The initiative marks a shift from conventional equipment replacement towards a more resource-efficient approach to industrial asset management.
The first phase, completed in April 2026, involved the on-site reconditioning of 25 ABB ACS800 variable speed drives without a major plant shutdown. By retaining the existing cabinets and restoring the drive modules rather than replacing entire panels, ABB helped ACC preserve capital investment, minimise material consumption and avoid approximately 16 tonnes of COâ‚‚ emissions.
A second phase, covering an additional 25 ACS800 drive modules, is scheduled for the fourth quarter of 2026. The programme is designed to improve long-term equipment reliability while allowing maintenance activities to be aligned with the plant’s operational schedules.
The ACS800 drives, installed at Jamul in 2010, had delivered more than a decade of near-continuous service in demanding cement manufacturing conditions. However, ageing electrical components and changing fault patterns had begun to affect their ability to meet the plant’s reliability requirements.
Rather than opting for complete equipment replacement, ACC engaged ABB’s certified engineers to conduct a comprehensive asset health assessment. The evaluation found that the existing cabinets and enclosures remained structurally sound, making targeted reconditioning a technically viable and cost-effective alternative to full replacement.
Drawing on nearly two decades of experience with ACC’s equipment and operating requirements, ABB developed a maintenance framework tailored to the plant’s shutdown windows, budget cycles and production priorities.
The Motion OneCare agreement incorporates planned equipment restoration, condition-based monitoring and energy assessments, enabling ACC to adopt a more systematic approach to maintaining critical electrical infrastructure.
As part of the programme, ACC has implemented ABB Abilityâ„¢ Digital Powertrain Insights to monitor drive performance and identify emerging operational issues before they result in equipment failures.
The digital platform provides continuous visibility into parameters such as temperature, current, vibration and fault patterns. These insights allow maintenance teams to detect early signs of equipment deterioration, schedule interventions more effectively and reduce the likelihood of unexpected downtime.
Amit Gupta, Local Division Manager, Motion Services, ABB India, said: “We know what unchecked wear costs over time: a small inefficiency that eats away at ROI for years. At Jamul, the evidence pointed clearly to assets with productive life still in them.”
“Our job was to restore them properly and give the team the tools to stay ahead of the next problem. At ABB, we don’t just fix what fails. We want to protect what works.”
The initiative also demonstrates the growing relevance of circular economy principles in cement manufacturing, where extending the service life of existing industrial equipment can reduce capital expenditure, material consumption and the environmental impact associated with manufacturing replacement components.
According to ABB, drive reconditioning can reduce lifecycle emissions by 50 to 80 per cent compared with complete equipment replacement. By preserving functional components and restoring critical modules, the process helps retain the economic and material value of existing industrial assets.
The addition of energy appraisals in subsequent phases will further expand the programme beyond equipment restoration, enabling ACC to assess drive performance, identify energy-saving opportunities and improve operating efficiency.
For cement manufacturers, variable speed drives play an important role in controlling motors and optimising energy consumption across production processes. Maintaining their reliability and efficiency is essential for minimising operational disruptions and managing electricity costs.
Vinod Bahety, CEO – Cement Business, Adani Group, said: “Moving from reactive firefighting to a structured maintenance plan was exactly what this operation needed. That kind of peace of mind doesn’t come easily. It comes from a partner that understands how your business runs.”
“We didn’t need a full system overhaul; we needed expert support, actionable insights, and a plan we could execute around our schedule. That’s what we got.”
The project supports ACC’s broader strategy to improve manufacturing efficiency through digital transformation, preventive maintenance and sustainable asset management.
ACC, a subsidiary of Ambuja Cements and part of the Adani Group, operates 20 cement manufacturing facilities and 119 ready-mix concrete plants across India. The company has been advancing initiatives focused on renewable energy, circular economy practices and technology-driven operational improvements.
Alongside Ambuja Cements, ACC is part of a large-scale building materials business committed to achieving net-zero emissions by 2050, with near-term and net-zero targets validated by the Science Based Targets initiative (SBTi).
The Jamul initiative aligns with these sustainability objectives by demonstrating how equipment life extension and digital monitoring can contribute to resource efficiency without requiring large-scale replacement of existing infrastructure.
ABB, a global technology company specialising in electrification and automation, brings more than 140 years of industrial expertise and employs approximately 110,000 people worldwide. Its Motion Services business supports industrial customers through equipment maintenance, modernisation, digital monitoring and lifecycle management solutions.
The agreement also reflects a wider shift in industrial maintenance practices, with manufacturers increasingly adopting predictive technologies to improve equipment availability, manage costs and reduce unplanned shutdowns.
With 25 drives already reconditioned and another 25 scheduled for restoration, ABB’s collaboration with ACC illustrates how targeted modernisation, digital monitoring and circular maintenance practices can extend the operational life of critical equipment while supporting more efficient and sustainable cement production.
NCL Industries Approves Rs. 5.95 bn Solar-Wind Investment
Cement Makers See Margin Relief as Oil Prices Lower Fuel Costs
ABB Extends Drive Lifespan at ACC Cement Plant Without Production Shutdown
ABB Drives Digital Transformation at TCI MAX Cement Plant in J&K
Ramco Cements’ Hard Worker Wins Eight Awards at ‘Love of Advertising Awards 2026’
NCL Industries Approves Rs. 5.95 bn Solar-Wind Investment
Cement Makers See Margin Relief as Oil Prices Lower Fuel Costs
ABB Extends Drive Lifespan at ACC Cement Plant Without Production Shutdown
ABB Drives Digital Transformation at TCI MAX Cement Plant in J&K
Ramco Cements’ Hard Worker Wins Eight Awards at ‘Love of Advertising Awards 2026’
Trending News
-
Concrete4 weeks agoMeghalaya Cabinet Approves MCCL Closure, Writes Off Rs. 244.3 mn
-
Concrete4 weeks agoFornnax Wins AIRIA’s Special Export Award for Rubber Machinery in 2025-26
-
Concrete4 weeks agoNuvoco reports 13.5% revenue growth in Q2 FY27
-
Concrete4 weeks agoUltraTech Cement Expands in Andhra Pradesh with Rs. 26.5 bn