Connect with us

Concrete

Creating a concrete connect

Published

on

Shares

The National Highways Authority of India (NHAI) had awarded the work for the four-laning of the Meerut-Bulandshahr section of NH-235 from 8.800 km to 73.512 km (design chainage in the state of Uttar Pradesh under NHDP Phase IV on Hybrid Annuity Model), for a concession period of 17.5 years, including a construction period of 910 days, i.e. two-and-a-half years, and an operation and maintenance period of 15 years to Freedom Point Expressways as concessionaire. Apco Infratech, who was the lowest bidder, had incorporated a SPV, Freedom Point Expressways (FEPL), as the concessionaire for development of the project.

??EPL had entered into a concession agreement (CA) with NHAI on March 4, 2016, for construction, operation and maintenance of the project,??informs DK Srivastava, Executive Vice-President, APCO Infratech. The CA sets out the scope, rights and obligations of all the parties, overall framework for the development, and operation and maintenance of the project. While the project bid was floated by NHAI at end of 2015, the appointed date was declared as April 28, 2017. ??uring this course of time and the completion period as well, the project alignment features have been modified to cater to the topographic and demographic variations and inhabitant demands.??/p>

Scope of work

The site of the four-lane project highway comprises the section of NH-235 (New NH-334) commencing 8+800 km to 66+482 km and excluding 3.522 km of existing bypass of NH-24 (i.e., the Meerut- Bulandshahr section), having a total length of 64.712 km, including 3.522 km of the existing Hapur Bypass of NH-24 in Uttar Pradesh. The total design length of the project road is about 61.19 km. This section traverses through three districts of Uttar Pradesh: Meerut, Hapur and Bulandshahr.

As Srivastava shares, ??HAI had proposed to bypass nodal towns, i.e. Phaphunda Bypass (2.7 km), Kharkhauda Bypass (3.2 km), Hapur Bypass (11.2 km ??greenfield and 1.228 km ??improvement of existing Hapur Bypass on NH 24) and Gulaothi Bypass (7.6 km), and widen the two-lane existing alignment into four lanes with a paved shoulder and divided median on the basis of a detailed project (feasibility) report carried out in the year 2010.??/p>

The alignment traverses along and across various canals, drains and railway crossings. In order to cater to these structures, nine minor bridges, one major bridge, and one RoB has been provided. Additionally, a six-lane carriageway underpass (three vehicular underpass (VUP), five pedestrian underpass (PUP)) has also been provided to accommodate major crossroads without conflict.

Resource planning and execution

FEPL, the concessionaire, had to design the project considering the above project particulars as per codal provisions of IRC: SP: 84 – 2014 and determine the requisite resources, i.e. manpower, material and machinery, to complete the project within the stipulated timeframe. The contractor had identified its need and planned its resources to execute the work within a 910 day timeline. Srivastava shares the key resource deployment in the form of material, manpower and machinery, as tabulated here:

Execution challenges

  • Various challenges were involved in the execution of this project.

  • Various hindrances in the form of factories, boundary wall, trees, houses, and shops.

  • Delay in handing over encumbrance-free ROW to the concessionaire.

  • Non-disbursement of compensation or dispute by landowners regarding compensation awarder.

  • Hindrances owing to irrigation structures and DFCC.

  • Construction ban imposed by the Supreme Court and National Green Tribunal.

  • Delay in finalisation of ??hange of scope??by the authority .

  • Delay in approval for tree felling by the Forest Department.

  • Lockdown due to outbreak of COVID-19.

??hese issues had resulted in project delays,??says Srivastava. ??he project timeline was stretched for 553 days in addition to 910 days. However, FEPL, with its prudent approach and accelerated efforts, reduced the time span to 295 days from the additional 553 days required for the project and achieved a provisional completion certificate on August 14, 2020.??/p>

Challnges during the Coronavirus outbreak

In March 2020, when the Government imposed the nationwide lockdown to curb the spread of the pandemic, the project was about to achieve the provisional certificate scheduled on April 25, 2020. Owing to the lockdown, the project lost movement, motivation and resources for executing project facility work (finishing work) and balance major work.

The concessionaire, upholding the professional ethics and values of its promoter APCO Infratech, retained manpower at its respective accommodation facilities and provided the best services to help them during a hard time. ??owever, a manpower exodus begun upon the start of special trains and buses to their respective home places,??says Srivastava. ??he government eased lockdown restriction for the infrastructure sector on April 20, 2020, but the district administration had not allowed commencement of work till May 4, 2020.??Workers were then facilitated with all type of Covid-19 precautions.

Safety first!

To avoid fatalities or accidents at work, FEPL ensured that the labour or manpower wore high-visibility clothing, which included a vest, hardhats, safety glasses, face shields, earplugs, fall arrest systems, safety-toed shoes, respirators and all types of PPE. The procedure was well-established??ome call it an internal traffic control plan??o separate workers from the path of vehicles and equipment.

Socioeconomic benefit

The Minister of Road Transport and Highways has cited that this project will shorten travel time from Meerut to Bulandshahr to one hour from the two hours earlier. Also, the highway will serve as a direct access route to Garh-Mukteshwar, where the state government is planning to develop a waterway and promote tourism. It will also serve as an access route to the upcoming Ganga Expressway in Meerut and Bulandshahr.

Achievement

The entire project has a rigid pavement and is among the few projects in Uttar Pradesh to have the entire length paved with pavement quality concrete. What?? more, the toll plaza has been established within 180 m RoW comprising a 14-lane road; it is one of the most advanced and equipped toll plazas.

– SHRIYAL SETHUMADHAVAN

PROJECT DETAILS

Cost: Rs 11.30 billion including COS granted for additions of elevated structures for safety of road users and access to villagers or farmers

Month of completion: August 14, 2020, (PCOD) and November 12, 2020 (COD)

Total length: 61.19 km

Developer: Freedom Point Expressways

Contractor: APCO Infratech

Consultant: SAI Consulting Engineering (SYSTRA)

Steel: SAIL, REAL Ishpath, JSPL

Other technology or material used: Fly ash or silica as cement

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Concrete

UltraTech Cement FY26 PAT Crosses Rs 80 bn

Company reports record sales, profit and 200 MTPA capacity milestone

Published

on

By

Shares

UltraTech Cement reported record financial performance for Q4 and FY26, supported by strong volumes, higher profitability and improved cost efficiency. Consolidated net sales for Q4 FY26 rose 12 per cent year-on-year to Rs 254.67 billion, while PBIDT increased 20 per cent to Rs 56.88 billion. PAT, excluding exceptional items, grew 21 per cent to Rs 30.11 billion.

For FY26, consolidated net sales stood at Rs 873.84 billion, up 17 per cent from Rs 749.36 billion in FY25. PBIDT rose 32 per cent to Rs 175.98 billion, while PAT increased 36 per cent to Rs 83.05 billion, crossing the Rs 80 billion mark for the first time.

India grey cement volumes reached 42.41 million tonnes in Q4 FY26, up 9.3 per cent year-on-year, with capacity utilisation at 89 per cent. Full-year India grey cement volumes stood at 145 million tonnes. Energy costs declined 3 per cent, aided by a higher green power mix of 43 per cent in Q4.

The company’s domestic grey cement capacity has crossed 200 MTPA, reaching 200.1 MTPA, while global capacity stands at 205.5 MTPA. UltraTech also recommended a special dividend of Rs 2.40 billion per share value basis equivalent to Rs 240.

Continue Reading

Concrete

Towards Mega Batching

Optimised batching can drive overall efficiencies in large projects.

Published

on

By

Shares

India’s pace of infrastructure development is pushing the construction sector to work at a significantly higher scale than previously. Tight deadlines necessitate eliminating concreting delays, especially in large and mega projects, which, in turn, imply installing the right batching plant and ensuring batching is efficient. CW explores these steps as well as the gaps in India’s batching plant market.

Choose well

Large-scale infrastructure and building projects typically involve concrete consumption exceeding 30,000-50,000 cum per annum or demand continuous, high-volume pours within compressed timelines, according to Rahul R Wadhai, DGM – Quality, Tata Projects.

Considering the daily need for concrete, “large-scale concreting involves pouring more than 1,000–2,000 cum per day while mega projects involve more than 3,000 cum per day,” says Satish R Vachhani, Advanced Concrete & Construction Consultant…

To read the full article Click Here

Continue Reading

Concrete

Andhra Offers Discom Licences To Private Firms Outside Power Sector

Policy allows firms over 300 MW to seek distribution licences

Published

on

By

Shares

The Andhra Pradesh government will allow private firms that require more than 300 megawatt (MW) of power to apply for distribution licences, making the state the first to extend such licences beyond the power sector. The policy targets information technology, pharmaceuticals, steel and data centres and aims to reduce reliance on state utilities as demand rises for artificial intelligence infrastructure.

Approved applicants will be able to procure electricity directly from generators through power purchase agreements, a change officials said will create more competitive tariffs and reduce supply risk. Licence holders will use the Andhra Pradesh Transmission Company (APTRANSCO) network on payment of charges and will not need a separate distribution network initially.

Licences will be granted under the Electricity Act, 2003 framework, with the Central and State electricity regulators retaining authority over terms and approvals. The recent Electricity (Amendment) Bill, 2025 sought to lower entry barriers, enable network sharing and encourage competition, while the state commission will set floor and ceiling tariffs where multiple discoms operate.

Industry players and original equipment manufacturers welcomed the policy, saying competitive supply is vital for large data centre investments. Major projects and partnerships such as those involving Adani and Google, Brookfield and Reliance, and Meta and Sify Technologies are expected to benefit as capacity expands in the state.

Analysts noted India’s data centre capacity is forecast to reach 10 gigawatts (GW) by 2030 and cited International Energy Agency estimates that global data centre electricity consumption could approach 945 terawatt hours by the same year. A one GW data centre needs an equivalent power allocation and one point five times the water, which authorities equated to 150 billion litres (150 bn litres).

Advisers warned that distribution licences will require close regulation and monitoring to prevent misuse and to ensure tariffs and supply obligations are met. Officials said the policy aims to balance investor requirements with regulatory oversight and could serve as a model for other states.

Continue Reading

Video Thumbnail

    SIGN-UP FOR OUR GENERAL NEWSLETTER


    Trending News