Concrete
Bartin Cimento Meets Guarantees
Published
10 years agoon
By
admin
In April 2012 Belim Makina completed the installation of a new 3000 t/d kiln line of Bartin Cimento, Turkey. Just one month later during a 48 hours test run at full production all parameters met the guarantees of IKN, who had provided the design of the complete pyro line. In addition, IKN had supplied key components like ID fan, valves, dampers, kiln drive, girth gear, kiln roller stations and the clinker cooler.
Bartin Cimento, a member of Sanko Holding, in 2010 decided to replace its old wet kiln line with state-of- the-art equipment, in order to increase production to 3.000 t/d and reduce energy consumption to the best possible level. The new line was to be placed adjacent to the existing wet kiln, which had to be maintained in operation. Upon stable production of the new line the old kiln was to be dismantled. The customer as well as Belim Makina, who was selected as EPC contractor, knew IKN well from earlier projects in Turkey and accepted its proposed solution for the pyro line as it promised operational reliability in combination with attractive process parameters. In particular, the decision to select IKN as supplier for the complete pyro line was based on process guarantees and mechanical warranties. The final solution comprised a six-stage LUCY type preheater with inline calciner, a conventional 4.2x62m 3-pier kiln and a Pendulum Cooler, which is known for its linear pendulum suspension and horizontal aeration. The calciner and kiln burners were designed for burning a mixture of pet coke and coal. In addition a modern multi-channel burner was required for the use of heavy fuel oil as an alternative during start-up.
Preheater LUCY
LUCY stands for low under pressure cyclones, a development of IKN’s sister company PSP of Czech Republic. The six-stage preheater tower rises 100 meters above ground level and accommodates amply two top cyclones followed by a single string of cyclones. The raw meal enters the preheater at the riser duct between the two top cyclones of 6 m diameter. It passes the cyclone stages C2 to C6 which are 7.5m in diameter. In line with the LUCY concept, the pressure drops and the corresponding degrees of raw meal separation decrease towards the hot gas inlet. The separated raw meal leaves the cone of the respective cyclone through steep and wide raw meal chutes equipped with flaps designed for continuous release of the meal at minimal counter flow of hot gas.
Calciner
Between cyclones C5 and C6 an inline calciner type KKN-AS with low NOx duct is installed. The preheated raw meal enters the calcining channel just above the location where the burner pipes and tertiary air ducts are attached. The lower part of the calciner has a width of 4.35m square. It ensures an efficient mixing of 4.35 m square. It ensures an efficient mixing of meal and fuel with the oxygen-rich tertiary air. The upper part of the calciner has a diameter of 4.1m. It ends in a swirl head followed by a down comer duct to the C6 inlet. Initial mixing in the bottom part and repeated mixing by the swirl head together with specified retention time care for complete fuel combustion at low oxygen surplus. Parallel to the calciner channel a so-called low NOx duct bypasses oxygen-rich tertiary air to the swirl head so that the calciner duct generates CO, which reduces a good portion of nitrogen oxides summarized as NOx. Combustion is completed in the swirl head and the down comer duct of the calciner in an oxygen rich atmosphere. The calciner burner is designed to burn any combination of petcoke or coal.
Kiln
For the production of 3.000 t/d a 62m long and 4.2m shell inner diameter rotary kiln of 3 per cent inclination supported by three piers was selected. Its diameter and volume allows for a reserve in gas volume along with higher production or along with alternate fuel combustion. The 12 radial roller bearings of the kiln supplied by IKN have spherical seats for the bushes, which tolerate bending of the roller shafts and render overheating less likely. They are equipped with an oil and water distribution system for lubrication and cooling. Temperature of oil and thrust ring are monitored by thermocouples. Adjustment boxes on the frame serve for horizontal alignment during operation. For uniform wear of rollers and tires regular axial shifts of the kiln take place. A shift to its upper position is performed by a single hydraulic thrust roller pushing against the tire of bottom pier #1. The kiln is then allowed to travel down by gravity against the thrust roller, which has meanwhile returned to its lower position. The axial shifts are programmed in regular intervals of 5 – 8 hours. Shell temperatures and tire slips are monitored by scanners. Combined with proven shell materials and statics, forced axial kiln shifts and spherical roller bearings provide optimal protection against mechanical kiln failures.
The inlet and outlet seals are air cooled double lamella types, which are easily maintained.
The 55MW thermal capacity multi-channel burner is designed to burn 100 per cent pet coke, 100 per cent coal or a mixture of both. For start-up heavy fuel oil can be used through a separate fuel lance of 5.280 kg/h capacity.
Cooler
The clinker cooler still is the key to the availability and heat efficiency of the pyro line. IKN’s Pendulum Cooler has an aerated surface of 68m2. Availability is assured by a single stage, single hydraulic cylinder drive located at the front end, by Linear Pendulum Supports (LPS) with no lubricated parts within the confined area of the under grate housing, by minimal number of movable parts of the grate surface, by a slow motion roller crusher capable of handling chunks up to a size passing the kiln burner pipe and by a minimal number of 7 fans connected to 7 compartments of the 21m long grate.
Heat efficiency equal to secondary and tertiary air of high and stable temperature is assured by the clinker inlet distribution system KIDS, which with regard to the width of the 3.2m wide grate generates a clinker bed of uniform resistance against the passage of air, and by air distribution to all clinker voids by gentle horizontal COANDA aeration. Named after Henry Coanda of Romania, this effect creates horizontal air jets which are aerating the clinker bed and by keeping adjacent to the grate surface provide an efficient cooling of the grate itself. Safe cooler operation is simply limited to the observance of a pre-set bed pressure drop of the first air compartment, which is controlled by the speed of the hydraulic cylinder. Rather than close automated control, which is provided as well, IKN recommends a fixed grate speed allowing for a pre-set range of bed pressure variation. In most cases – including Bartin Cimento – fixed grate speed comes along with stable kiln operation.
Thanks to the accuracy of the grate alignment and the minimal gaps between moving and fixed parts of the grate, the amount of clinker falling into the under-grate compartments is minimal. The dust could be evacuated during annual shut downs. For comfort and safety, a tube chain conveyor is installed for the extraction of any clinker dust to the clinker discharge. Typically, the tube extractor is operated once a day for a couple of hours.
Installation
Installation of the pyro line took place from September 2011 until April 2012. During this period IKN delegated various experts for inspection of local manufacturing based on its detail drawings and for assistance of Belim Makina for speedy identification and installation of parts. The cooperation with Belim Makina was excellent as the company had earlier experience with IKN equipment.
A highlight and challenging task was the installation and alignment of the kiln girth gear. Using a crane, both halves of the girth gear were wrapped around the kiln and firmly bolted together. Upon measurements of an acceptable run-out, the crew installed the auxiliary drive, adjusted the rollers to their final position, and finalized the gear alignment. auxiliary drive, adjusted the rollers to their final position, and finalized the gear alignment. For cooler grate surface installation, preassembly tools specifically designed for this project were used, which reduced installation time and which made sure that all parts fitted easily into their position. For LPS alignment a laser-light theodolite was used and the reference points marked on the kiln foundation were protocolled for later verification.
Finally, the six-stage preheater at Bartin is the new landmark which represents the latest technology in cement production in the area.
Commissioning/Testing
In May 2012 the new pyroline was started up. Within the two days performance test the same month all relevant technical parameters were measured during operation and a protocol was signed.
Conclusions
The performance of the new pyro line at Bartin Cimento confirms that the combination of IKN Pendulum Coolers with a state-of-the-art pyro system provides excellent results. The combination leverages the IKN cooler performance to an over-all plant performance which in this case benefits Bartin +Cimento. It confirms further that for new pyro lines and refurbishment projects, excellent process know-how, in-house manufacturing capability coupled with thorough design experience provides superior results in terms of time, efficiency, and cost.
by Frank Lichomski, IKN GmbH, Germany
Design Parameters:
|
Capacity |
3.000 tpd |
|---|---|
| Preheater | 6 stage single string type LUCY with inline calciner (KKN-AS) |
| Calciner burner | "for 100% petcoke, 100% coal or mixture of both alternatively 100% HFO" |
| Kiln | 4,2m x 62 m |
| Kiln Burner | "for 100% petcoke, 100% coal or mixture of both alternatively 100% HFO" |
| specific heat consumption | <688 kcal/kg |
| Cooler | "single stage with single hydraulic cylinder drive suspended by Linear Pendulum Support (LPS) aerated surface: 67 m2 installed cooling air: 2,1 Nm3/kg clinker" |
| cooler discharge clinker temperature | 65?C above ambient |
| Roller crusher | Roll crusher with 3 rolls, width: 3m |
| Exhaust fan | 245 Nm3/h |
Concrete
Akhoya Gets New 2.2 Km Road Link Under SASCI
Two cement concrete roads opened at Rs 29.1 million (mn) cost
Published
5 hours agoon
July 3, 2026By
admin
Two cement concrete pavement roads covering a total stretch of 2.2 km in Akhoya village were inaugurated on 27th June 2026 by MLA Nuklutoshi Longkumer, who attended as the special guest. The project comprises the one km L Pangersowa Road and the one point two km Longchara Junction to RC Chiten Jamir Memorial Government High School road. A formal programme followed the inauguration at the school auditorium.
A technical report was presented by Er Waloniba of the Urban Engineering Wing-III, Kohima, which stated the project was sanctioned in March 2026 under the Special Assistance to States for Capital Investment scheme for 2025-26 at a sanctioned cost of Rs 29.1 million (mn). The work order was issued to M/s Ensign Construction on thirtieth April 2026 with a stipulated completion period of 12 months. Work commenced on fourth May 2026 and was completed on sixth June 2026, with the contractor and team finishing the tasks in around two months. The project included a single-lane cement concrete pavement with side drains, two slab culverts and breast walls at required locations.
Longkumer acknowledged the Chief Minister, the advisor for urban development, contractors and other stakeholders for the allocation and support, and he commended the contractor for early completion. He noted that cooperation from landowners and the community had been important in resolving land related issues that can otherwise delay developmental works. He emphasised that planned developmental activities carried out with collective effort would enable more projects to be implemented successfully.
The headmaster of RC Chiten Jamir Memorial Government High School, I Chubasenba Longkumer, outlined the school background, noting it was established in 1962, was earlier known as Government High School Changtongya and was renamed in 2014. Local representatives said the improved approach roads would ease access for students, staff, patients and the general public and fulfil a long standing aspiration of residents. A dedicatory prayer was offered by the pastor and the programme concluded with a ribbon cutting attended by village council and town council representatives.
Indian Cement Review (ICR) and Fuller Technologies brought industry, policy and technology leaders together to discuss how cement innovation can drive green construction at scale, writes Rakesh Rao.
India is building at a pace few countries can match. Highways, airports, housing, logistics parks, industrial corridors and urban infrastructure are reshaping the country’s economic geography. But beneath this growth story lies a difficult question: can India continue to build at scale without locking itself into a high-carbon future?
That question formed the core of an online panel discussion titled “Driving Green Construction Through Cement Innovation”, organised by Indian Cement Review (ICR) in association with Fuller Technologies as the Presenting Partner on June 25, 2026. The webinar brought together experts from cement technology, R&D, global industry platforms, building performance policy and international development cooperation to examine how low-carbon cement and material innovation can accelerate India’s green construction transition.
The discussion came at a crucial time. India has committed to achieving net-zero emissions by 2070 and reducing the carbon intensity of its economy by 45 per cent by 2030. At the same time, the country’s construction sector is expanding rapidly, driven by urbanisation, infrastructure development, housing demand and industrial growth. Cement, as one of the most widely used construction materials, sits at the heart of this transition. It is indispensable to development, but also central to the challenge of reducing embodied carbon in buildings and infrastructure.
Moderated by Nitika Krishan, Senior Urban Infrastructure and Sustainable Policy Consultant, the panel featured:
- Kiranmai Sanagavarapu, Director, Low Carbon Solutions, Fuller Technologies;
- Dr Hemantkumar Aiyer, VP and Head R&D, Nuvoco Vistas Corp Ltd;
- Devika Wattal, Innovation Lead, Global Cement and Concrete Association (GCCA);
- Dr Sunita Purushottam, MD, GBPN India (Global Buildings Performance Network); and
- Vaibhav Rathi, Senior Technical Advisor, GIZ (the German Agency for International Cooperation)
Setting the tone for the discussion, Nitika Krishan underlined the scale of the challenge before the sector. “The question before us is no longer whether we build, but how we build sustainably,” she said. She pointed out that construction accounts for nearly 40 per cent of global energy-related carbon emissions when both operational and embodied carbon are considered. Cement production, she added, remains one of the hardest industrial processes to decarbonise.
For India, this is not merely an environmental issue. It is a development issue, a competitiveness issue and increasingly, a market issue. As one of the world’s largest cement producers and among the fastest-growing construction markets, India’s material choices will influence the carbon trajectory of its built environment for decades. As Krishan observed, sustainability solutions in economies such as India must not remain limited to laboratory success. They must be scalable, commercially viable and practical at national level.
The innovation gap: From technology to market
Experts believe that there is a need to bridge the innovation gaps for making decarbonisation in cement and concrete scalable. Devika Wattal of GCCA, explained, “The starting point must be the core cement manufacturing process itself. The first and foremost is the heart of our process, the heart of cement manufacturing. How do we reduce clinker? That is always a topic where industry is working very intrinsically.”
Clinker reduction remains one of the most important pathways for lowering emissions in cement. Since clinker production is energy-intensive and chemically emits carbon dioxide, reducing the clinker factor through supplementary cementitious materials (SCMs), blended cements and new chemistries can have a significant impact. Wattal also noted that carbon capture, utilisation and storage (CCUS) will have a role, though it may not be the first lever for all markets.
However, she stressed that innovation cannot stop at technology development. A solution that works in the lab must also be adaptable to industry, scalable in production and acceptable in construction practice. “It is important for that innovation to be adaptable, to be scalable, and so that it can be executed in real time,” she said.
Wattal also called for stronger enabling systems around innovation. These include performance-based standards, product-level embodied carbon databases and clearer frameworks for evaluating green materials. Without these, low-carbon cement products may struggle to compete with conventional materials in procurement and design.
R&D must balance carbon, cost and performance
Bringing in the R&D perspective into the discussion, Dr Hemantkumar Aiyer of Nuvoco Vistas emphasised that low-carbon cement development cannot be treated as a single-variable exercise. Cement must perform in real construction conditions. It must deliver strength, durability, consistency and cost competitiveness, while also reducing carbon.
“The root of understanding and balancing all these aspects lies in materials, and knowing the materials,” he said.
According to Dr Aiyer, R&D teams must understand the variability of raw materials such as fly ash, slag and clinker. Different sources produce different material behaviours. This makes mix optimisation, material characterisation and processing-property relationships critical. When performance is affected, cement manufacturers must understand how strength enhancers, admixtures and other performance chemicals interact with the material system.
He also linked material science with process efficiency. Clinkerisation takes place at extremely high temperatures, around 1,400 to 1,450 degrees Celsius. Any improvement in raw mix design, process control or energy optimisation can, therefore, help reduce emissions and cost. Dr Aiyer pointed to artificial intelligence-based optimisation, Cement 4.0 tools and advanced software as important enablers for real-time process and material control.
“The more you understand the materials, the more you can control it,” he said.
LC3: The promise is proven, the sequencing is not
Limestone calcined clay cement, commonly referred to as LC3, has attracted global attention because it can reduce clinker content significantly by using calcined clay and limestone while maintaining performance in many applications. Kiranmai Sanagavarapu of Fuller Technologies said the technology itself has already moved beyond proof of concept. Fuller Technologies has worked with calcined clay technology for nearly two decades and has seen plants running in France and Ghana. These plants, she said, are meeting local and national specifications, while the economics are beginning to make sense.
“The calciner is performing, the economics is stacking up, it is making business sense to produce,” she said.
But if the technology is viable, why has adoption not scaled faster? For Sanagavarapu, the answer lies in project sequencing. Too often, clay characterisation happens after equipment is specified. This, she warned, is a backward approach because calciner design depends on clay mineralogy, kaolinite content, iron levels, reactivity, moisture and other variables.
“If you don’t know what your deposit looks like before you commit for the equipment, you are, in a way, going blind into designing,” she said.
She also identified permitting and plant integration as major bottlenecks. Environmental clearances, mining permissions and local regulatory approvals must begin early. Similarly, calcined clay must be integrated into existing grinding, blending and logistics systems from the design stage, not treated as an afterthought during commissioning.
India already has IS 18189:2023 standard for LC3, but Sanagavarapu pointed out that the standard is not yet visible enough in procurement documents. “The gap between what is technically being permitted and what the procurement is asking is the single biggest bottleneck,” she said.
In her view, successful scale-up depends on getting the sequence right: clay characterisation first, permitting in parallel, standards aligned with construction, and integration built into plant design.
India’s LC3 journey: Progress, but demand remains thin
Providing details of India’s LC3 commercialisation experience, Vaibhav Rathi of GIZ noted that JK Cement carried out the first commercial production of LC3 at its Rajasthan plant, followed by JK Lakshmi Cement three months later. These initiatives were supported by the International Climate Initiative of the Government of Germany, with IIT Delhi contributing deep institutional knowledge on LC3 research and BIS certification.
Rathi said India’s early experience has produced clear lessons. One of the biggest was the need to build capacity among regulators. While BIS certification existed, State Pollution Control Boards were unfamiliar with the technology and unsure about the approval pathway.
“The capacity building is not just needed amongst the producer and the users of the cement, but also the regulators who are working with this technology for the first time,” he said.
He also highlighted the need for better information on China clay deposits. Since China clay is currently classified as a minor mineral, centralised data on availability, quality and location is limited. If cement manufacturers are to adopt LC3 at scale, stronger mineral intelligence will be important.
The third issue is demand. LC3 has already been used in projects such as Palava City in Mumbai and Noida International Airport, but these remain limited examples. “It is in a chicken and egg situation,” Rathi said. “Cement companies are saying we need more demand, and users are saying there is not enough cement available.”
Public procurement, he suggested, could help break this cycle. If agencies such as CPWD and other public bodies begin testing, accepting and specifying LC3, it could create the market confidence needed for cement companies to invest in production and storage.
Building codes must catch up with innovation
Dr Sunita Purushottam of GBPN India argued that material choices will determine built environment emissions over the long term, but India’s current policy signals remain fragmented. Although LC3 has received BIS recognition, she pointed out that building codes, municipal bylaws, schedules of rates and sustainability codes do not yet provide uniform guidance on low-carbon cement.
“The current cement regulations are largely prescriptive and favouring traditional materials,” she said. This limits the ability of alternative materials to compete on performance, durability and emissions.
Dr Purushottam also raised the issue of taxation. Cement, including LC3, currently falls under the same GST bracket as conventional cement. A differentiated tax structure, she argued, could help accelerate market adoption. “In order for the market to demand LC3, that differentiation in the GST could go a long way,” she said.
She noted that green building certifications such as IGBC and GRIHA are already creating demand for low-carbon materials by assigning points for embodied carbon and sustainable material use. However, she said large-scale adoption will require regulatory mandates, particularly through building codes and state-level notifications.
She also cautioned that low-carbon cement alone does not solve the entire building performance problem. A material may reduce embodied carbon, but the operational carbon of a building depends on thermal performance, design, insulation and energy use. “The energy part has two elements,” she said. “One is the embodied carbon of the material itself, and the other is the operational carbon.”
Collaboration is the bridge between invention and impact
Wattal said GCCA sees innovation as a strategic priority and works through platforms that connect industry with academia and start-ups. “There is no way we will decarbonise our sector without innovation,” she said.
However, she stressed that research must be connected to actual industry challenges. Innovations developed in isolation may fail when they encounter real-world barriers such as raw material variability, plant integration, cost, standards and finance. Start-ups, too, need industry mentorship and scale-up pathways.
Wattal also flagged the importance of finance. Even strong technologies may struggle to attract investment if there is no common understanding of bankability. “We have always put projects into, is this a bankable project? But the definition of a bankable project has never been defined,” she said.
For India, she saw strong potential in its academic and start-up ecosystem, but said the challenge lies in alignment and prioritisation. The country has the research base, industrial capacity and market size. What it now needs is a coordinated route from innovation to deployment.
There is a practical concern for cement manufacturers: how can existing plants be adapted for lower emissions without compromising reliability or commercial viability?
Kiranmai Sanagavarapu addressed, “The reliability risk in calcined clay retrofit is definitely real, but it is almost always self-inflicted. The risk arises when a new process is added to an existing circuit without properly redesigning grinding and blending configurations.”
Existing cement plants, she explained, can take two broad routes. The first is external sourcing of calcined clay combined with mill optimisation. This requires lower capital investment and can potentially move in 12 to 18 months if other conditions are in place. It may reduce emissions by around 20 to 30 per cent. The second route is integrated calcination on site, which requires higher capital expenditure and longer lead times, but provides greater control over quality, supply and emissions reduction potential.
For Sanagavarapu, the principle is simple: low-carbon retrofits must be designed with intent. “Design it with an intent properly from the start. Start in the market conditions where the economics are already working,” she said.
Circularity: The overlooked advantage
According to Vaibhav Rathi, fly ash and slag are already well established in cement and construction (C&D), but construction and demolition waste remains underutilised. “C&D waste is a growing business opportunity which not many have taken up,” he said. India’s continuous construction and demolition activity creates huge volumes of waste, much of which contributes to air pollution, land degradation and material inefficiency. With the right processing and standards, this waste can be converted into useful construction products.
Rathi also pointed out that LC3 has a circular economy dimension that is often overlooked. It can use low-grade kaolin-rich clay left behind after high-grade clay is extracted for other applications. “LC3 is not only a low-carbon solution, but also a circular economy solution,” he said.
At the same time, he cautioned that LC3 in India is not yet cheap because it has not reached scale. Site-specific techno-commercial feasibility studies, supported jointly by development agencies and industry, could help companies assess whether LC3 production makes technical and financial sense at a given location.
Dr Purushottam added that India must address both low-carbon cement and construction waste together. “Both low-carbon cement and C&D waste go hand in hand. India does not have an option but to work on both,” she said.
Dr Aiyer called for policy shifts from both government and industry, including preferential purchasing of sustainable materials, minimum supplementary cementitious material requirements in public and public-private projects, and faster regulatory implementation. “If we can fast-track the regulatory standards and their implementation on the ground, that is the way to go,” he said.
From green ambition to green construction
Cement innovation is no longer only about chemistry. It is about systems. Low-carbon cement will scale only when technology, standards, procurement, finance, regulation, education and construction practice move together.
LC3 and other low-carbon technologies have shown promise. India has early commercial examples, strong research capability and growing market interest. But mainstream adoption will depend on whether demand can be created, regulators can be capacitated, standards can be embedded in procurement, and manufacturers can see a clear business case.
For a country building at India’s scale, the opportunity is enormous. Cement will continue to be central to infrastructure and urban development. The challenge now is to ensure that the cement used in India’s growth story carries a lower carbon burden.
- Rakesh Rao
Participate in Cement Expo 2026 and discover how next-gen infrastructure can be built with innovations in cement.
Concrete
JK Cement Declared Preferred Bidder For Gilund Limestone Block
Shares Edge Higher As Company Wins Rajasthan Block
Published
3 days agoon
June 30, 2026By
admin
JK Cement gained after being declared preferred bidder for the Gilund Limestone Block in Chittorgarh, Rajasthan, a lease area of 370.96 hectares. The firm saw its shares trade at Rs. 5550.05, up by 28.45 points or 0.52 per cent from the previous close of Rs. 5521.60 on the BSE. The scrip opened at Rs. 5569.15 and touched a high of Rs. 5625.00 and a low of Rs. 5531.00.
The stock recorded turnover of 1742 shares on the counter and the BSE group A stock with face value Rs. 10 has a 52 week high of Rs. 7565.00 on 20-Aug-2025 and a 52 week low of Rs. 4670.05 on 12-Jun-2026. Last one week high and low stood at Rs. 5625.00 and Rs. 5329.00 respectively. The promoters holding in the company stood at 45.66 per cent, while institutions and non-institutions held 40.61 per cent and 13.73 per cent respectively.
The e-auction conducted by the Government of Rajasthan resulted in the company being declared preferred bidder for the mining lease, and the allocation will enable the company to plan phased development of the deposit, subject to regulatory approvals. The Gilund block spans 370.96 hectares and its allocation is intended to support raw material security for the company’s cement operations in the region. The designation follows the government auction process and will allow the company to plan development and integration of the deposit into its supply chain.
The current market capitalisation stands at Rs. 430.38 billion (bn), reflecting market response to the mining news and prevailing valuation levels for the sector. Investors and analysts will watch for formal allotment and related disclosures that can clarify timelines, capital expenditure and expected production profiles. The report is intended for informational purposes and does not constitute investment advice, and market participants are advised to consult advisers before making decisions.
Akhoya Gets New 2.2 Km Road Link Under SASCI
Green Construction Through Cement Innovation
JK Cement Declared Preferred Bidder For Gilund Limestone Block
Star Cement Named Preferred Bidder For Boro Lakhindong Block
KERC Proposal To Cut Rooftop Solar Export Tariff Raises Concern
Akhoya Gets New 2.2 Km Road Link Under SASCI
Green Construction Through Cement Innovation
JK Cement Declared Preferred Bidder For Gilund Limestone Block
Star Cement Named Preferred Bidder For Boro Lakhindong Block

