My first real project was one such. I was just two years out of engineering college, a mechanical engineer raring to have a go at the world. I was fortunate that I got a job in a well-known engineering and projects company, (at a very princely salary of Rs 700 per month, by the way!) and I spent the first two years on the shop floor in a heavy engineering workshop, where no two jobs were alike, no two machine tools were identical, and no two people thought or acted similarly. It was diversity at its best ever, as you can possibly see, and every hour, every day of it was worthwhile. It was here, that one night while I was on night shift duty in the machine shop, I took a break to go into the adjacent central office and typed out a three page letter addressed to the Managing Director, giving detailed suggestions on how the graduate engineers training scheme could be improved. But, that is another story, for another day.

Let us come back to the project story, for now. The year was 1981, I would guess. Without naming the project and the customer, let me just say that it was a hi-tech metallurgical project, being installed for the first time in India in an integrated steel plant, valued at approximately Rs 4 to 5 crore. This was being executed in collaboration with a famous German company. After two years of a good grind in the machine shop floor, I was given the role of a project coordinator in this project, operating initially from the Kolkata Project and Engineering Office, and then moving to site once erection work started. This is when all hell broke loose. This is where we proved beyond an iota of doubt that Mr Murphy was an optimist, because here everything went wrong, and more! I remember that we used to lament that everything that we engineered, manufactured or purchased for this project, gave trouble of some kind or other at site, starting from anti-static floor-mats to Programmable Logic Control Panels, from foundation bolts to hydraulic actuators.

Talking about foundation bolts, this is an item often forgotten, probably because it falls ??etween the stools??of scope of supply of the Supplier and the Erector and the Civil Contractor. First thing we found at site when kicking off erection work, was that the foundation bolts were missing, no one delivered them. It took a few days of running around to get the whole set manufactured, and things got delayed in the process. Today, the first thing that I check in a project, (always, everytime) is have the anchor bolts and inserts been delivered. That was lesson number one!

An anecdotal account of all the pitfalls we encountered at this project site, would have surely made absorbing reading, but sadly, it is somewhat difficult to recall full details of 30 year old incidents. However, some such snippets are still etched in mind.

Another freak problem was, that of fast uncontrolled descent of 25 tonne fabricated vacuum covers, when they were being stopped electrically at the end of the lift. This was due to the few milliseconds of delay of braking through electro-hydraulic thrustor brakes, but the free fall of the heavy covers was really scary. We solved this one at site by installing electro-mechanical timers in the motor circuit, such that motor is stopped with a delay, after the brake gets the signal. I personally loved this one, and that is why I may not forget this incident ever in my lifetime!

Hydraulics were an important part of the project, not only for actuation, but also for fine controls. There were several Moog Control valves with closed loop electronics, and obviously, there were special low-micron high pressure filters upstream of these valves. These were in addition to normal coarse filters in the circuit, as well as LP filters on return line, and recirculating filtration circuits. When we started testing and trial operations of the hydraulics, after thorough cleaning/pickling/pressure test etc, the HP filters started getting choked frequently, and soon we had consumed all spare filter cartridges, which were imported as two years??spares! This, despite the fact that the whole hydraulic Power System along with the Tank were located in a pressurized cellar. What ensued was a lot of study, a lot of data collection, and a lot of consultation with experts. We learnt a lot about selection criteria of hydraulic filters, agglomeration of particulates in hydraulic flow, logjam effect, etc. Ultimately, we zeroed in on a recirculating electrostatic paper filter system, which ran 24×7 in parallel, and brought down the particulate contamination in the tank, of all sizes, to considerably lower levels, and only then the imported HP Filter cartridges started giving long life. This incident made me some sort of an ??xpert??on hydraulic oil filtration.

I know that some the incidents will evoke laughter, but I will still take the risk of narrating the story of the travelling weigh hopper, which refused to travel. This one was a 800 KG capacity load-cell mounted motorised weigh hopper designed to travel on square bar rails, equipped with trailing cable. This hopper was to travel below several bunkers, and receive measured weights of various mineral additives, and then discharge the same into a two chamber vacuum lock. When we did everything right, and switched on the power from local control push button, the small little wheels of the hopper started rotating furiously, but it did not move forward. It was a real hilarious scene. The weight of the hopper was far too less compared to the motor power, and there was inadequate rolling friction for traction to take place. We did a star-delta switch arrangement to reduce the motor power, and it worked beautifully thereafter.

Pages of this issue will fall short of space, if I were to keep talking about all the other problems, related to things like steam ejectors, counter-sunk bolts for liner plates, electro-mechanical actuators, slide gates in ladles, etc., etc, and also, things may become too technical for some of us. The essence is, during design and manufacture phase of a project, we may do many things good or bad, right or wrong, but all of these come home to roost at site, during installation. No more can the problems or mistakes be overlooked or avoided, they have to be resolved then and there, and otherwise work will stall. In that way, Erection at site is the last bit of execution, which is unforgiving, merciless. Here, at site, none of the time-tested strategies like ??assing the buck?? ??elaying/postponing?? ??kirting the issue?? etc work. Here, one has to catch the proverbial bull by the horn and find a solution and implement the solution as soon as possible. Of course, this is the reason why site work is so interesting, at the same time so much more full of adrenalin, action and tension. On hindsight, I liked it. And my advice to young project managers is that they should not miss an opportunity to work at installation sites, particularly if the project is ??irst of its kind in the country?? One or two years of work at site is like five years in the air-conditioned office, in terms of enriching experience of problem solving and project management.

– SUMIT BANERJEE

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Concrete

UltraTech Cement Expands in Andhra Pradesh with Rs. 26.5 bn

Petnikota plant adds 3.6 MTPA cement dispatch capacity

Published

on

By

Shares

UltraTech Cement has expanded its manufacturing footprint in Andhra Pradesh with the commissioning of Petnikota Cement Works, an integrated cement plant built with an investment of around Rs. 26.5 bn. The facility is located in Petnikota village in Kolimigundla mandal of Nandyal district, in the Rayalaseema region.

Construction of the plant began in May 2025. The facility has a clinkerisation capacity of 3.3 MTPA and a cement dispatch capacity of 3.6 MTPA, strengthening the company’s production and distribution presence in the State.

The plant is expected to provide direct employment to 650 people and indirect employment to another 2,000. It has been designed to operate entirely on green energy and does not have a captive thermal power plant. The project also uses no groundwater, according to information released by the Andhra Pradesh Government.

Nara Lokesh, Andhra Pradesh Minister for Information Technology, said in the release that the facility was taken from groundbreaking to commissioning in 14 months. He described the project as a state-of-the-art addition to the company’s operations in the State and said it would create 2,650 direct and indirect employment opportunities.

Petnikota Cement Works adds to UltraTech Cement’s manufacturing capacity in Andhra Pradesh while supporting industrial activity in Nandyal district. The plant’s energy design and stated groundwater-use policy are also intended to reduce the environmental impact of its operations. The company has identified the facility as part of its continuing capacity expansion in the Indian cement market.

Continue Reading

Concrete

Nuvoco reports 13.5% revenue growth in Q2 FY27

Cement sales rose 9% to 4.7 MMT, while EBITDA increased 11%.

Published

on

By

Shares
Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.
The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.
On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid renewable energy project in Rajasthan. Once operational, the project is expected to generate about 100 million units of renewable electricity annually. The company expects it to reduce reliance on conventional power sources and improve long-term cost certainty across its Rajasthan operations.
Jayakumar Krishnaswamy, Managing Director, Nuvoco Vistas Corp. Ltd., said, “Q2 FY27 was a testament to resilient execution in a challenging operating environment. Despite intense and erratic rainfall in our key markets, global and regional logistics & supply chain disruptions, and elevated input costs stemming from ongoing geopolitical uncertainty, the Company delivered strong YoY growth in Revenue, EBITDA, and PAT. Our performance reflects the strength of our strategic levers of premiumisation and geographical mix optimisation, which helped realisations amid muted cement prices.”
He added, “During the quarter, the Company achieved a significant growth milestone with the successful commissioning of the 2 MMTPA Grinding Unit at Limla, Surat, underscoring our strong project execution capabilities. This achievement reinforces our confidence in delivering the remaining modules of the Vadraj Cement Project at Kutch and Sachana within the planned timelines. Looking ahead, while we remain mindful of evolving macroeconomic and geopolitical dynamics, we remain focused on operational excellence, accelerating premiumisation, optimising supply chain efficiencies, and executing our growth projects as planned.

Continue Reading

Concrete

Meghalaya Cabinet Approves MCCL Closure, Writes Off Rs. 244.3 mn

Cabinet approves winding up of state-owned cement company

Published

on

By

Shares

The Meghalaya Cabinet has approved the closure and winding up of Meghalaya Cherra Cement (MCCL), a state-owned cement company, with pending liabilities of approximately Rs. 244.3 mn to be written off as part of the process. The decision was announced by Chief Minister Conrad K Sangma on October 13, 2026.

The approved write-off comprises about Rs. 89 mn in sales tax dues and Rs. 155.3 mn in royalty dues. The Cabinet’s decision addresses the liabilities that remained after the company’s operations and enables the government to proceed with its formal closure.

Sangma said employee dues owed by MCCL had been settled in line with the state government’s commitment. The settlement of employee-related liabilities is a key part of the winding-up process and removes outstanding obligations to the company’s workforce.

The Chief Minister explained that MCCL is owned by the government, meaning the pending liabilities would otherwise involve transfers between the state government and its departments. Writing off the dues is intended to simplify the accounting and administrative steps required to complete the closure.

The decision is also intended to ensure that the winding-up does not create an additional financial burden for the state government. With employee payments settled and the sales tax and royalty liabilities addressed through the approved write-off, the Cabinet’s approval marks a further step towards completing the formal closure of MCCL.

The action follows the state government’s decision to discontinue the company and resolve its outstanding obligations through an orderly winding-up process. The approved measures cover the principal liabilities identified for settlement and allow the government to advance the remaining formal procedures associated with closing the state-owned enterprise.

Continue Reading

Video Thumbnail
▶

    SIGN-UP FOR OUR GENERAL NEWSLETTER

    Trending News

    SUBSCRIBE TO THE NEWSLETTER

     

    Don't miss out on valuable insights and opportunities to connect with like minded professionals.

     


      This will close in 0 seconds