Taking Stock of the PAT Thresholds

Published

on

Shares

The Perform, Achieve and Trade (PAT) launched by the Bureau of Energy Efficiency incentivises energy efficiency and consumption, resulting in economic benefits in the long term.

The Indian cement industry is involved in production of several types of cement such as Ordinary Portland Cement (OPC), Portland Pozzolana Cement (PPC), Portland Blast Furnace Slag Cement (PBFS), Oil Well Cement, Rapid Hardening Portland Cement, Sulphate Resisting Portland Cement, White Cement, etc. The Perform, Achieve and Trade (PAT) launched by the Bureau of Energy Efficiency under the Ministry of Power, Government of India, offers an opportunity to the industry to improve its energy efficiency and reduce energy consumption resulting in long term economic benefits in terms of reduced fuel expenditure with trading.

The key goal of the PAT scheme under NMEEE, is to mandate specific energy efficiency improvements for the most energy intensive industries, and further incentivise them to achieve better energy efficiency improvements that are superior to their specified SEC improvement targets. To facilitate this, the scheme provides the option to industries that achieve superior savings to be rewarded with energy saving certificates for the excess savings, and to trade the additional certified energy savings certificates with other designated consumers who can utilise these certificates to comply with their reduction targets. The Energy Saving Certificates (ESCerts) thus issued will be tradable on special trading platforms to be created in the power exchanges.

The Bureau of Energy Efficiency focused on development of normalisation factors so as to normalise the variation of operating parameters in the target year with respect to baseline operating parameters.

Let us look at the baseline energy consumption parameters taken for consideration before the normalisation thresholds were ascertained: It would be worthwhile to see how the industry has progressed against this baseline scenario for Thermal Energy Consumption and Electrical Energy Consumption as identified by the Bureau of Energy Efficiency.

The CII Energy Efficiency Audit conducted over several cement manufacturing units in 2018, provides us with the state of energy efficiency improvements achieved by the Indian industry stalwarts. While the names of the best individual performers have been kept undisclosed, we can at least see the top performing assets and the corresponding efficiencies they have achieved. The CII Report Energy Benchmarking (2019) has given the following data of the top best performing Cement Kilns in terms of Energy Consumption (CII Tables 4.1, 4.2, 4.3 and 4.3 – page 30).

The data shows improvement in the energy efficiency, both in the electrical as well as in the thermal area. But this shows the top ten performers doing better than the benchmark values set in 2007- 10. However, we do not know what the average data for the industry is. CII has taken up many energy efficiency improvement projects for implementation with the industry and many of them have been implemented. The gap identified for Electrical efficiency is as follows:

Waste Heat Recovery (WHR) systems on the other hand has given major savings in energy and remains the major focus area for adoption to reduce the electrical energy and related emission. The economics of putting up a captive power generating unit versus putting up a WHR system shows unique advantages for cost reduction. The capital investment for waste heat recovery systems is high at Rs 8 Cr /MW going by the current costs, whereas the CPP units can come at Rs 4.5 cr/MW; however, the project IRR would be very different as the cost of generation would be as low as Rs 0.40 per unit for the former while Rs 4.5 per unit for the latter, which given the current trajectory of fossil fuel prices is already under severe stress of upward correction. It is only the initial cost that continues to act as a deterrent for putting up a WHR unit.

The Indian cement industry must act responsibly and move quickly to put in investments that could raise the WHR installed capacity to cross the minimum threshold of 25 per cent of electricity consumption. That will still be far from the 20 billion KWhr of total electricity consumption by the industry.

The other area of concern is the price trajectory of fossil fuels, which would continue to move northwards. The WHR systems are one simplest way of insulating the industry from the vagaries of future price increases.

Thus, waste heat recovery systems could be the natural hedge to fossil fuel price increases for a substantial portion of the electrical consumption. As matters stand, most WHR systems would be the highest IRR projects that the industry as an ensemble can think of today.

Concrete

BMC Cement Concretisation Cuts Pothole Repairs By 70 Per Cent

Project worth Rs 170 billion (Rs 170 bn) aims to concretise 1,900 km by 2027

Published

on

By

Shares



The Brihanmumbai Municipal Corporation’s cement concretisation project, valued at Rs 170 billion (Rs 170 bn), has reduced expenditure on pothole repairs by 70 per cent over three years. Spending on repairs fell from Rs 2.02 billion in 2023–24 to Rs 1.56 billion in 2024–25 and then to Rs 890 million (Rs 890 mn) in 2025–26. The current tender is expected to be about Rs 440 million, representing a further 50 per cent reduction.

The project is being executed in two phases, with Phase I covering 307 km from October 2023 and Phase II covering 370 km from October 2024. The Indian Institute of Technology is auditing Phase II and will now also audit Phase I to ensure quality and accountability. Mumbai’s total road network spans approximately 2,050 km, of which about 1,200 km had been converted to cement concrete before 2022.

Since 2022 an additional 677 km were taken up for concretisation and nearly 71 per cent of that work, amounting to 481 km, has been completed. Municipal officials indicated that 10–15 per cent of the remaining work is expected to be completed by May 2026 and another 10 per cent by December 2026. The entire programme is scheduled for completion by May 2027, by which time nearly 1,900 km of Mumbai’s roads are expected to be fully concretised.

The administration has also developed a real time dashboard that displays detailed information about contracts, contractors and progress and citizens can access the latest updates online. The dashboard includes contact details for the civic officials and contractors responsible for particular roads to enhance transparency and accountability. The commissioner directed that ongoing works be completed by 31 May ahead of the monsoon to safeguard completion targets and minimise disruption.

Continue Reading

Concrete

Shree Cement Approves Rs 1,800 Crore Meghalaya Plant

Integrated unit to be completed by quarter ending March 2028

Published

on

By

Shares



Shree Cement has approved the establishment of an integrated cement plant in Meghalaya, signalling a targeted capacity expansion to serve regional demand. The board cleared a unit at Village Daistong in East Jaintia Hills District with a clinker capacity of zero point nine five million tonnes per annum (mn t) and a cement capacity of zero point nine nine million tonnes per annum (mn t). The project was approved on April four, 2026 and is designed as a new addition to the company’s production network where it currently has no existing plant.

The company has earmarked an estimated investment of Rs 1,800 crore (Rs 18 billion (bn)) for the project, which will be financed through a mix of internal accruals and debt. Management has indicated a balanced financing strategy to preserve cash flows while supporting long-term growth and operational investment. The financing approach is intended to avoid over reliance on external borrowing and to maintain financial discipline during the build out.

The plant is expected to improve logistics efficiency and compress distribution distances to emerging demand centres in the north-east, potentially lowering transportation costs and lead times. By locating production closer to demand the company aims to strengthen market access and respond more effectively to regional construction activity. The project forms part of a broader strategy to diversify the production base across geographies and reduce concentration risk.

Execution is planned over a multi-year window with completion targeted by the quarter ending March 2028 and the company will proceed with construction and requisite regulatory clearances. The integrated design is intended to enhance operational control and production efficiency once operational. The decision follows a regulatory filing dated April four, 2026 and the disclosed details have not been independently verified.

Continue Reading

Concrete

WCA Welcomes SiloConnect as associate corporate member

Published

on

By

Shares

The World Cement Association (WCA) has announced SiloConnect as its newest associate corporate member, expanding its network of technology providers supporting digitalisation in the cement industry. SiloConnect offers smart sensor technology that provides real-time visibility of cement inventory levels at customer silos, enabling producers to monitor stock remotely and plan deliveries more efficiently. The solution helps companies move from reactive to proactive logistics, improving delivery planning, operational efficiency and safety by reducing manual inspections. The technology is already used by major cement producers such as Holcim, Cemex and Heidelberg Materials and is deployed across more than 30 countries worldwide.

Continue Reading

Video Thumbnail
â–¶

    SIGN-UP FOR OUR GENERAL NEWSLETTER


    Trending News

    SUBSCRIBE TO THE NEWSLETTER

     

    Don't miss out on valuable insights and opportunities to connect with like minded professionals.

     


      This will close in 0 seconds