RUPESH KUMAR explains why it is important to control concrete temperature and how it can be done.
With mega structures coming up every?where using high-grade concrete, the control of concrete temperature is become a matter of frequent discu?ssion among civil engineers.

The concern
Green concrete, the nascent stage of concrete hardening, requires a lot of care to mature as good concrete. Concrete is weak in tension bearing; more so, in the initial stage of hardening. Its vulnerability becomes more critical when there are tensile forces induced owing to the hardening process. Being an exothermic reaction, heat is generated during the process; this causes thermal differential and stress that act as a tensile force and cause cracks.

In many cases, cracks developed at the initial stages do not heal and remain or widen further as the concrete shrinks during further hardening. This leads to a situation where structural stability, integrity and durability begin to get compromised. The following observations can be made in the early days of concrete, primarily in the first week:

  • Concrete matures with time and temperature.
  • Strength comes with maturity.
  • In seven days, almost 2/3 of 28 days strength gain for OPC cement-based concrete is expected, though this can vary according to the design mix.
  • The exothermic chemical reaction is most active during this period.
  • Thermal gain is achieved to its maximum during this period; concrete core temperature starts declining after reaching its peak in most cases.
  • Core temperature rise causes thermal differential and stress in concrete.
  • The higher the temperature, faster the maturity. But early higher temperature leads to a greater tendency to crack internally, owing to higher thermal stress. Increasing temperature in the early days has shown more strength on the seventh day and less on day 28 compared to standard maturity of concrete on day seven and 28 respectively, owing to thermal micro-cracking.
  • Concrete plastic shrinkage and initial shrinkage are more dominant during this period and slow down with time. Late shrinkage can continue for many months but the effect is not so significant as the concrete strength is able to counteract the stress of late shrinkage in most cases.
  • Cracks developed during the initial stage owing to plastic shrinkage may not heal automatically in further maturity. On the contrary, at times the crack increases in width, depth or both with time, owing to shrinkage stress acting as a localised tensile force.
  • Cracks develop when the tensile stress increases more than the tensile bearing capacity of the concrete.
  • If the concrete does not gain sufficient strength during the peak concrete temperature, and specifically during higher thermal differential, there is higher likelihood of cracking.
  • The peak temperature of concrete and the thermal differential depends on the green concrete temperature as well as the ambient temperature along with shuttering (temporary formwork) condition.
  • The heat gain in the concrete for a given design mix is the same; thus, the green concrete has a direct effect on the heat gain and rise in concrete core temperature. The higher the green concrete temperature, higher the core peak temperature, and vice versa.
  • The thermal differential causes the stress in the concrete and core to the surface temperature of the concrete must be kept in controlled condition to control the differential. However, the peak temperature of the core beyond a limit may cause other long-term effects like DEF (delayed ettringite formation; a matter yet to be ascertained codally) and needs to be addressed. In Indian tropical conditions, DEF is not expected to be of serious concern if the temperature is taken care of to limit peak temperature below 70?and pozzolanic material is used in the mix. However, thermal differential of concrete must be an area of focus for durable concrete.

Green concrete temperature
The temperature control limits of green concrete are specified in various codes and they all vary. There are references for RCC green concrete temperature for below 40?, up to 38? up to 32?, up to 30? and up to 25? in various codes, including BIS, BS and ASTM.

With higher grades of concrete, the maximum allowable core temperature restrictions are of higher consideration, which restrict the green concrete temperature less than what is allowed in the codes.

To restrict the peak temperature, the green concrete temperature is asked to be reduced. In such a specific scenario, a holistic approach should be taken to define the green concrete temperature as lowering the temperature is a costly affair – although it is not intended to compromise the strength and durability of the concrete. Care should be taken as green concrete temperature control requires a broader approach than simply lowering the temperature during production; it should first be ascertained whether it is really required. It is more prudent to have higher temperature rather than more thermal differential. Also, the lower temperature should be sustained – not less at any one stage of the concrete production, transportation, placement and construction. Further, thermal consideration of concrete is more important for mass concrete than smaller sections.

Way to set concrete temperature limit
To understand the thermal consideration for a given concrete in a project, a preliminary test should be done to arrive at the initial data. Except generally established limits, at present, the codes have not established the procedure for review and analysis of concrete temperature acceptance for a given scenario. A procedure with the action points mentioned below can be used to logically arrive at a calculation analysis and mock-up review to arrive at the concrete temperature acceptance for the given scenario. Some important questions to ask during calculation analysis and mock-up testing are:

How does the concrete temperature rise with time and when the peak temperature is reached for a given mix? For this, a thermal probe can be inserted before placing the concrete and recoding can be done using a thermal data logger. Alternatively, manual set-up and reading can be done, but manual recoding is tedious. The data can be recorded or plotted and analysed.

What is the design calculation with consideration of thermal stress and the crack width allowed as per the design? The data can be obtained from the design calculation sheet or designer.

How is the reinforcement as per the design of the structure and is it able to take the stress developed in the concrete owing to thermal stress? The designer can confirm this and reinforcement adequacy for taking additional thermal stress can be checked considering the crack width limitation as per the design calculation.

How is the maturity of concrete and subsequently the strength of concrete with respect to time? The data can be obtained by taking additional sufficient concrete samples and keeping them under standard testing condition. Curing tank temperature can be taken if the temperature is not being maintained in the curing tank. Testing of concrete sampling shall be done as per testing the procedure at various durations.

Is there any crack observed in the mock up and is there is any crack owing to thermal stress and not plastic shrinkage? To avoid plastic shrinkage, the mock shall preferably be for an adiabatic condition for unreinforced, 1 cu m of mass or miniature replica of the actual structure.

Close observation is required to check crack development; if required, a core can be taken to check the inside of the concrete mass. Normally, thermal stress if developed and causing a crack inside, will reflect up to the surface as the surface to core thermal differential is expected to be more than the thermal differential of the core to the other inner part of concrete. Based on a visual examination, the cracks can be checked.

Now, based on the data mentioned above, one can calculate the estimated concrete temperature and acceptable thermal differential. It can also be analysed whether the concrete is expected to crack beyond the design calculation for the given reinforcement design and estimated concrete peak temperature in the project ambient temperature, and more so for the thermal differential. Then, verification can be done by examining the mock-up concrete.

Thus, one can ascertain whether concrete can sustain the expected peak temperature and thermal differential for a given design mix with reinforcement as per design and ambient condition during construction. In case of non-reinforced concrete (PCC-based structure), reinforcement stress bearing will not be present and the concrete would be able to sustain only as much stress as the maturity of concrete will allow.

About the author
Rupesh Kumar
is a Quality Manager and Concrete Technologist with 18 years of experience working in mega projects in India and abroad. He has dealt with more than 2.5 million cu m of concrete in projects of RMC, hospital, factories, stadium, metros, airports and statue.

This artical was first published in Construction World magazine

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Concrete

UltraTech Cement Expands in Andhra Pradesh with Rs. 26.5 bn

Petnikota plant adds 3.6 MTPA cement dispatch capacity

Published

on

By

Shares

UltraTech Cement has expanded its manufacturing footprint in Andhra Pradesh with the commissioning of Petnikota Cement Works, an integrated cement plant built with an investment of around Rs. 26.5 bn. The facility is located in Petnikota village in Kolimigundla mandal of Nandyal district, in the Rayalaseema region.

Construction of the plant began in May 2025. The facility has a clinkerisation capacity of 3.3 MTPA and a cement dispatch capacity of 3.6 MTPA, strengthening the company’s production and distribution presence in the State.

The plant is expected to provide direct employment to 650 people and indirect employment to another 2,000. It has been designed to operate entirely on green energy and does not have a captive thermal power plant. The project also uses no groundwater, according to information released by the Andhra Pradesh Government.

Nara Lokesh, Andhra Pradesh Minister for Information Technology, said in the release that the facility was taken from groundbreaking to commissioning in 14 months. He described the project as a state-of-the-art addition to the company’s operations in the State and said it would create 2,650 direct and indirect employment opportunities.

Petnikota Cement Works adds to UltraTech Cement’s manufacturing capacity in Andhra Pradesh while supporting industrial activity in Nandyal district. The plant’s energy design and stated groundwater-use policy are also intended to reduce the environmental impact of its operations. The company has identified the facility as part of its continuing capacity expansion in the Indian cement market.

Continue Reading

Concrete

Nuvoco reports 13.5% revenue growth in Q2 FY27

Cement sales rose 9% to 4.7 MMT, while EBITDA increased 11%.

Published

on

By

Shares
Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.
The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.
On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid renewable energy project in Rajasthan. Once operational, the project is expected to generate about 100 million units of renewable electricity annually. The company expects it to reduce reliance on conventional power sources and improve long-term cost certainty across its Rajasthan operations.
Jayakumar Krishnaswamy, Managing Director, Nuvoco Vistas Corp. Ltd., said, “Q2 FY27 was a testament to resilient execution in a challenging operating environment. Despite intense and erratic rainfall in our key markets, global and regional logistics & supply chain disruptions, and elevated input costs stemming from ongoing geopolitical uncertainty, the Company delivered strong YoY growth in Revenue, EBITDA, and PAT. Our performance reflects the strength of our strategic levers of premiumisation and geographical mix optimisation, which helped realisations amid muted cement prices.”
He added, “During the quarter, the Company achieved a significant growth milestone with the successful commissioning of the 2 MMTPA Grinding Unit at Limla, Surat, underscoring our strong project execution capabilities. This achievement reinforces our confidence in delivering the remaining modules of the Vadraj Cement Project at Kutch and Sachana within the planned timelines. Looking ahead, while we remain mindful of evolving macroeconomic and geopolitical dynamics, we remain focused on operational excellence, accelerating premiumisation, optimising supply chain efficiencies, and executing our growth projects as planned.

Continue Reading

Concrete

Meghalaya Cabinet Approves MCCL Closure, Writes Off Rs. 244.3 mn

Cabinet approves winding up of state-owned cement company

Published

on

By

Shares

The Meghalaya Cabinet has approved the closure and winding up of Meghalaya Cherra Cement (MCCL), a state-owned cement company, with pending liabilities of approximately Rs. 244.3 mn to be written off as part of the process. The decision was announced by Chief Minister Conrad K Sangma on October 13, 2026.

The approved write-off comprises about Rs. 89 mn in sales tax dues and Rs. 155.3 mn in royalty dues. The Cabinet’s decision addresses the liabilities that remained after the company’s operations and enables the government to proceed with its formal closure.

Sangma said employee dues owed by MCCL had been settled in line with the state government’s commitment. The settlement of employee-related liabilities is a key part of the winding-up process and removes outstanding obligations to the company’s workforce.

The Chief Minister explained that MCCL is owned by the government, meaning the pending liabilities would otherwise involve transfers between the state government and its departments. Writing off the dues is intended to simplify the accounting and administrative steps required to complete the closure.

The decision is also intended to ensure that the winding-up does not create an additional financial burden for the state government. With employee payments settled and the sales tax and royalty liabilities addressed through the approved write-off, the Cabinet’s approval marks a further step towards completing the formal closure of MCCL.

The action follows the state government’s decision to discontinue the company and resolve its outstanding obligations through an orderly winding-up process. The approved measures cover the principal liabilities identified for settlement and allow the government to advance the remaining formal procedures associated with closing the state-owned enterprise.

Continue Reading

Video Thumbnail
▶

    SIGN-UP FOR OUR GENERAL NEWSLETTER

    Trending News

    SUBSCRIBE TO THE NEWSLETTER

     

    Don't miss out on valuable insights and opportunities to connect with like minded professionals.

     


      This will close in 0 seconds