Connect with us

Concrete

Rationalising cement plant design

Published

on

Shares

If the capacities are more or less fixed and the variables in plant design lie in a narrow range, then why can?t we have standard modular cement plants?
In the recent past, very few cement projects have been announced and taken up for implementation. India?s investment growth, which was quite robust during the last decade, has fallen substantially in the last two years. Several reasons have been attributed for this present dearth of ongoing cement projects; policy uncertainty, delayed project approvals, land acquisition issues, economic slowdown leading to uncertain markets, high interest rates, supply side bottlenecks, et al. Irrespective of whether it is due to some or all of these reasons, the fact remains that the commencement of any and every cement project today, is considerably delayed from earlier times. It therefore becomes necessary to reduce and crash project implementation timelines to ensure that revenue flows start as soon as possible. Quite often, the viability of a project may hinge on this.
The design and engineering of a cement plant can play a significant role in reducing project times, but this can only be achieved with proactive cooperation and teamwork between the customer, technology supplier and the designer.

The typical cycle
In a typical project plan of a cement plant, it is generally accepted that the time between the placement of the first major purchase order and first excavation at site is at least six months, provided the customer places an EPC order on a major cement machinery supplier having adequate resources for carrying out simultaneous engineering on multiple streams. If, on the other hand, the customer opts to place individual equipment orders on OEMs, this time period could stretch to anywhere between eight to eleven months. In the equipment ordering mode, it is the customer who bears the responsibility of coordination between the OEMs, the consultant and the contractors at site.

The purpose of this article is to stimulate some out-of-the-box thinking to evaluate and check if even the accepted six months between the first purchase order and first excavation, can be reduced further. We shall not attempt this in the case of equipment ordering mode as the intense coordination, required between customer, OEMs and the consultant for even the first release of construction drawings, shall automatically ensure delays.

Common patterns
Let us start with the future sizes of cement plants. Today, most of the large limestone deposits in India have been either tied up or already exploited. The existing deposits are far away from urban centres, which are the large consumers of cement. It is therefore likely that the days of 10,000 tpd plus cement plants are over, and that the plants of the future are likely to be in the 5,000 to 7,000 tpd range. This size will help in exploiting smaller deposits, which are also likely to be more accessible from a logistics point of view. While this article does not rule out the large plants completely, it is our contention that the majority of the plants of the future are likely to be in the 5,000 to 7,000 tpd range.

With the need to cover the stockpiles, all the material storages will have to be either silos or longitudinal storages. The storage capacities of these stockpiles in terms of number of days for various materials like limestone, additives, clinker, coal and gypsum are also fairly standardised.

Most of the deposits today are located away from existing railway lines. Thus, the primary mode of transport of materials to and from the plant is likely to be road. Most plants are located on fairly flat ground and minor undulations in the ground are levelled off and the plinth levels of all the process buildings in the plant are usually considered at one level.

The systems ultimately selected by most customers are also fairly standard. Vertical roller mills for raw and coal grinding, reverse air bag houses for de-dusting of kiln gases, six stage pre-heaters, three support kilns, coolers, ESPs for cooler gases and clinker tanks for clinker storage, are the norm for most plants. The central portion of the plant, which is considered the heart of the cement plant stretching from the raw mill, through the blending silo, pre-heater, kiln, cooler up to the clinker silo, are usually laid out in a straight line.

Hence, one can see that the so-called ?variables? in a cement plant generally lie within a narrow band of values, and can therefore be frozen at an optimum value. And this brings us to the central question of this article. Why are all cement plants today designed from first principles, going through the motions of obtaining equipment drawings from the OEMs, preparing general arrangement drawings of the process buildings and designing the civil structures to finally produce construction drawings?

It is suggested for the technology suppliers and the EPC contractors to get together and pre-engineer the plants to be ready with at least the general arrangement drawings and a portion of the civil design of the main process buildings. If the 3D models of the buildings are made ready, the site conditions, which vary from site to site, can be factored in and the required analysis can be done expeditiously.

Standard solutions to save time
The idea is to standardise and modularise the heart of the cement plant such that the final general arrangement drawings are ready before the customer orders the plant. It can be seen that, for a particular plant size, at the most, three sizes of raw mills will be sufficient to handle the variations in the grindability of different types of limestone. An additional fourth size means that the next plant size can be catered to. Three sizes each of blending and clinker silos will suffice to fulfil most customer requirements, for two plant capacities, 5,000 and 7,000 tpd. The cyclone pre-heater, kiln, cooler and coal mill sizes are usually decided once the rated capacity of the plant is frozen. The layout of the modules can be prepared in such a manner that it is possible to remove a module of one size and plug in one of another size without affecting the rest of the layout.

Thus, most of the engineering related to layouts can be completed earlier and about four to six weeks can be saved from the six months for engineering as mentioned earlier. This is possible only in an EPC mode of ordering. When the customer chooses to order the plant as individual equipment or even as packages, there is a certain amount of sequencing that gets inherently built in to the project management process. In this case, the customer becomes the hub and the rest of the stakeholders, the spokes. Every major activity between the stakeholders needs to be ratified or approved by the customer, thus inserting points of delay in the entire process. In EPC mode, this coordination between receipt of equipment drawings, preparation of general arrangement drawings and civil design happens internally with the customer being kept in the loop at all times. While the customer can interject whenever necessary, the mandatory customer approval, that is required in the other modes, does not hinder or delay the process. The customer thus manages the project by exception.

Another area that frequently remains unaddressed is rationalisation or streamlining. When the plants are ordered in package mode, the customer attempts to bring together the OEMs, the consultant and the civil and mechanical contractors, and hopes that between them, they will put together the most cost-effective plant. But if one looks at the post-order value drivers for the stakeholders, none of them have a genuine interest in reducing wasteful civil quantities. The OEMs and consultant are interested in reducing the man-hours they spend on the project, to cut their costs. The contractors are paid per cubic metre of concrete or tonne of steel and do not have a say in rationalising the layouts or civil designs. That is why, at the end of a project, most customers have a nagging In an EPC mode, the EPC contractor is simultaneously responsible for layouts and civil design. He is in a better position to bring about rationalisation of the plant. An added advantage is that site queries that usually crop up during construction are handled more expeditiously because the civil design is in-house. But that advantage is not relevant here.

If pre-engineering, as suggested above, is also carried out, the EPC contractor has more time to rationalise and can therefore do a better job. The customer needs to play a significant role in this process. Tempting as it may be, he needs to curb the natural tendency to make changes in the pre-engineered layouts. Changes to be incorporated will set back the process several steps and squander away the time gains expected from this approach.

To summarise
If cement plant sizes can be standardised to some popular capacities, it is possible for EPC contractors to modularise the main process sections and pre-engineer some of the critical paths in the project in order to save valuable project implementation time.

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Concrete

Cement Makers’ Margins To Fall Rs 50-75 Per Tonne Amid West Asia Conflict

Crisil Sees Margins Easing Despite Steady Demand

Published

on

By

Shares

Crisil said operating margins of Indian cement manufacturers are expected to decline by Rs 50-75 per tonne (t) this fiscal to Rs 925-950 per t due to higher input costs triggered by the West Asia conflict. The analysis covered 18 cement companies accounting for nearly 90 per cent of India’s domestic cement capacity and noted margins had improved sharply to around Rs 1,000 per t in fiscal 2026.

Crisil noted that the reduction would be driven mainly by higher power and fuel costs, which account for about 30 per cent of total costs, as petcoke and imported coal prices have surged amid geopolitical uncertainties. Freight costs, which account for about a quarter of total costs, are also expected to remain elevated because of higher diesel prices. The impact on profitability is likely to be more pronounced in the first half of the fiscal year before easing commodity prices moderate cost pressures later.

The rating agency said steady domestic demand and strong balance sheets should keep credit profiles stable despite the moderation in margins. Green energy currently accounts for 35-40 per cent of the sector’s total electricity consumption and is expected to partly cushion higher energy costs. Operating cash flows are likely to remain resilient, supported by projected 6-7 per cent growth in cement demand this fiscal.

Crisil highlighted that demand growth will be driven primarily by infrastructure spending, which meets about one-third of sector consumption, and by a nearly 18 per cent higher budgetary allocation for core ministries that should support project execution. Weaker rural housing demand amid pressure on agricultural incomes from a possible below-average monsoon may be offset by improved urban housing demand supported by favourable home-loan rates and a strong pipeline of Pradhan Mantri Awas Yojana-Urban projects. Ongoing capacity additions will keep capital expenditure elevated and may lift net debt to EBITDA to between 1.2 and 1.4 times from around 1.0 time last fiscal, though ratios are expected to remain healthy.

Continue Reading

Concrete

UltraTech Board Approves Rs 50 bn Fundraise Via NCDs

Company to issue half a million debentures for expansion plan

Published

on

By

Shares

UltraTech Cement’s board of directors has approved raising Rs 5,000 crore (Rs 50 bn) through non?convertible debentures issued in rupees.

The finance committee cleared a proposal to issue up to 500,000 fully paid, unsecured, listed, rated, redeemable, rupee?denominated, non?convertible, non?cumulative debentures of Rs 1 lakh each (Rs 0.1 mn each), aggregating to the Rs 5,000 crore programme.

As of June 2026 the firm reported net debt of Rs 15,875 crore (Rs 158.75 bn) and said its capacity expansion projects under execution are backed by capital expenditure of about Rs 17,000 crore (Rs 170 bn) over the next two to two?and?a?half years.

UltraTech spent Rs 9,500 crore (Rs 95 bn) on capital expenditure in financial year 2026 and in April the group crossed 200.1 mn tonnes per annum of domestic grey cement capacity and 205.5 mn tonnes per annum of global capacity.

The chief financial officer indicated the company would take consolidated capacity beyond 242 mn tonnes per annum, with grey cement capacity reaching 212.7 mn tonnes per annum by the end of financial year 2027. He noted the net debt?to?earnings before interest, taxes, depreciation and amortisation ratio stood at 0.87 times as of June 2026 and the company was confident of ending financial year 2027 with the ratio below one time.

In the first quarter of financial year 2026?27 UltraTech’s net profit attributable to owners rose 16.8 per cent year?on?year to Rs 2,599.3 crore (Rs 25.993 bn) and revenue from operations increased 15.9 per cent to Rs 24,648.20 crore (Rs 246.482 bn). The board approval is expected to complement internal cash flows as the company advances its expansion programme.

Continue Reading

Concrete

Lokesh Lays Stone For Rs 31 Billion Cement Unit In Kadapa

Line-2 expansion to make Kadapa a major cement hub

Published

on

By

Shares

Andhra Pradesh Education and IT Minister Nara Lokesh on Wednesday laid the foundation stone for the Line-2 expansion of Dalmia Bharat Cement at Chinnakomerla village in Mylavaram Mandal in Kadapa district. The project carries an investment of Rs 31 billion (bn) and is slated for completion by the third quarter of the financial year 2028. The expansion is intended to boost industrial growth and employment generation across the Rayalaseema region.

Once commissioned, the Kadapa facility will become Dalmia Bharat’s largest integrated cement manufacturing ecosystem in southern India, creating over 1,000 direct and indirect jobs and opening new business avenues for regional micro, small and medium enterprises and transport operators. Lokesh said the expansion signalled growing corporate confidence in the state and reflected the practical ease of doing business that secured repeat investment.

He placed the project within the government’s wider economic targets and recalled the Yuvagalam padayatra commitment to generate two million (mn) jobs within five years, noting that the state would cultivate talent while industry created opportunities. Lokesh highlighted Andhra Pradesh’s competitive pursuit of major manufacturing accounts, mentioning past successes and a personal initiative to engage global investors when persuading them to anchor expansion in the state.

The plant will leverage Kadapa’s abundant limestone reserves to scale production and sustainability. Clinker capacity is planned to rise from two point five million tonnes per annum (mn tpa) to six point one mn tpa, while overall cement output will increase from three point six mn tpa to nine point six mn tpa. The unit is designed to operate on over eighty per cent renewable energy and deploy waste heat recovery, zero liquid discharge, water recycling and advanced AI systems to optimise efficiency. Industries Minister TG Bharat, BC Welfare Minister S. Savitha and Jammalamadugu MLA C. Adinarayana Reddy attended the ceremony.

Continue Reading

Video Thumbnail
â–¶

    SIGN-UP FOR OUR GENERAL NEWSLETTER


    Trending News

    SUBSCRIBE TO THE NEWSLETTER

     

    Don't miss out on valuable insights and opportunities to connect with like minded professionals.

     


      This will close in 0 seconds