Connect with us

Concrete

Rationalising cement plant design

Published

on

Shares

If the capacities are more or less fixed and the variables in plant design lie in a narrow range, then why can?t we have standard modular cement plants?
In the recent past, very few cement projects have been announced and taken up for implementation. India?s investment growth, which was quite robust during the last decade, has fallen substantially in the last two years. Several reasons have been attributed for this present dearth of ongoing cement projects; policy uncertainty, delayed project approvals, land acquisition issues, economic slowdown leading to uncertain markets, high interest rates, supply side bottlenecks, et al. Irrespective of whether it is due to some or all of these reasons, the fact remains that the commencement of any and every cement project today, is considerably delayed from earlier times. It therefore becomes necessary to reduce and crash project implementation timelines to ensure that revenue flows start as soon as possible. Quite often, the viability of a project may hinge on this.
The design and engineering of a cement plant can play a significant role in reducing project times, but this can only be achieved with proactive cooperation and teamwork between the customer, technology supplier and the designer.

The typical cycle
In a typical project plan of a cement plant, it is generally accepted that the time between the placement of the first major purchase order and first excavation at site is at least six months, provided the customer places an EPC order on a major cement machinery supplier having adequate resources for carrying out simultaneous engineering on multiple streams. If, on the other hand, the customer opts to place individual equipment orders on OEMs, this time period could stretch to anywhere between eight to eleven months. In the equipment ordering mode, it is the customer who bears the responsibility of coordination between the OEMs, the consultant and the contractors at site.

The purpose of this article is to stimulate some out-of-the-box thinking to evaluate and check if even the accepted six months between the first purchase order and first excavation, can be reduced further. We shall not attempt this in the case of equipment ordering mode as the intense coordination, required between customer, OEMs and the consultant for even the first release of construction drawings, shall automatically ensure delays.

Common patterns
Let us start with the future sizes of cement plants. Today, most of the large limestone deposits in India have been either tied up or already exploited. The existing deposits are far away from urban centres, which are the large consumers of cement. It is therefore likely that the days of 10,000 tpd plus cement plants are over, and that the plants of the future are likely to be in the 5,000 to 7,000 tpd range. This size will help in exploiting smaller deposits, which are also likely to be more accessible from a logistics point of view. While this article does not rule out the large plants completely, it is our contention that the majority of the plants of the future are likely to be in the 5,000 to 7,000 tpd range.

With the need to cover the stockpiles, all the material storages will have to be either silos or longitudinal storages. The storage capacities of these stockpiles in terms of number of days for various materials like limestone, additives, clinker, coal and gypsum are also fairly standardised.

Most of the deposits today are located away from existing railway lines. Thus, the primary mode of transport of materials to and from the plant is likely to be road. Most plants are located on fairly flat ground and minor undulations in the ground are levelled off and the plinth levels of all the process buildings in the plant are usually considered at one level.

The systems ultimately selected by most customers are also fairly standard. Vertical roller mills for raw and coal grinding, reverse air bag houses for de-dusting of kiln gases, six stage pre-heaters, three support kilns, coolers, ESPs for cooler gases and clinker tanks for clinker storage, are the norm for most plants. The central portion of the plant, which is considered the heart of the cement plant stretching from the raw mill, through the blending silo, pre-heater, kiln, cooler up to the clinker silo, are usually laid out in a straight line.

Hence, one can see that the so-called ?variables? in a cement plant generally lie within a narrow band of values, and can therefore be frozen at an optimum value. And this brings us to the central question of this article. Why are all cement plants today designed from first principles, going through the motions of obtaining equipment drawings from the OEMs, preparing general arrangement drawings of the process buildings and designing the civil structures to finally produce construction drawings?

It is suggested for the technology suppliers and the EPC contractors to get together and pre-engineer the plants to be ready with at least the general arrangement drawings and a portion of the civil design of the main process buildings. If the 3D models of the buildings are made ready, the site conditions, which vary from site to site, can be factored in and the required analysis can be done expeditiously.

Standard solutions to save time
The idea is to standardise and modularise the heart of the cement plant such that the final general arrangement drawings are ready before the customer orders the plant. It can be seen that, for a particular plant size, at the most, three sizes of raw mills will be sufficient to handle the variations in the grindability of different types of limestone. An additional fourth size means that the next plant size can be catered to. Three sizes each of blending and clinker silos will suffice to fulfil most customer requirements, for two plant capacities, 5,000 and 7,000 tpd. The cyclone pre-heater, kiln, cooler and coal mill sizes are usually decided once the rated capacity of the plant is frozen. The layout of the modules can be prepared in such a manner that it is possible to remove a module of one size and plug in one of another size without affecting the rest of the layout.

Thus, most of the engineering related to layouts can be completed earlier and about four to six weeks can be saved from the six months for engineering as mentioned earlier. This is possible only in an EPC mode of ordering. When the customer chooses to order the plant as individual equipment or even as packages, there is a certain amount of sequencing that gets inherently built in to the project management process. In this case, the customer becomes the hub and the rest of the stakeholders, the spokes. Every major activity between the stakeholders needs to be ratified or approved by the customer, thus inserting points of delay in the entire process. In EPC mode, this coordination between receipt of equipment drawings, preparation of general arrangement drawings and civil design happens internally with the customer being kept in the loop at all times. While the customer can interject whenever necessary, the mandatory customer approval, that is required in the other modes, does not hinder or delay the process. The customer thus manages the project by exception.

Another area that frequently remains unaddressed is rationalisation or streamlining. When the plants are ordered in package mode, the customer attempts to bring together the OEMs, the consultant and the civil and mechanical contractors, and hopes that between them, they will put together the most cost-effective plant. But if one looks at the post-order value drivers for the stakeholders, none of them have a genuine interest in reducing wasteful civil quantities. The OEMs and consultant are interested in reducing the man-hours they spend on the project, to cut their costs. The contractors are paid per cubic metre of concrete or tonne of steel and do not have a say in rationalising the layouts or civil designs. That is why, at the end of a project, most customers have a nagging In an EPC mode, the EPC contractor is simultaneously responsible for layouts and civil design. He is in a better position to bring about rationalisation of the plant. An added advantage is that site queries that usually crop up during construction are handled more expeditiously because the civil design is in-house. But that advantage is not relevant here.

If pre-engineering, as suggested above, is also carried out, the EPC contractor has more time to rationalise and can therefore do a better job. The customer needs to play a significant role in this process. Tempting as it may be, he needs to curb the natural tendency to make changes in the pre-engineered layouts. Changes to be incorporated will set back the process several steps and squander away the time gains expected from this approach.

To summarise
If cement plant sizes can be standardised to some popular capacities, it is possible for EPC contractors to modularise the main process sections and pre-engineer some of the critical paths in the project in order to save valuable project implementation time.

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Concrete

JSW Cement Commissions 1 MTPA Unit in Rajasthan

Rajasthan grinding capacity rises to 3.50 MTPA after commissioning

Published

on

By

Shares

JSW Cement has commissioned an additional 1 MTPA cement grinding unit in Nagaur, Rajasthan, taking the company’s total cement grinding capacity to 25.1 MTPA. The commissioning was announced on Tuesday, October 6.

The company said the new unit had increased the total cement grinding capacity at its Rajasthan plant to 3.50 MTPA. The expansion adds to JSW Cement’s production infrastructure as it continues to build capacity across its operating network.

The company’s total clinker manufacturing capacity, including capacity at its joint venture JSW Cement FZC, stands at 9.74 MTPA. Clinker is an intermediate material used in cement production, and its availability supports the company’s grinding operations.

JSW Cement is also pursuing a proposed merger of its listed subsidiary Shiva Cement with the company. The scheme, approved by the boards of the respective companies, involves issuing five fully paid-up JSW Cement equity shares for every 41 shares held by Shiva Cement shareholders other than JSW Cement.

The arrangement remains subject to shareholder and regulatory approvals. JSW Cement currently holds 66.23 per cent of Shiva Cement’s paid-up equity share capital, and the shares held by JSW Cement in the subsidiary will be cancelled under the proposal without any issue of JSW Cement shares against that holding.

The scheme has an appointed date of April 1, 2026, and the company has indicated that completion could take 12 to 14 months, depending on the receipt of approvals. These include clearances from stock exchanges, the Securities and Exchange Board of India, the National Company Law Tribunal and other applicable authorities, along with approvals from shareholders and creditors where required. JSW Cement shares closed at Rs. 113.15 on the BSE, up Rs. 2.05, or 1.85 per cent.

Continue Reading

Concrete

Wonder Cement appoints Mahesh Singh as VP Corporate Brand Communication 

Published

on

By

Shares

Singh brings 20+ years of brand and marketing experience, and will lead integrated corporate brand communication initiatives at Wonder Cement 

New Delhi

Wonder Cement, a leading cement manufacturer, has appointed Mahesh Singh as Vice President – Corporate Brand Communication. In his new role, he will oversee corporate brand strategy and communication, including digital and performance marketing, public relations, trade, events, exhibitions, sports and experiential marketing. 

Singh brings over two decades of experience across marketing and communications, with roles spanning the automotive industry, agencies and entrepreneurship. He spent more than a decade with Honda Motorcycle & Scooter India, working across integrated communication, media, digital, retail and consumer engagement. His stint also included helping build the company’s digital marketing capabilities. 

He moved to dentsu X India as Vice President – Strategy & Planning, working across categories such as automotive, auto components, electric vehicles, FMCG, consumer electronics, BFSI, apparel and brand consulting. His responsibilities included media and marketing strategy, product launches, content, performance marketing and consumer activations. 

Singh subsequently took an entrepreneurial route with Radiant Brands before joining Shriram Ltd (SPR Autotech) as Head – Marketing & Communications. There, his remit included brand and corporate strategy, communications, PR and ORM, retail identity, loyalty programmes and events. 

At Wonder Cement, Singh will be responsible for bringing together the company’s corporate brand communication initiatives across digital, performance marketing, PR, trade, sports and experiential platforms. The role will focus on creating an integrated approach to communication across consumers, trade partners and other key stakeholders. 

The appointment brings to Wonder Cement a marketer whose career has spanned the brand, agency and entrepreneurial sides of the communications ecosystem. 

Wonder Cement, part of the RK Group, is a cement manufacturer with roots in Rajasthan and a focus on quality, trust and transparency. The company has grown to six manufacturing plants, and a cement capacity of 21.5 MTPA. With more than 2,000 employees and a network of over 5,000 dealers, its operations span manufacturing, distribution and customer engagement, with a focus on consistent product quality and efficient execution. 

Continue Reading

Concrete

JSW Cement commissions additional 1 MTPA grinding unit in Rajasthan

The Nagaur expansion takes JSW Cement’s total grinding capacity to 25.10 MTPA.

Published

on

By

Shares



JSW Cement has commissioned an additional 1 million tonne per annum (MTPA) cement grinding unit at its Nagaur Integrated Plant in Rajasthan. The commissioning takes the company’s total cement grinding capacity to 25.10 MTPA. 
JSW Cement’s total clinker manufacturing capacity, including its joint venture JSW Cement FZC, now stands at 9.74 MTPA.
The company began operations in North India in March 2026 with the Nagaur Integrated Plant, comprising a 3.30 MTPA clinkerisation unit and a 2.50 MTPA cement grinding unit. With the latest expansion, the plant’s total grinding capacity has increased to 3.50 MTPA.
The additional capacity will cater to cement demand across Rajasthan, Haryana, Punjab and the National Capital Region (NCR). The expansion has been funded through a combination of equity and long-term debt.
During the quarter ended September 30, 2026, JSW Cement also commissioned an Alternate Fuel Handling System and a Waste Heat Recovery System (WHRS) at the Nagaur plant.
Nilesh Narwekar, CEO, JSW Cement, said the additional grinding capacity was a strategic priority for the company’s expansion in North India. He added that the Alternate Fuel Handling System and WHRS were expected to reduce production costs.

Continue Reading

Video Thumbnail
â–¶

    SIGN-UP FOR OUR GENERAL NEWSLETTER

    Trending News

    SUBSCRIBE TO THE NEWSLETTER

     

    Don't miss out on valuable insights and opportunities to connect with like minded professionals.

     


      This will close in 0 seconds