Pankaj Kejriwal, Whole Time Director and COO, Star Cement, on driving efficiency today and designing sustainability for tomorrow.

In an era where the cement industry is under growing pressure to decarbonise while scaling capacity, Star Cement is charting a pragmatic yet forward-looking path. In this conversation, Pankaj Kejriwal, Whole Time Director and COO, Star Cement, shares how the company is leveraging waste heat recovery, alternative fuels, low-carbon products and clean energy innovations to balance operational efficiency with long-term sustainability.

How has your Lumshnong plant implemented the 24.8 MW Waste Heat Recovery System (WHRS), and what impact has it had on thermal substitution and energy costs?
Earlier, the cost of coal in the Northeast was quite reasonable, but over the past few years, global price increases have also impacted the region. We implemented the WHRS project about five years ago, and it has resulted in significant savings by reducing our overall power costs.
That is why we first installed WHRS in our older kilns, and now it has also been incorporated into our new projects. Going forward, WHRS will be essential for any cement plant. We are also working on utilising the waste gases exiting the WHRS, which are still at around 100 degrees Celsius. To harness this residual heat, we are exploring systems based on the Organic Rankine Cycle, which will allow us to extract additional power from the same process.

With the launch of Star Smart Building Solutions and AAC blocks, how are you positioning yourself in the low-carbon construction materials segment?
We are actively working on low-carbon cement products and are currently evaluating LC3 cement. The introduction of autoclaved aerated concrete (AAC) blocks provided us with an effective entry into the consumer-facing segment of the industry. Since we already share a strong dealer network across products, this segment fits well into our overall strategy.
This move is clearly supporting our transition towards products with lower carbon intensity and aligns with our broader sustainability roadmap.

With a diverse product portfolio, what are the key USPs that enable you to support India’s ongoing infrastructure projects across sectors?
Cement requirements vary depending on application. There is OPC, PPC and PSC cement, and each serves different infrastructure needs. We manufacture blended cements as well, which allows us to supply products according to specific project requirements.
For instance, hydroelectric projects, including those with NHPC, have their own technical norms, which we are able to meet. From individual home builders to road infrastructure, dam projects, and regions with heavy monsoon exposure, where weather-shield cement is required, we are equipped to serve all segments. Our ability to tailor cement solutions across diverse climatic and infrastructure conditions is a key strength.

How are you managing biomass usage, circularity, and waste reduction across
your operations?

The Northeast has been fortunate in terms of biomass availability, particularly bamboo. Earlier, much of this bamboo was supplied to paper plants, but many of those facilities have since shut down. As a result, large quantities of bamboo biomass are now available, which we utilise in our thermal power plants, achieving a Thermal Substitution Rate (TSR) of nearly 60 per cent.
We have also started using bamboo as a fuel in our cement kilns, where the TSR is currently around 10 per cent to 12 per cent and is expected to increase further. From a circularity perspective, we extensively use fly ash, which allows us to reuse a major industrial waste product. Additionally, waste generated from HDPE bags is now being processed through our alternative fuel and raw material (AFR) systems. These initiatives collectively support our circular economy objectives.

As Star Cement expands, what are the key logistical and raw material challenges you face in scaling operations?
Fly ash availability in the Northeast is a constraint, as there are no major thermal power plants in the region. We currently source fly ash from Bihar and West Bengal, which adds significant logistics costs. However, supportive railway policies have helped us manage this challenge effectively.
Beyond the Northeast, we are also expanding into other regions, including the western region, to cater to northern markets. We have secured limestone mines through auctions and are now in the process of identifying and securing other critical raw material resources to support this expansion.

With increasing carbon regulations alongside capacity expansion, how do you balance compliance while sustaining growth?
Compliance and growth go hand in hand for us. On the product side, we are working on LC3 cement and other low-carbon formulations. Within our existing product portfolio, we are optimising operations by increasing the use of green fuels and improving energy efficiency to reduce our carbon footprint.
We are also optimising thermal energy consumption and reducing electrical power usage. Notably, we are the first cement company in the Northeast to deploy EV tippers at scale for limestone transportation from mines to plants. Additionally, we have installed belt conveyors for limestone transfer, which further reduces emissions. All these initiatives together help us achieve regulatory compliance while supporting expansion.

Looking ahead to 2030 and 2050, what are the key innovation and sustainability priorities for Star Cement?
Across the cement industry, carbon capture is emerging as a major focus area, and we are also planning to work actively in this space. In parallel, we see strong potential in green hydrogen and are investing in solar power plants to support this transition.
With the rapid adoption of solar energy, power costs have reduced dramatically – from 10–12 per unit to around2.5 per unit. This reduction will enable the production of green hydrogen at scale. Once available, green hydrogen can be used for electricity generation, to power EV fleets, and even as a fuel in cement kilns.
Burning green hydrogen produces only water and oxygen, eliminating carbon emissions from that part of the process. While process-related CO2 emissions from limestone calcination remain a challenge, carbon capture technologies will help address this. Ultimately, while becoming a carbon-negative industry is challenging, it is a goal we must continue to work towards.

Concrete

Cement Makers’ Margins To Fall Rs 50-75 Per Tonne Amid West Asia Conflict

Crisil Sees Margins Easing Despite Steady Demand

Published

on

By

Shares



Crisil said operating margins of Indian cement manufacturers are expected to decline by Rs 50-75 per tonne (t) this fiscal to Rs 925-950 per t due to higher input costs triggered by the West Asia conflict. The analysis covered 18 cement companies accounting for nearly 90 per cent of India’s domestic cement capacity and noted margins had improved sharply to around Rs 1,000 per t in fiscal 2026.

Crisil noted that the reduction would be driven mainly by higher power and fuel costs, which account for about 30 per cent of total costs, as petcoke and imported coal prices have surged amid geopolitical uncertainties. Freight costs, which account for about a quarter of total costs, are also expected to remain elevated because of higher diesel prices. The impact on profitability is likely to be more pronounced in the first half of the fiscal year before easing commodity prices moderate cost pressures later.

The rating agency said steady domestic demand and strong balance sheets should keep credit profiles stable despite the moderation in margins. Green energy currently accounts for 35-40 per cent of the sector’s total electricity consumption and is expected to partly cushion higher energy costs. Operating cash flows are likely to remain resilient, supported by projected 6-7 per cent growth in cement demand this fiscal.

Crisil highlighted that demand growth will be driven primarily by infrastructure spending, which meets about one-third of sector consumption, and by a nearly 18 per cent higher budgetary allocation for core ministries that should support project execution. Weaker rural housing demand amid pressure on agricultural incomes from a possible below-average monsoon may be offset by improved urban housing demand supported by favourable home-loan rates and a strong pipeline of Pradhan Mantri Awas Yojana-Urban projects. Ongoing capacity additions will keep capital expenditure elevated and may lift net debt to EBITDA to between 1.2 and 1.4 times from around 1.0 time last fiscal, though ratios are expected to remain healthy.

Continue Reading

Concrete

UltraTech Board Approves Rs 50 bn Fundraise Via NCDs

Company to issue half a million debentures for expansion plan

Published

on

By

Shares



UltraTech Cement’s board of directors has approved raising Rs 5,000 crore (Rs 50 bn) through non?convertible debentures issued in rupees.

The finance committee cleared a proposal to issue up to 500,000 fully paid, unsecured, listed, rated, redeemable, rupee?denominated, non?convertible, non?cumulative debentures of Rs 1 lakh each (Rs 0.1 mn each), aggregating to the Rs 5,000 crore programme.

As of June 2026 the firm reported net debt of Rs 15,875 crore (Rs 158.75 bn) and said its capacity expansion projects under execution are backed by capital expenditure of about Rs 17,000 crore (Rs 170 bn) over the next two to two?and?a?half years.

UltraTech spent Rs 9,500 crore (Rs 95 bn) on capital expenditure in financial year 2026 and in April the group crossed 200.1 mn tonnes per annum of domestic grey cement capacity and 205.5 mn tonnes per annum of global capacity.

The chief financial officer indicated the company would take consolidated capacity beyond 242 mn tonnes per annum, with grey cement capacity reaching 212.7 mn tonnes per annum by the end of financial year 2027. He noted the net debt?to?earnings before interest, taxes, depreciation and amortisation ratio stood at 0.87 times as of June 2026 and the company was confident of ending financial year 2027 with the ratio below one time.

In the first quarter of financial year 2026?27 UltraTech’s net profit attributable to owners rose 16.8 per cent year?on?year to Rs 2,599.3 crore (Rs 25.993 bn) and revenue from operations increased 15.9 per cent to Rs 24,648.20 crore (Rs 246.482 bn). The board approval is expected to complement internal cash flows as the company advances its expansion programme.

Continue Reading

Concrete

Lokesh Lays Stone For Rs 31 Billion Cement Unit In Kadapa

Line-2 expansion to make Kadapa a major cement hub

Published

on

By

Shares



Andhra Pradesh Education and IT Minister Nara Lokesh on Wednesday laid the foundation stone for the Line-2 expansion of Dalmia Bharat Cement at Chinnakomerla village in Mylavaram Mandal in Kadapa district. The project carries an investment of Rs 31 billion (bn) and is slated for completion by the third quarter of the financial year 2028. The expansion is intended to boost industrial growth and employment generation across the Rayalaseema region.

Once commissioned, the Kadapa facility will become Dalmia Bharat’s largest integrated cement manufacturing ecosystem in southern India, creating over 1,000 direct and indirect jobs and opening new business avenues for regional micro, small and medium enterprises and transport operators. Lokesh said the expansion signalled growing corporate confidence in the state and reflected the practical ease of doing business that secured repeat investment.

He placed the project within the government’s wider economic targets and recalled the Yuvagalam padayatra commitment to generate two million (mn) jobs within five years, noting that the state would cultivate talent while industry created opportunities. Lokesh highlighted Andhra Pradesh’s competitive pursuit of major manufacturing accounts, mentioning past successes and a personal initiative to engage global investors when persuading them to anchor expansion in the state.

The plant will leverage Kadapa’s abundant limestone reserves to scale production and sustainability. Clinker capacity is planned to rise from two point five million tonnes per annum (mn tpa) to six point one mn tpa, while overall cement output will increase from three point six mn tpa to nine point six mn tpa. The unit is designed to operate on over eighty per cent renewable energy and deploy waste heat recovery, zero liquid discharge, water recycling and advanced AI systems to optimise efficiency. Industries Minister TG Bharat, BC Welfare Minister S. Savitha and Jammalamadugu MLA C. Adinarayana Reddy attended the ceremony.

Continue Reading

Video Thumbnail
â–¶

    SIGN-UP FOR OUR GENERAL NEWSLETTER


    Trending News

    SUBSCRIBE TO THE NEWSLETTER

     

    Don't miss out on valuable insights and opportunities to connect with like minded professionals.

     


      This will close in 0 seconds