UltraTech’s Kukurdih unit runs fully on green energy

The Chhattisgarh plant has met 100 per cent of its electricity needs through green energy since April 2026.

Published

on

Shares
UltraTech Cement’s Kukurdih Cement Works in Chhattisgarh has met 100 per cent of its electricity requirement through green energy every month since April 2026. Commissioned in 2024, the integrated cement manufacturing unit has an installed grey cement capacity of 3.3 million tonnes per annum.
The plant meets its electricity requirement through a combination of renewable power sourcing and Waste Heat Recovery Systems (WHRS). UltraTech said the combination enables the unit to meet its power needs through green energy while maintaining operational reliability.
Since April 2026, nearly a third of UltraTech’s 76 manufacturing units in India have maintained green energy utilisation above 50 per cent of their electricity requirement. Five units, including Kukurdih, have exceeded 95 per cent green energy utilisation.
The company is also progressively deploying Battery Energy Storage Systems (BESS) across its manufacturing network to support greater integration of renewable energy. UltraTech said it has not invested in new captive thermal power capacity at its integrated units, including greenfield projects and brownfield expansions, for more than 10 years.
As of Q1FY27, UltraTech’s captive green energy capacity stood at 1,897 MW, comprising 1,463 MW of renewable capacity from solar, wind and hybrid sources, and 434 MW of WHRS capacity.
Under its RE100 commitment, the company aims to increase the share of green power in its total power mix to 85 per cent by 2030 and 100 per cent by 2050.

Concrete

JSW Cement commissions additional 1 MTPA grinding unit in Rajasthan

The Nagaur expansion takes JSW Cement’s total grinding capacity to 25.10 MTPA.

Published

on

By

Shares
JSW Cement has commissioned an additional 1 million tonne per annum (MTPA) cement grinding unit at its Nagaur Integrated Plant in Rajasthan. The commissioning takes the company’s total cement grinding capacity to 25.10 MTPA. 
JSW Cement’s total clinker manufacturing capacity, including its joint venture JSW Cement FZC, now stands at 9.74 MTPA.
The company began operations in North India in March 2026 with the Nagaur Integrated Plant, comprising a 3.30 MTPA clinkerisation unit and a 2.50 MTPA cement grinding unit. With the latest expansion, the plant’s total grinding capacity has increased to 3.50 MTPA.
The additional capacity will cater to cement demand across Rajasthan, Haryana, Punjab and the National Capital Region (NCR). The expansion has been funded through a combination of equity and long-term debt.
During the quarter ended September 30, 2026, JSW Cement also commissioned an Alternate Fuel Handling System and a Waste Heat Recovery System (WHRS) at the Nagaur plant.
Nilesh Narwekar, CEO, JSW Cement, said the additional grinding capacity was a strategic priority for the company’s expansion in North India. He added that the Alternate Fuel Handling System and WHRS were expected to reduce production costs.

Continue Reading

Concrete

JSW Cement Boards Approve Proposed Shiva Cement Merger

JSW Cement will issue five shares for every 41 Shiva Cement shares

Published

on

By

Shares

The Boards of Directors of JSW Cement and its listed subsidiary Shiva Cement have approved a scheme of arrangement for the amalgamation of Shiva Cement with and into JSW Cement. The proposed merger is intended to create a unified cement platform and generate operational, financial and management synergies.

The consolidation will pool the companies’ financial, managerial, technical, distribution and marketing resources. It will also support backward integration through Shiva Cement’s clinker facility, which is expected to reduce reliance on external procurement and improve supply chain efficiency.

The companies said the transaction would provide greater funding flexibility, reduce financing costs and eliminate inter-company guarantees. It is also expected to simplify the corporate structure by reducing administrative duplication, compliance requirements and consolidation efforts, while aligning the financial statements of both entities.

Under the approved share-exchange ratio, JSW Cement will issue five equity shares with a face value of Rs. 10 each for every 41 equity shares with a face value of Rs. 2 each held in Shiva Cement. The issuance will apply to Shiva Cement shareholders other than JSW Cement and will give the subsidiary’s public shareholders direct ownership in a larger listed company.

The scheme remains subject to approvals from the stock exchanges, the Securities and Exchange Board of India, the National Company Law Tribunal, the Odisha Industrial Infrastructure Development Corporation and other applicable statutory and regulatory authorities. Approval from the companies’ shareholders and creditors may also be required under applicable laws or directions from the tribunal. The transaction is expected to be completed within 12 to 14 months, subject to the timely receipt of these approvals.

Continue Reading

Concrete

JSW Cement commissions additional 1 MTPA grinding unit at Nagaur

Published

on

By

Shares

With this commissioning, JSW Cement’s total cement grinding capacity has increased to 25.10 MTPA, 
Mumbai

JSW Cement, one of India’s leading green cement producers and part of the diversified JSW Group, today announced the successful commissioning of an additional 1.00 MTPA cement grinding unit at Nagaur, Rajasthan. The commissioning marks another significant milestone in the Company’s growth strategy.

With this commissioning, JSW Cement’s total cement grinding capacity has increased to 25.10 MTPA, while its total clinker manufacturing capacity, including clinker capacity at its joint venture, JSW Cement FZC, stands at 9.74 MTPA.

JSW Cement had commenced operations in North India in March 2026 with the Nagaur Integrated Plant, comprising a 3.30 MTPA clinkerisation unit and 2.50 MTPA cement grinding unit. With the commissioning of the additional 1.00 MTPA cement grinding unit, the plant’s total cement grinding capacity has increased to 3.50 MTPA, enhancing the company’s ability to cater to the growing cement demand across Rajasthan, Haryana, Punjab and the National Capital Region (NCR). The expansion has been funded through a strategic mix of equity and long-term debt.

During the quarter ended 30th September 2026, JSW Cement has also commissioned the Alternate Fuel Handling System and the Waste Heat Recovery system (WHRS) at the Nagaur Integrated Plant.

Nilesh Narwekar, CEO, JSW Cement, said: “The commissioning of additional 1.00 MTPA grinding capacity at Nagaur is a key strategic priority for us and will accelerate JSW Cement’s expansion into North India. We look forward to servicing the growing needs of the region and contributing to the economic growth of Rajasthan, Haryana, Punjab and the NCR area. I am delighted to share that the company has commissioned this grinding unit within the expected timeline, showcasing our project execution capabilities. Further, the Alternate Fuel Handling System and the Waste Heat Recovery system (WHRS) are expected to substantially reduce our production costs going forward.”