BMC Cement Concretisation Cuts Pothole Repairs By 70 Per Cent

Project worth Rs 170 billion (Rs 170 bn) aims to concretise 1,900 km by 2027

Published

on

Shares

The Brihanmumbai Municipal Corporation’s cement concretisation project, valued at Rs 170 billion (Rs 170 bn), has reduced expenditure on pothole repairs by 70 per cent over three years. Spending on repairs fell from Rs 2.02 billion in 2023–24 to Rs 1.56 billion in 2024–25 and then to Rs 890 million (Rs 890 mn) in 2025–26. The current tender is expected to be about Rs 440 million, representing a further 50 per cent reduction.

The project is being executed in two phases, with Phase I covering 307 km from October 2023 and Phase II covering 370 km from October 2024. The Indian Institute of Technology is auditing Phase II and will now also audit Phase I to ensure quality and accountability. Mumbai’s total road network spans approximately 2,050 km, of which about 1,200 km had been converted to cement concrete before 2022.

Since 2022 an additional 677 km were taken up for concretisation and nearly 71 per cent of that work, amounting to 481 km, has been completed. Municipal officials indicated that 10–15 per cent of the remaining work is expected to be completed by May 2026 and another 10 per cent by December 2026. The entire programme is scheduled for completion by May 2027, by which time nearly 1,900 km of Mumbai’s roads are expected to be fully concretised.

The administration has also developed a real time dashboard that displays detailed information about contracts, contractors and progress and citizens can access the latest updates online. The dashboard includes contact details for the civic officials and contractors responsible for particular roads to enhance transparency and accountability. The commissioner directed that ongoing works be completed by 31 May ahead of the monsoon to safeguard completion targets and minimise disruption.

Concrete

Nuvoco Marks 10 Years, Targets 35 MMTPA Capacity by FY28

Nuvoco celebrates a decade of growth, targeting 35 MMTPA cement capacity by FY28.

Published

on

By

Shares
Nuvoco Vistas Corporation Limited is celebrating a decade of operations under the theme ‘Dus Saal Bemisaal’, highlighting its expansion in India’s building materials sector. The company has grown from a single cement manufacturing facility into a diversified organisation operating across cement, ready-mix concrete (RMC) and modern building materials.
The company’s journey began in 2014 when its parent, Nirma Group, commissioned a 2 million metric tonnes per annum (MMTPA) greenfield cement plant at Nimbol, Rajasthan. A major milestone followed in October 2016 with the acquisition of Lafarge India, significantly expanding its manufacturing footprint.
Nuvoco strengthened its market presence through the acquisition of Emami Cement, now NU Vista Limited, in 2020, followed by its public listing in 2021. In April 2025, the company added Vadraj Cement to its portfolio, strengthening its presence in western India.
Nuvoco has an operating cement capacity of 27 MMTPA and 14 manufacturing units, including the Kutch and Sachana facilities in Gujarat, which are in advanced stages of completion. It also operates 58 ready-mix concrete plants across India and offers a range of modern building materials.
The company aims to increase its cement capacity to 35 MMTPA by FY2027-28, representing approximately 15-fold growth over the decade.
Reflecting on the milestone, Hiren Patel, Chairman, Nuvoco Vistas Corporation Limited, said, “From our beginnings at Nimbol to the organisation we are today, every milestone has added a new chapter to Nuvoco’s journey and strengthened our belief in building for the long term.”
The company continues to focus on capacity expansion, operational efficiency, innovation and sustainability while strengthening its position in India’s construction materials market.

Continue Reading

Concrete

J&K Government Notifies City Gas Distribution Policy

Policy targets PNG and CNG expansion across all 20 districts

Published

on

By

Shares

Jammu and Kashmir government has notified the City Gas Distribution (CGD) Policy, 2026, following its approval by the Council of Ministers headed by Chief Minister Omar Abdullah. The policy sets out a phased framework for expanding Piped Natural Gas (PNG) and Compressed Natural Gas (CNG) access for households, businesses, industries and the transport sector across the Union Territory.

CGD networks will be expanded in phases across all 20 districts, with the aim of bringing reliable natural gas closer to consumers and supporting a gradual shift from conventional fuels. The government said the policy is designed to improve energy access while creating an investor-friendly and time-bound environment for gas distribution projects.

The policy provides for single-window and time-bound clearances, streamlined procedures for setting up CNG stations and standardised norms for the Right of Way. These measures are intended to reduce procedural delays, simplify project implementation and facilitate investment in natural gas infrastructure.

It also prioritises gas connectivity for major industrial estates, including those in Kathua, Samba and Pulwama. Improved access to natural gas is expected to support industrial activity, enhance energy efficiency and help businesses manage fuel costs, while strengthening their competitiveness and encouraging investment in the clean-energy sector.

The policy is also expected to create opportunities for local employment, apprenticeships and skill development in the construction, operation and maintenance of gas distribution networks and related services. Abdullah described the measure as an important step towards cleaner growth, sustainable development and a modern energy ecosystem in Jammu and Kashmir, saying it would expand reliable energy access and support industry and investment.

Continue Reading

Concrete

JSW Cement Commissions 1 MTPA Grinding Unit at Nagaur

Nagaur unit lifts JSW Cement’s grinding capacity to 25.10 MTPA

Published

on

By

Shares

JSW Cement has commissioned an additional 1 MTPA grinding unit at Nagaur in Rajasthan. MTPA refers to million tonnes per annum. The commissioning has increased the company’s total cement grinding capacity to 25.10 MTPA, while its total clinker manufacturing capacity, including capacity at its joint venture JSW Cement FZC, stands at 9.74 MTPA.

The company began operations in North India in March 2026 with the Nagaur Integrated Plant, which comprised a 3.30 MTPA clinkerisation unit and a 2.50 MTPA cement grinding unit. Following the latest commissioning, the plant’s total cement grinding capacity has risen to 3.50 MTPA.

The expanded facility is expected to strengthen JSW Cement’s ability to serve cement demand across Rajasthan, Haryana, Punjab and the National Capital Region. The project has been funded through a combination of equity and long-term debt, according to the company.

During the quarter ended 30 September 2026, JSW Cement also commissioned an Alternate Fuel Handling System and a Waste Heat Recovery System (WHRS) at the Nagaur Integrated Plant. The company said the additions formed part of its broader effort to improve operational efficiency at the facility.

Nilesh Narwekar, chief executive officer of JSW Cement, said the additional grinding capacity was a strategic priority that would support the company’s expansion in North India. He added that the unit had been commissioned within the expected timeline, reflecting the company’s project execution capabilities, and that the alternate fuel and waste heat recovery systems were expected to substantially reduce production costs going forward.

Continue Reading

Video Thumbnail
▶

    SIGN-UP FOR OUR GENERAL NEWSLETTER

    Trending News

    SUBSCRIBE TO THE NEWSLETTER

     

    Don't miss out on valuable insights and opportunities to connect with like minded professionals.

     


      This will close in 0 seconds