Technology
Barrage of praise!
Published
6 years agoon
By
admin
Built at a cost of Rs 27.32 billion in 24 months, the Annaram Barrage of the KLIS project made use of secant piling in the cut-off foundation for the first time in the world in barrage construction.
It’s a part two of our series on the Kaleshwaram Lift Irrigation Scheme (KLIS), among the world’s largest irrigation projects. In this edition, we showcase the construction of Annaram Barrage, constructed by Afcons Infrastructure. This barrage, combined with the Medigadda and Sundilla barrages constitute the ambitious KLIS. Almost 2,000 million cu ft (tmc) of water per day will be moved upriver through gravity canals from Medigadda barrage to Annaram barrage, from where it will be pumped further back to Sundilla barrage. From there, the water will be diverted to Yellampalli reservoir and then distributed to nearby districts.
"We entered the dam and barrage segment in 2017 with the Annaram barrage project, which is part of this mammoth water preservation project," says K Subramanian, Executive Vice-Chairman, Afcons Infrastructure. "Despite entering a new segment, Afcons has achieved several national benchmarks in concrete pumping in the irrigation and hydropower sector. Kudos to the entire team for bringing in the laurels!"
"Being part of such an amazing and extraordinary engineering marvel is an honour. Annaram was the first of the three barrages to be completed substantially before time," adds Sekhar Das, Project Manager, Annaram Barrage Project, Afcons Infrastructure. "The early delivery makes Afcons’s maiden venture into the irrigation segment extra special. With a capacity of 10.87 tmc, Annaram is the second-largest barrage in the entire KLIS." Annaram Barrage was built at a cost of Rs 27.32 billion in a timeframe of 24 months.
Civil scope
Here’s a look at the civil structure specifications of this barrage:
Dimensions: Length – 1,270 m; Width – 100 m
No. of piers: 72. Dimensions (each): Length – 100 m; Thickness – 4 m; Height – 24 m
Launching apron: Upstream – 71 m; Downstream – 116.4 m.
The scope of work included:
Construction of the barrage for a length of 1,270 m with 66 vents of 15 m along with energy dissipation arrangement and abutments, wing and return/flank wall, etc
All mechanical works related to the barrage radial gates of size 15 m +13 m (12 in total) for under sluice bay and for other bays of size 15 m + 12 m (54 in total)
Road bridge with clear carriageway of 7.50 m
Earth bunds in right and left side to connect the road
Construction of guide bunds of both the sides of barrage
Laying of CC block size of 1,500 x 1,500 x 900 mm with loose stone protection in both streams and along with water side of guide bunds.
Laying of stone pitching in upstream and downstream of barrage and launching apron with stones in water side of guide bunds
Design flood discharge – 65,000 cusecs.
Quantifying right
Materials such as cement,reinforcement steel, aggregate, structural steel and rock boulders have been used in the construction of this barrage.
Highlights include:
1,200,000 cu m of concreting done for the entire project
55,000 mt of reinforcement steel used
80 lakh cu m of earthwork moved
1,500 tonne of cement consumed on average per day
200 mt of steel used on average per day
About 6,000 cu m concrete poured on average per day
More than 1 lakh cu m concreting per month achieved for four consecutive months.
Fully equipped
As this project had a short deadline, Afcons sourced additional equipment and resources from time to time to complete work efficiently. "The initial change of scope and halt of work for over 45 days during floods meant extra resources were the key to getting this barrage completed in just 24 months," shares Das. He goes on to elaborate upon the equipment used in the construction of the barrage: 11 piling rigs; 120 dumper trucks; 60 excavators; 11 boring rigs; seven boom placers; four concrete pumps; 36 transit mixers; seven batching plants; two crusher plants with a capacity of 250 tph; vibro hammer for sheet piling; crawler cranes; pick-n-carry cranes; trailers; and dewatering pumps.
Further, Doka formwork was used in the construction of the piers, where 3-m height lift could be achieved in one go. Rolla deck sheets were used in place of precast panels for the road bridge, saving nearly two months" time for casting of panels, erection and material handling. "Moreover, the project progress was monitored in Primavera and financial status tracked on SAP to keep the project on track in all aspects," says Das. "All periodic reports were made as per formats prepared after discussion with all department heads. We also tracked daily progress through CCTV cameras, site visits and focused WhatsApp groups."
Innovation in execution
Conquering challenges
Effective planning and strong teamwork were definitely factors that helped the team overcome various difficulties during execution. As Das shares, "The approach to the site location was poor initially; so mobilisation was a major challenge. But with the help of the authorities and correct permissions, mobilisation could begin smoothly. For timely land acquisition, we conducted numerous meetings with the villagers and explained the benefits of the barrage and KLIS. It helped a great deal to expedite land acquisition. Local support was critical in timely completion."
Das shares other major challenges involved in constructing this barrage and how the team effectively overcame them:
Approach roads: There were no appropriate roadways to transport materials to the site. Many roads and approach paths were created before the project began to cater to this remote location.
Dewatering: As the barrage location was right on the riverbed, the entire area was filled with water. Dewatering arrangements were made using a multistage well-point dewatering system, which helped speed up the process.
River diversion: To start construction activities, the whole length of the river was diverted using separate bunds. The bunds were constructed upstream for temporary diversion and connected to the total length of the barrage.
Procurement: Procurement was a major challenge. Owing to the remoteness of the site location, even for small materials, one would have to travel at least 300 km. Hence, planning and procurement played a critical role in avoiding delays.
Change of barrage location: At the outset of the project, there was a big change in plan. The location of the barrage was shifted, increasing its length by 151 m. A new geological survey was done at the new site once again. This resulted in extra work of more than 4,000 piles and 20 per cent increase over the estimated quantities of concreting and steel. And while there was increase in work quantity, the survey also threw up another major challenge. The ground at the new site had differentiated strata with layers of sand, soil, gravel and, at times, hard rock. Thus secant piling was used in the cut-off foundation.
Safety first
Afcons established and maintained strong health, safety and environment protocols for this project. Consistent mobilisation of resources (machinery, formwork, manpower) in time was ensured for timely completion. The result: a clean safety record of 8.2 million safe man-hours!
SERAPHINA D’SOUZA
Project details
Location: Annaram, Telangana
Features/specifications: Construction of barrage for a length of 1,270 m with 66 vents of 15 m along with energy dissipation arrangement and abutments, wing and return/flank wall
Total cost: Rs 27.32 billion
Contractor: AFCONS-VIJETA-PES (JV). Afcons Infrastructure. Website:
www.afcons.com; Vijeta. Website: www.vijeta.in; PES. Website: www.peseng.net
Architect/planner: Central Design Organisation (CDO), Government of Telangana.
Cement/concrete: In-house production. Material was procured from many vendors.
You may like
Concrete
Reimagining Logistics: Spatial AI and Digital Twins
Published
19 hours agoon
April 13, 2026By
admin
Digital twins and spatial AI are transforming cement logistics by enabling real-time visibility, predictive decision-making, and smarter multi-modal operations across the supply chain. Dijam Panigrahi highlights how immersive AR/VR training is bridging workforce skill gaps, helping companies build faster, more efficient, and future-ready logistics systems.
As India accelerates infrastructure investment under flagship programs such as PM GatiShakti and the National Infrastructure Pipeline, the pressure on cement manufacturers to deliver reliably, efficiently, and cost-effectively has never been greater. Yet for all the modernisation that has taken place on the production side, the end-to-end logistics chain, from clinker dispatch to the last-mile delivery of bagged cement to construction sites, remains a domain riddled with inefficiencies, opacity and manual decision-making.
The good news is that a new generation of spatial computing technologies is now mature enough to transform this reality. Digital twins, spatial artificial intelligence (AI) and immersive augmented and virtual reality (AR/VR) training platforms are converging to offer cement producers something they have long sought: real-time visibility, autonomous decision-making at the operational edge, and a scalable solution to the persistent skills gap that hampers workforce performance.
Advancing logistics with digital twins
The cement supply chain is uniquely complex. A single integrated plant may manage limestone quarrying, kiln operations, grinding, packing and despatch simultaneously, with finished product flowing through rail, road, and waterway networks to reach hundreds of regional depots and distribution points. Coordinating this network using spreadsheets, siloed ERP data, and phone calls is not merely inefficient; it is a structural liability in a competitive market where delivery reliability is a key differentiator.
Digital twin technology offers a way out. A cement logistics digital twin is a continuously updated, three-dimensional virtual replica of the entire supply chain, from the truck loading bays at the plant to the inventory levels at district depots. By ingesting data from IoT sensors on conveyor belts and packing machines, GPS trackers on road and rail fleets, weighbridge records, and weather feeds, the digital twin provides planners with a single, authoritative picture of where every ton of cement is, in real time.
The value, however, goes well beyond visibility. Because the digital twin mirrors the physical system in dynamic detail, it can run scenario simulations before decisions are executed. If a primary rail corridor is disrupted, logistics managers can model alternative routing options, shifting volumes to road or coastal shipping, and assess the cost and time implications within minutes rather than days. If a packing line at the plant is running below capacity, the twin can automatically recalculate dispatch schedules downstream and alert depot managers to adjust receiving resources accordingly.
For cement companies operating multi-plant networks across geographies as varied as Rajasthan and the North-East, this kind of end-to-end situational awareness is transformative. It collapses information latency from hours to seconds, enables proactive rather than reactive logistics management, and creates the data foundation upon which AI-driven decision-making can be built. Companies that have deployed logistics digital twins in comparable heavy-industry contexts have reported reductions in transit time variability of up to 20 per cent and meaningful decreases in demurrage and detention costs, savings that flow directly to the bottom line.
Smart logistics operations
A digital twin is only as powerful as the intelligence layer that sits on top of it. This is where Spatial AI becomes the critical differentiator for cement logistics.
Traditional logistics management systems are reactive. They record what has happened and flag exceptions after the fact. Spatial AI systems, by contrast, are proactive. They continuously analyse the state of the logistics network as represented in the digital twin, identify emerging bottlenecks before they crystallise into delays, and recommend corrective actions.
At the plant gate, AI-powered visual inspection systems using spatial depth-sensing cameras can assess truck conditions, verify load integrity and confirm seal tamper status in seconds, replacing the manual checks that currently slow throughput. At the depot level, Spatial AI can monitor stock drawdown rates in real time, cross-reference them against pending customer orders and inbound shipment ETAs, and automatically trigger replenishment orders when safety thresholds are approached. In transit, AI systems processing GPS and telematics data can detect anomalous vehicle behaviour, including extended stops, route deviations, speed irregularities and alert fleet managers instantly.
Perhaps most significantly for Indian cement logistics, Spatial AI can optimise the complex multi-modal routing decisions that are central to competitive cost management. Given the variability in road quality, seasonal accessibility, rail rake availability, and regional demand patterns across India’s vast geography, the combinatorial complexity of routing optimisation is beyond human planners working with conventional tools. AI systems can process this complexity continuously and adapt routing recommendations as conditions change, reducing empty running, improving vehicle utilisation and cutting fuel costs.
The agentic dimension of modern AI is particularly relevant here. Agentic AI systems do not merely analyse and recommend; they act. In a cement logistics context, this means an AI system that can, within pre-authorised boundaries, directly communicate revised dispatch instructions to plant teams, update booking confirmations with freight forwarders and reallocate available rail rakes across plant locations, all without waiting for a human to process a recommendation and make a call. For logistics executives, this represents a genuine shift from managing a workforce to setting the rules of engagement and reviewing outcomes. The operational tempo achievable with agentic AI simply cannot be matched by human-in-the-loop systems working at the pace of emails and phone calls.
Bridging the skills gap
Technology investments in digital twins and spatial AI will deliver diminishing returns if the human workforce cannot operate effectively within the new systems they create. This is a challenge that India’s cement industry cannot afford to underestimate. The sector relies on a large, geographically dispersed workforce, including truck drivers, depot managers, despatch supervisors, fleet maintenance technicians, many of whom have been trained on paper-based processes and manual workflows. Retraining this workforce for a digitised, AI-augmented environment is a substantial undertaking, and conventional classroom or on-the-job training methods are poorly suited to the scale and pace required.
Immersive AR and VR training platforms offer a fundamentally different approach. By creating photorealistic, interactive simulations of logistics environments, such as a plant dispatch bay, a depot yard, the interior of a cement truck cab, allow workers to practice complex procedures and decision-making scenarios in a safe, consequence-free virtual environment. A depot manager can work through a simulated rail rake delay scenario, making decisions about customer allocation and communication
without the pressure of real orders being affected. A truck driver can practice the correct procedure for securing a load of bagged cement without the risk of a road incident.
The learning science case for immersive training is compelling. Studies consistently show that experiential, simulation-based learning produces faster skill acquisition and higher retention rates than didactic instruction, with some research indicating retention rates three to four times higher for VR-based training compared to classroom methods. For complex operational procedures where muscle memory and situational awareness matter as much as conceptual knowledge, the advantage of immersive simulation is even more pronounced.
Today’s leading cloud-based spatial computing platforms enable high-fidelity AR and VR training experiences to be delivered on standard mobile devices, removing the hardware barrier that has historically made immersive training impractical for large, distributed workforces. This is particularly relevant for cement companies with depots and logistics operations in tier-two and tier-three locations, where access to specialised training hardware cannot be assumed.
The integration of AR into live operations also creates ongoing learning opportunities beyond formal training programs. As an example, maintenance technicians equipped with AR overlays can receive step-by-step guidance for equipment procedures directly in their field of view, reducing error rates and service times for critical plant and fleet assets.
New strategy, new horizons
India’s cement industry is entering a period of intensifying competition, rising logistics costs, and demanding customers with shrinking tolerance for delivery variability. The companies that will lead over the next decade will be those that treat logistics not as a cost centre to be minimised, but as a strategic capability to be built.
Digital twins, spatial AI and immersive AR/VR training are not distant future technologies, they are deployable today on infrastructure that Indian cement companies already operate. The question is not whether to adopt them, but how quickly to do so and where to begin.
About the author:
Dijam Panigrahi is Co-Founder and COO of GridRaster Inc., a provider of cloud-based spatial computing platforms that power high-quality digital twin and immersive AR/VR experiences on mobile devices for enterprises. GridRaster’s technology is deployed across manufacturing, logistics and infrastructure sectors globally.
Concrete
Beyond Despatch: Building a Strategic Supply Chain Process
Published
19 hours agoon
April 13, 2026By
admin
Dr SB Hegde, Global Cement Industry Leader discusses the imperative need for modern cement plants to recognise packaging and bag traceability as critical components of quality assurance and supply chain management.
In cement manufacturing, considerable attention is given to clinker quality, kiln operation, grinding efficiency and laboratory control. Yet the final stage of the process, cement packaging and despatch, often receives less strategic focus. The cement bag leaving the plant gate represents the final interface between the manufacturer and the customer. Even if clinker chemistry, fineness and strength development are well controlled, weaknesses in packaging, handling, or distribution can affect product quality before it reaches the construction site.
Operational experience from cement plants across different regions shows that packaging efficiency and bag traceability have a significant influence on product reliability, logistics performance and brand credibility. In modern cement plants, packaging systems are no longer viewed merely as despatch equipment. They are increasingly recognised as an important part of quality assurance, supply chain management and customer confidence.
Operational importance of packaging
Cement packaging systems must operate with high speed, accuracy and reliability to support efficient despatch operations. Rotary packers equipped with electronic weighing systems have improved packing accuracy and productivity in many plants.
However, maintaining operational discipline remains essential. Regular calibration of weighing systems, maintenance of packer spouts and proper bag application are important for maintaining consistent bag weights and preventing cement loss.
Operational benchmarks observed in many cement plants are summarised in Table 1.
Plants that improved calibration discipline and equipment maintenance have reported packing loss reductions of about 1 per cent to 1.5 per cent, which represents significant annual savings.
Quality assurance beyond the plant gate
Quality control in cement plants traditionally focuses on laboratory parameters such as fineness, compressive strength and chemical composition. However, the condition of cement when it reaches the customer is equally important.
Cement bags may travel through several stages including plant storage, transport vehicles, dealer warehouses and retail outlets before reaching the construction site. During this journey, cement may be exposed to humidity, rough handling and improper storage conditions.
Table 2 shows common factors that may affect cement quality during distribution.
Studies indicate that cement stored under humid conditions for long periods may experience 10 per cent to 20 per cent reduction in early strength. Therefore, maintaining proper packaging integrity and traceability is essential.
Role of cement bag traceability systems
Traceability systems allow manufacturers to identify when and where cement was produced and despatched. These systems connect packaging operations with production records and logistics data.
When customer complaints occur, traceability enables manufacturers to identify:
- Production batch
- Packing date and time
- Plant location
- Laboratory test results
Several technologies are used to implement bag traceability, as shown in Table 3.
Among these technologies, QR code authentication systems are becoming popular because customers can verify product authenticity through smartphones.
Digital transformation
Digital technologies are transforming cement packaging operations. Modern packing lines now integrate:
- automated rotary packers
- electronic bag counting systems
- robotic palletising systems
- ERP-based despatch management
- digital supply chain monitoring
These technologies improve operational efficiency and transparency across the supply chain.
Such systems help manufacturers track cement movement across the distribution network and respond quickly to quality concerns.
Case Study: Digital Cement Bag Authentication
Several cement manufacturers in Asia and the Middle East have implemented QR code-based bag authentication systems to improve supply chain transparency.
In one integrated cement plant, QR codes were integrated into the rotary packing machine. Each cement bag received a unique digital identity linked to the production database.
The QR code contained information such as:
• plant location
• manufacturing date and time
• product type
• batch number
Customers and dealers could scan the code using a mobile application to verify product authenticity.
After implementation, the company reported:
• reduction in counterfeit bag circulation
• improved despatch data accuracy
• faster resolution of customer complaints
• better visibility of distribution networks
The system was also integrated with the company’s ERP platform, enabling real-time monitoring of production and despatch activities.
Future-Smart Packaging Systems
The future of cement packaging lies in the integration of Industry 4.0 technologies with logistics and supply chain management.
Packaging lines will increasingly become part of connected digital ecosystems linking production, quality control, despatch and market distribution.
Artificial intelligence and data analytics may also help detect abnormalities in bag weight variations, equipment performance and despatch patterns.
Global benchmark indicators
Global benchmarking of cement packaging operations highlights the increasing importance of efficiency, automation and digital traceability in modern cement supply chains. Leading cement plants are now focusing on key performance indicators such as packer availability, bag weight accuracy, packing losses, truck turnaround time and digital traceability coverage. Studies show that overall equipment effectiveness (OEE) in many industrial operations is still around 65 per cent to 70 per cent, whereas world-class plants aim for levels above 85 per cent, indicating significant scope for improvement in operational efficiency.
At the same time, the global cement packaging sector is expanding steadily, supported by growing infrastructure demand and increased emphasis on reliable and moisture-resistant packaging solutions. The cement packaging market is projected to grow steadily in the coming decade as companies adopt automation, smart packaging technologies and integrated logistics systems to improve despatch efficiency and supply chain transparency. In this context, benchmarking against global indicators helps cement plants identify performance gaps and adopt best practices such as automated bagging systems, QR-based traceability, ERP-linked despatch monitoring, and predictive maintenance of packing equipment.
Strategic Recommendations
To fully benefit from packaging and traceability systems, cement manufacturers should consider the following approaches.
• Packaging systems should be treated as an integral part of the manufacturing value chain rather than simply despatching equipment.
• Investments in modern packers, automated loading systems and digital traceability technologies should be encouraged.
• Industry associations may also promote standard traceability practices to reduce counterfeit products and improve transparency in the cement market.
Finally, continuous training of plant personnel in packaging operations and maintenance practices is essential for sustaining operational efficiency.
Conclusion
Cement packaging has evolved from a routine mechanical operation into a strategic component of modern cement manufacturing. Efficient packaging systems ensure that the quality achieved within the plant is preserved during transportation and distribution. Traceability technologies allow manufacturers to track cement movement, investigate complaints and prevent counterfeit products.
As the cement industry moves toward digitalisation and integrated supply chains, packaging and bag traceability will play an increasingly important role in quality assurance, operational efficiency and customer confidence. Ultimately, the cement bag leaving the plant carries not only cement but also the reputation and responsibility of the manufacturer.
References
- Hewlett, P.C., & Liska, M. (2019). Lea’s Chemistry of Cement and Concrete. Butterworth-Heinemann.
- Schneider, M., Romer, M., Tschudin, M., & Bolio, H. (2011). Sustainable cement production. Cement and Concrete Research, 41(7), 642–650.
- International Cement Review. (2023). Advances in cement packaging and logistics systems.
- World Business Council for Sustainable Development (2021). Cement Industry Supply Chain Innovation Report.
- Gartner, E., & Hirao, H. (2015). Reducing CO2 emissions in cement production. Cement and Concrete Research.
- ScienceDirect Industry Studies. (2024). Operational efficiency benchmarks and overall equipment effectiveness in industrial manufacturing systems.
- World Cement Association. (2022). Digital Transformation in Cement Manufacturing and Logistics. London.
- Towards Packaging Research. (2024). Global cement
packaging market trends and technology outlook. Industry Market Analysis Report. - Towards Packaging Research. (2024). Global cement
packaging market trends and technology outlook. Industry Market Analysis Report.
About the author:
Dr SB Hegde is a Professor at Jain College of Engineering, Karnataka, and Visiting Professor at Pennsylvania State University, USA. With 248 publications and 10 patents, he specialises in low-carbon cement, Industry 4.0, and sustainability, consulting with cement companies to support India’s net-zero goals.
Table 1. Key Operational Parameters for Cement Packaging Systems
Parameter Typical Industry Range Recommended Target Operational Significance
Rotary packer capacity 2400–3600 bags/hr 3000–4000 bags/hr Improves despatch efficiency
Bag weight tolerance ±0.5 kg ±0.25 kg Reduces customer complaints
Bag leakage rate 1 per cent to 2 per cent <0.5 per cent Minimises cement loss Packing accuracy 98 per cent to 99 per cent >99.5 per cent Ensure compliance with standards
Truck loading time 30–45 minutes 20–30 minutes Improves logistics efficiency
Table 2. Causes of Cement Quality Degradation During Distribution
Factor Typical Cause Impact on Cement
Moisture exposure Poor storage or rain exposure Lump formation
Long storage duration Slow inventory turnover Loss of early strength
Bag damage Rough handling Cement loss
Improper stacking Excessive loading Bag rupture
Counterfeit bag reuse Refilling of empty bags Brand damage
Table 3. Comparison of Cement Bag Traceability Technologies
Technology Advantages Limitations
Printed batch code Low cost and simple Limited traceability
Barcode Fast scanning Requires equipment
QR code Smartphone verification Requires digital platform
RFID tagging Automated tracking Higher cost
Blockchain systems High transparency Complex implementation
Economy & Market
SEW-EURODRIVE India Opens Drive Technology Centre in Chennai
Published
3 weeks agoon
March 25, 2026By
admin
The new facility strengthens SEW-EURODRIVE India’s manufacturing, assembly and service capabilities
SEW-EURODRIVE India has inaugurated a new Drive Technology Centre (DTC) in Chennai, marking a significant expansion of its manufacturing and service infrastructure in South India. The facility is positioned to enhance the company’s responsiveness and long-term support capabilities for customers across southern and eastern regions of the country.
Built across 12.27 acres, the facility includes a 21,350-square-metre assembly and service setup designed to support future industrial growth, evolving application requirements and capacity expansion. The centre reflects the company’s long-term strategy in India, combining global engineering practices with local manufacturing and service capabilities.
The new facility has been developed in line with green building standards and incorporates sustainable features such as natural daylight utilisation, solar power generation and rainwater harvesting systems. The company has also implemented energy-efficient construction and advanced climate control systems that help reduce shopfloor temperatures by up to 3°C, improving production stability, product quality and working conditions.
A key highlight of the centre is the 15,000-square-metre assembly shop, which features digitisation-ready assembly cells based on a single-piece flow manufacturing concept. The facility also houses SEW-EURODRIVE India’s first semi-automated painting booth, aimed at ensuring uniform surface finish and improving production throughput.
With the commissioning of the Chennai Drive Technology Centre, SEW-EURODRIVE India continues to strengthen its manufacturing footprint and reinforces its long-term commitment to supporting industrial growth and automation development in India.
BMC Cement Concretisation Cuts Pothole Repairs By 70 Per Cent
Shree Cement Approves Rs 1,800 Crore Meghalaya Plant
WCA Welcomes SiloConnect as associate corporate member
TotalEnergies and Holcim Launch Floating Solar Plant in Belgium
Cortec® Corporation applauded for its strong safety performance
BMC Cement Concretisation Cuts Pothole Repairs By 70 Per Cent
Shree Cement Approves Rs 1,800 Crore Meghalaya Plant
WCA Welcomes SiloConnect as associate corporate member
TotalEnergies and Holcim Launch Floating Solar Plant in Belgium

