JSW Cement Forays Into North India With Nagaur Plant

Nagaur plant raises grinding capacity to 24.1 million tonnes per annum

Published

on

Shares

JSW Cement has commenced production at a greenfield integrated cement plant in Nagaur, Rajasthan, marking its first integrated facility in north India and extending the JSW Group’s national presence. The Nagaur unit will serve high-growth markets in Rajasthan, Haryana, Punjab and the National Capital Region. The company presented the commissioning as a key step in its pan-India expansion.

The commencement increases the company’s total cement grinding capacity to 24.1 million tonnes per annum (mn tpa) and brings total clinker manufacturing capacity, including the capacity at its joint venture JSW Cement FZC, to nine point seven four million tonnes per annum (mn tpa). The firm described these additions as strengthening its supply chain and regional reach. The Nagaur site is positioned strategically to reduce logistics for northern markets.

The Nagaur integrated plant comprises a three point three mn tpa clinkerisation unit and a two point five mn tpa cement grinding unit, with an additional one mn tpa grinding unit under construction. The facility was completed within 21 months, demonstrating the company’s project execution capabilities. Management indicated the combined configuration will improve service levels and product availability across target states.

The plant was funded through a mix of equity and long-term debt and the company allocated eight billion (bn) Rs from the fresh issue proceeds of its initial public offering to part-finance the unit. The financing was presented as part of a broader capital plan to support capacity additions and operational enhancements. The firm said the investment aligns with its mid-term growth objectives.

The site is designed with sustainability measures including provision for co-processing alternative fuels, a seven kilometre overland belt conveyor to move limestone from nearby mines and a forthcoming 16 megawatt (MW) Waste Heat Recovery System to recycle process heat and lower emissions. The company reported the expansion brings it closer to its mid-term capacity target of 41.85 mn tpa and to a longer term ambition of 60 mn tpa.

Concrete

30-Day Traffic Diversion In Place For CC Road Works In Madhapur

Diversions in place from May 16 for cement concrete road works

Published

on

By

Shares

The Cyberabad Traffic Police issued a traffic advisory as road works begin for the laying of a cement concrete (CC) road from Jaya Shankar Statue to RRR Restaurant at Parvathnagar in Madhapur limits. The advisory indicated that traffic diversions will be in place for 30 days from May 16 to ensure the smooth flow of vehicles and to minimise congestion on the affected stretch. The measure aims to balance uninterrupted construction activity with the movement needs of commuters.

Traffic moving from Toddy Compound towards Parvathnagar village will be diverted at Parvathnagar junction towards Sunnam Cheruvu and the 100 feet road. Local motorists and public transport operators have been advised to follow the diversionary route as directed by traffic personnel on duty. Alternate routes and signage have been planned to mitigate delays and to manage peak hour congestion.

Police officials said the diversion had been planned to facilitate uninterrupted road works while maintaining traffic movement in the area. Commuters were urged to plan their travel accordingly and to cooperate with traffic staff managing the stretch. Authorities indicated that enforcement of diversions would be active and that violations could attract penalties.

The 30 day schedule is intended to allow contractors to complete the laying and curing phases with minimal interruption to vehicular flow. Residents and businesses in adjacent localities have been advised to factor the diversion into deliveries and travel plans. The traffic police promised continuous monitoring of the works and the operational diversions and emphasised that temporary inconvenience was necessary for longer term improvement of the road network. Traffic personnel will be stationed at key junctions and additional signage and temporary markings will be displayed to guide motorists and pedestrians through the revised alignments while public transport services will follow the diversion where feasible and operators have been asked to adjust timetables to minimise disruption.

Continue Reading

Concrete

HeidelbergCement India Receives Consent For Khandwa Grinding Unit

Consent granted by Madhya Pradesh Pollution Control Board

Published

on

By

Shares

HeidelbergCement India (HeidelbergCement India) has received regulatory consent to establish a cement blending and grinding unit at Village Dongaliya, Tehsil Punasa, District Khandwa in Madhya Pradesh. The consent was granted by the Madhya Pradesh Pollution Control Board under the Water (Prevention & Control of Pollution) Act, 1974 and the Air (Prevention & Control of Pollution) Act, 1981 and is dated 17 May 2026. The company disclosed the development in a filing made under Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015.

The project plan envisages procurement of long term availability of fly ash and the allotment of land on lease for setting up the unit. The proposed facility is described as a blending and grinding installation which will process cementitious materials sourced from nearby operations and suppliers. Company filings state the measures required to secure raw material logistics and statutory compliance before commencing construction.

The addition of a grinding unit in Khandwa is intended to strengthen regional supply and improve logistical efficiency by reducing haulage distances for finished product. The unit is expected to complement existing capacities in central India and to offer flexibility in product mix through blending operations. The reliance on fly ash as a supplementary cementitious material will necessitate long term supply agreements with thermal power producers and coordination with waste utilisation policies.

The disclosure to the regulator and to the stock exchanges follows standard corporate governance practice and aims to keep investors apprised of capital expenditure initiatives. The company indicated that subsequent permits and clearances would be sought in accordance with applicable environmental and land use rules. The project is presented as part of HeidelbergCement India’s broader strategy to optimise capacity distribution and to respond to regional demand dynamics.

Continue Reading

Concrete

PROMECON introduces infrared-based tertiary air measurement system for cement kilns

Published

on

By

Shares

The new solution promisescontinuous, real-time tertiary air flow measurement in cement plant operations.

PROMECON GmbH has launched the McON IR Compact, an infrared-based measuring system designed to deliver continuous, real-time tertiary air flow measurement in cement plant operations. The system addresses the longstanding process control challenge of accurate tertiary air monitoring under extreme kiln conditions. It uses patented infrared time-of-flight measurement technology that operates without calibration or maintenance intervention.

Precise tertiary air measurement is a critical requirement for stable rotary kiln operation. The McON IR Compact is engineered to function reliably at temperatures up to 1,200°C and in the presence of abrasive clinker dust. Its vector-based digital measurement architecture ensures that readings remain unaffected by swirl, dust deposits or drift. Due to these conditions conventional measurement systems in pyroprocess environments are often compromised.

The system is fully non-intrusive and requires no K-factors, recalibration or periodic readjustment, enabling years of uninterrupted operation. This design directly supports plant availability and reduces the maintenance overhead typically associated with process instrumentation in high-temperature zones.

PROMECON has deployed the McON IR Compact at multiple cement facilities, including Warta Cement in Poland. Plant operators report that the system has aided in identifying blockages, optimising purging cycles for gas burners, and supplying accurate flow data for AI-based process optimisation programmes. The practical outcomes include more stable kiln operation, improved process control, and earlier detection of process disturbances.

On the energy side, real-time tertiary air data enables reduction in induced draft fan load and helps flatten process oscillations across the pyroprocess. This translates to lower fuel and energy consumption, fewer unplanned shutdowns, and a measurable reduction in NOx peaks. This directly reflects on the downstream cost implications for plants operating SCR or SNCR systems for emissions compliance.

Continue Reading

Video Thumbnail
â–¶

    SIGN-UP FOR OUR GENERAL NEWSLETTER


    Trending News

    SUBSCRIBE TO THE NEWSLETTER

     

    Don't miss out on valuable insights and opportunities to connect with like minded professionals.

     


      This will close in 0 seconds