Material, Machinery and Manpower!

Published

on

Shares

Here?? the latest connection between the ancient cities of Prayagraj and Varanasi: the six-laning of the Handia to Varanasi section of NH-2 from 712.900-km to 785.544-km in Uttar Pradesh under NHDP Phase 5 on HAM. At Rs.24.47 billion, the completion of this highway has opened doors of accessibility for national and international tourists and devotees. It is also a major part of the Delhi Calcutta Golden Quadrilateral Project-1 and Asian Highway-1. The stretch passes through the major districts of Eastern Uttar Pradesh, i.e. Prayagraj, Bhadohi, Mirzapur and Varanasi.

With this project, the travel time between Prayagraj and Varanasi has been reduced to between one-and-a-half and two hours only, from three to four hours previously.

Initial brief

The NHAI (developer) tender document provided the development features as six-laning of the existing four-lane road in 72.644-km length, with the provision of five new elevated structures, three new grade separators, three minor bridges, 10 new VUPs, and 12 new PUPs, and provided the inventory of the existing four-lane road.

As for manpower, machinery and time, RC Jain, Senior Vice-President – Operations, GR Infraprojects, says. ??e have used a short-term schedule to map out the detailed tasks needed to coordinate day-to-day work in each specific activity for timely completion of the project.??The schedule was developed by the key personnel of the highway and structures team to plan and coordinate their work at the detail level. Further, the schedules used to be revised by the team every one, two or four weeks depending on the complexity of the work. ??his encouraged continuity of work to complete it within its given time schedule of 910 days. Although it was one project, we planned it in five separate packages and mobilised the team accordingly.??/p>

Machinery and materials

A huge fleet of specialised plant and equipment was procured. Ratan Lal Kashyap, Senior Vice-President – Procurement, GR Infraprojects, says, ??amp sites were established at five locations on the project stretch to execute such a humongous task within such a short period. Further, the advanced and newly purchased equipment fleet and machineries have played a vital role, resulting in less maintenance and good efficiency.??/p>

In highway works, this included two concrete batching plants for PQC concrete, an advanced HMP plant and WMM plant along with a number of pavers, graders, dozers, excavators, rollers and dumpers. As for structure works, here?? the list:

  • Four concrete batching plants to produce concrete

  • Three hydraulic rigs for piling works along with cranes of the required capacity

  • Boom placers, transit mixers, shuttering and stagging material and other allied tools and tackles for concreting works

  • Four launching girders operated simultaneously on five elevated structures with 228 spans of PSC precast segmental spine and wings in the superstructure

  • Four high-capacity cranes to launch the flyover girders

  • Development of a casting yard with EOT cranes, batching plant, and automatic cutting and binding machine for reinforcement

  • Advanced quality control lab for testing concrete and various other materials.

Further, in terms of vital construction materials used in highway construction, Kashyap mentions ??G-40 grade of bitumen for enhanced performance; polymer-modified bitumen for BC for enhanced performance; and CTSB in subbase to improve the CBR.??As for structure works, he adds, ??MT steel of Grade FE 550D: 45,000 mt; high-tensile strand (HTS): 6,500 mt; spherical bearings: 932; and modular expansion joints, which were used in the superstructure of the elevated structures.??/p>

How technology took over the construction challenge!

Jain elaborates on the role technology played in overcoming construction-related challenges that arose during the project:

  • RE wall: A huge quantity of earth fill was required for filling at the RE wall locations. For fulfilling the required quantity, the earth was stocked at various locations prior to the rainy season, by which we were able to continuously carry out the work. Further, traffic was also plying on the existing four-lane area; hence, work had to be executed with deployment of machinery with precise safety.

  • Kanwar Yatra during July-August each year and Kumbh Mela in January 2019: These were major deterrents to progress. During this period, the administration would take over control of the site to maintain safe passage for pilgrims travelling between Prayagraj and Varanasi. Progress was drastically hampered during such events. To overcome the situation, additional machinery and manpower were deployed during the day and night.

  • Highway works: Availability of hindrance-free land is the challenge, which constrains execution of work to bits and pieces, involving a lot of shifting of machinery. Thus was overcome by deploying extra machinery and continuous planning.

  • Structure works: An elevated structure having a 23.55-m deck width with a single pier is the most challenging to design and even more difficult to execute in a densely populated area managing the flow of existing highway traffic in available ROW of 26-30 m at most places. To overcome such challenges, a segmental superstructure with spine and wings arrangement was adopted. The spine and wing segments were cast in the casting yard, transported by specially designed trailers, erected by launching girders and, thereafter, prestressed with high-capacity jacks.

Despite the deployment of various techniques and technologies, work was completely suspended at the onset of pandemic. ??ut later,??as Kashyap shares, ??ith the help of the administration, adopting standard operating procedures for preventing COVID-19 among workers and maintaining social distancing and hygienic conditions at camps and workplaces, we could start critical works with 20 per cent of the workforce. We gradually increased this in the next three months as per approval from the local administration.??/p>

Accident-free execution and safe activity

The total number of labour involved in this project has varied month to month; on average, 367,500 man-month labourers were deployed during the construction period. Also, an elaborate safety plan was prepared at the start of work and regular safety audits were conducted by the safety consultant appointed by the client, NHAI. Jain says, ??HAI helped us ensure safety in the work zone for traffic and the workforce. We also had our separate safety team, which ensured safety measures were undertaken before the start of each activity and until the safe completion of the same.??/p>

Impact on economic development

This project will lead to various benefits such as economic development owing to better connectivity between Prayagraj and Varanasi and other areas of Uttar Pradesh; employment opportunities to locals during construction and operation phases; greater road safety; reduction in vehicle operating costs, environmental benefits such as reduction in emissions and noise levels because of smooth traffic flow on the improved road; and improvement in existing cross-drainage structures, minimising water logging along the road.

– SHRIYAL SETHUMADHAVAN

Project Details:

Cost: Rs 24.47 billion

Completion: November 2020

Construction period: 910 days

Total length: 72.644-km

Developer: National Highway Authority of India (NHAI)

Concessionaire: Varanasi Sangam Expressway

EPC contractor: GR Infraprojects

Consultant: Theme Engineering Services, Jaipur

Equipment supplier: Owned equipment by GR Infraprojects

Steel supplier: SAIL, TATA Steel

Road signage and thermoplast production: In-house development

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Concrete

Molecor Renews OCS Europe Certification Across Spanish Plants

Certification reinforces commitment to preventing microplastic pollution

Published

on

By

Shares

Molecor has renewed its OCS Europe certification for another year across all its production facilities in Spain under the Operation Clean Sweep (OCS) voluntary initiative, reaffirming its commitment to sustainability and environmental protection. The renewal underlines the company’s continued focus on preventing the unintentional release of plastic particles during manufacturing, with particular attention to safeguarding marine ecosystems from microplastic pollution.

All Molecor plants in Spain have been compliant with OCS Europe standards for several years, implementing best practices designed to avoid pellet loss and the release of plastic particles during the production of PVC pipes and fittings. The OCS-based management system enables the company to maintain strict operational controls while aligning with evolving regulatory expectations on microplastic prevention.

The renewed certification also positions Molecor ahead of newly published European regulations. The company’s practices are aligned with Regulation (EU) 2025/2365, recently adopted by the European Parliament, which sets out requirements to prevent pellet loss and reduce microplastic pollution across industrial operations.

Extending its sustainability commitment beyond its own operations, Molecor is actively engaging its wider value chain by informing suppliers and customers of its participation in the OCS programme and encouraging responsible microplastic management practices. Through these efforts, the company contributes directly to the United Nations Sustainable Development Goals, particularly SDG 14 ‘Life below water’, reinforcing its role as a responsible industrial manufacturer committed to environmental stewardship and long-term sustainability.

Continue Reading

Concrete

Coforge Launches AI-Led Data Cosmos Analytics Platform

New cloud-native platform targets enterprise data modernisation and GenAI adoption

Published

on

By

Shares

Coforge Limited has recently announced the launch of Coforge Data Cosmos, an AI-enabled, cloud-native data engineering and advanced analytics platform aimed at helping enterprises convert fragmented data environments into intelligent, high-performance data ecosystems. The platform strengthens Coforge’s technology stack by introducing a foundational innovation layer that supports cloud-native, domain-specific solutions built on reusable blueprints, proprietary IP, accelerators, agentic components and industry-aligned capabilities.

Data Cosmos is designed to address persistent enterprise challenges such as data fragmentation, legacy modernisation, high operational costs, limited self-service analytics, lack of unified governance and the complexity of GenAI adoption. The platform is structured around five technology portfolios—Supernova, Nebula, Hypernova, Pulsar and Quasar—covering the full data transformation lifecycle, from legacy-to-cloud migration and governance to cloud-native data platforms, autonomous DataOps and scaled GenAI orchestration.

To accelerate speed-to-value, Coforge has introduced the Data Cosmos Toolkit, comprising over 55 IPs and accelerators and 38 AI agents powered by the Data Cosmos Engine. The platform also enables Galaxy solutions, which combine industry-specific data models with the core technology stack to deliver tailored solutions across sectors including BFS, insurance, travel, transportation and hospitality, healthcare, public sector and retail.

“With Data Cosmos, we are setting a new benchmark for how enterprises convert data complexity into competitive advantage,” said Deepak Manjarekar, Global Head – Data HBU, Coforge. “Our objective is to provide clients with a fast, adaptive and AI-ready data foundation from day one.”

Supported by a strong ecosystem of cloud and technology partners, Data Cosmos operates across multi-cloud and hybrid environments and is already being deployed in large-scale transformation programmes for global clients.

Continue Reading

Concrete

India, Sweden Launch Seven Low-Carbon Steel, Cement Projects

Joint studies to cut industrial emissions under LeadIT

Published

on

By

Shares

India and Sweden have announced seven joint projects aimed at reducing carbon emissions in the steel and cement sectors, with funding support from India’s Department of Science and Technology and the Swedish Energy Agency.

The initiatives, launched under the LeadIT Industry Transition Partnership, bring together major Indian companies including Tata Steel, JK Cement, Ambuja Cements, Jindal Steel and Power, and Prism Johnson, alongside Swedish technology firms such as Cemvision, Kanthal and Swerim. Leading Indian academic institutions, including IIT Bombay, IIT-ISM Dhanbad, IIT Bhubaneswar and IIT Hyderabad, are also participating.

The projects will undertake pre-pilot feasibility studies on a range of low-carbon technologies. These include the use of hydrogen in steel rotary kilns, recycling steel slag for green cement production, and applying artificial intelligence to optimise concrete mix designs. Other studies will explore converting blast furnace carbon dioxide into carbon monoxide for reuse and assessing electric heating solutions for steelmaking.

India’s steel sector currently accounts for about 10–12 per cent of the country’s carbon emissions, while cement contributes nearly 6 per cent. Globally, heavy industry is responsible for roughly one-quarter of greenhouse gas emissions and consumes around one-third of total energy.

The collaboration aims to develop scalable, low-carbon industrial technologies that can support India’s net-zero emissions target by 2070. As part of the programme, Tata Steel and Cemvision will examine methods to convert steel slag into construction materials, creating a circular value chain for industrial byproducts.

Continue Reading

Trending News

SUBSCRIBE TO THE NEWSLETTER

 

Don't miss out on valuable insights and opportunities to connect with like minded professionals.

 


    This will close in 0 seconds