Always Escalate, so as not to Escalate

Published

on

Shares

Languages are such wonderful medium of human expression, because words can have such myriad meanings. There are many words which mean quite different things, taken in context. Unfortunately, here we are not talking about languages, but about project management. ??lways escalate, so as not to escalate??may sound, at first glance, like a meaningless play with words, but it is really not so, in our context. Check out these meanings: Escalate ??To increase in intensity or extent, or Escalate ??To become more serious, or be amplified.

Here, in this column, I mean to say that one must always escalate issues and problems to higher levels at the earliest opportunity, so as to avoid escalation of project cost and time. From my exposure to Project successes and failures, this is a very core issue in project management. Project cost escalation (time and cost are inextricably connected) is a very dreaded word in project management parlance. Not only dreaded, but also hated! But as long as there will be projects, there will remain the possibility of time/cost escalations. Unforeseen things happen, unprecedented situations develop, circumstances spin out of control, and these tend to delay projects and increase costs.

But in almost all cases, there are ways to manage and reduce the impact of these unforeseen things, provided we decide on a solution and act quickly to implement the solution. This is where we fail, because we do not highlight these events, rather we tend to push these below the proverbial carpet, as if they will vanish on their own. Why does this happen? There are two very interesting reasons, one hierarchical, and the other behavioural, and both act in tandem.

No organisation is absolutely flat, and there are levels. This is true for project teams also. In all cases, there will at least be three levels. There are operating people in the field, there is a manager who is responsible for leading and guiding the team, and then there will be so called ??op management?? which could be a CEO, or a Board, or a similar body assigned for review and/or oversight. Now, nascent problems in a project, such as insipient causes for delay, are likely to be known first to the operating level, who have their ??ars glued to the ground??

Think of it, who is most likely to get early signals of possible delays in designing of a building, or manufacturing of a critical component, or construction of a crucial structure, or a key regulatory approval ? who will know first, about a strike in a supplier?? factory, about an agitation at construction site, or about resignation of a key member of sub-contractors??team ? First to know will be the ??oot soldiers??of a project team. Now, this is very powerful information, with far-reaching consequences. However, sadly, officials at this level are not empowered to analyse the impact of such delays, leave alone evolve a solution. The knowledge to do so, and the authority to do so, lies one or two hierarchical levels higher up. And, more often than not, the information is not escalated upwards. Why not? That brings us to the second interesting reason.

This has to do more with psychology than project management per se. We all have an instinctive tendency to hush up bad news because we feel if we pass on these information, it will be taken as our failure. We try to resolve the problem at our level, and in the process waste precious time for intervention. What we do not realise, is that small adversities, when suppressed, may well become huge irreversible setbacks for a project, and that in these matters, speed of escalation and transparency always pay.

The sooner the bad news is known, the better it is, because the corrective actions can be taken immediately. But such rational thinking is often layered by the fear of immediate and short term outcomes of so-called failures. This is a cultural issue, this has to do more with our minds, than with our sense of logic. In larger project organisations, this phenomenon may also be driven by some nuances of internal politics. In any case, the project suffers. To get round this well-known issue, sometimes top management deploys informal and alternative channels to ensure flow of such information directly from field to boardroom. This is a crude workaround, because this kind of strategies undermine the formal organisation structures and dilutes accountability.

– SUMIT BANERJEE

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Concrete

NBCC Wins Rs 550m IOB Office Project In Raipur

PMC Contract Covers Design, Execution And Handover

Published

on

By

Shares

State-owned construction major NBCC India Ltd has secured a new domestic work order worth around Rs 550.2 million from Indian Overseas Bank (IOB) in the normal course of business, according to a regulatory filing.

The project involves planning, designing, execution and handover of IOB’s new Regional Office building at Raipur. The contract has been awarded under NBCC’s project management consultancy (PMC) operations and excludes GST.

NBCC said the order further strengthens its construction and infrastructure portfolio. The company clarified that the contract is not a related party transaction and that neither its promoter nor promoter group has any interest in the awarding entity.

The development has been duly disclosed to the stock exchanges as part of NBCC’s standard compliance requirements.

Continue Reading

Concrete

Nuvoco Q3 EBITDA Jumps As Cement Sales Hit Record

Premium products and cost control lift profitability

Published

on

By

Shares

Nuvoco Vistas Corp. Ltd reported a strong financial performance for the quarter ended 31 December 2025 (Q3 FY26), driven by record cement sales, higher premium product volumes and improved operational efficiencies.

The company achieved its highest-ever third-quarter consolidated cement sales volume of 5 million tonnes, registering growth of 7 per cent year-on-year. Consolidated revenue from operations rose 12 per cent to Rs 27.01 billion during the quarter. EBITDA increased sharply by 50 per cent YoY to Rs 3.86 billion, supported by improved pricing and cost management.

Premium products continued to be a key growth driver, sustaining a historic high contribution of 44 per cent for the second consecutive quarter. The strong momentum reflects rising brand traction for the Nuvoco Concreto and Nuvoco Duraguard ranges, which are increasingly recognised as trusted choices in building materials.

In the ready-mix concrete segment, Nuvoco witnessed healthy demand traction across its Concreto product portfolio. The company launched Concreto Tri Shield, a specialised offering delivering three-layer durability and a 50 per cent increase in structural lifespan. In the modern building materials category, the firm introduced Nuvoco Zero M Unnati App, a digital loyalty platform aimed at improving influencer engagement, transparency and channel growth.

Despite heavy rainfall affecting parts of the quarter, the company maintained improved performance supported by strong premiumisation and operational discipline. Capacity expansion projects in the East, along with ongoing execution at the Vadraj Cement facilities, remain on track. The operationalisation of the clinker unit and grinding capacity, planned in phases starting Q3 FY27, is expected to lift total cement capacity to around 35 million tonnes per annum, reinforcing Nuvoco’s position as India’s fifth-largest cement group.

Commenting on the results, Managing Director Mr Jayakumar Krishnaswamy said Q3 marked strong recovery and momentum despite economic challenges. He highlighted double-digit volume growth, premium-led expansion and a 50 per cent rise in EBITDA. The company also recorded its lowest blended fuel cost in 17 quarters at Rs 1.41 per Mcal. Refurbishment and project execution at the Vadraj Cement Plant are progressing steadily, which, along with strategic capacity additions and cost efficiencies, is expected to strengthen Nuvoco’s long-term competitive advantage.

Continue Reading

Concrete

Cement Industry Backs Co-Processing to Tackle Global Waste

Industry bodies recently urged policy support for cement co-processing as waste solution

Published

on

By

Shares
Leading industry bodies, including the Global Cement and Concrete Association (GCCA), European Composites Industry Association, International Solid Waste Association – Africa, Mission Possible Partnership and the Global Waste-to-Energy Research and Technology Council, have issued a joint statement highlighting the cement industry’s potential role in addressing the growing global challenge of non-recyclable and non-reusable waste. The organisations have called for stronger policy support to unlock the full potential of cement industry co-processing as a safe, effective and sustainable waste management solution.
Co-processing enables both energy recovery and material recycling by using suitable waste to replace fossil fuels in cement kilns, while simultaneously recycling residual ash into the cement itself. This integrated approach delivers a zero-waste solution, reduces landfill dependence and complements conventional recycling by addressing waste streams that cannot be recycled or are contaminated.
Already recognised across regions including Europe, India, Latin America and North America, co-processing operates under strict regulatory and technical frameworks to ensure high standards of safety, emissions control and transparency.
Commenting on the initiative, Thomas Guillot, Chief Executive of the GCCA, said co-processing offers a circular, community-friendly waste solution but requires effective regulatory frameworks and supportive public policy to scale further. He noted that while some cement kilns already substitute over 90 per cent of their fuel with waste, many regions still lack established practices.
The joint statement urges governments and institutions to formally recognise co-processing within waste policy frameworks, support waste collection and pre-treatment, streamline permitting, count recycled material towards national recycling targets, and provide fiscal incentives that reflect environmental benefits. It also calls for stronger public–private partnerships and international knowledge sharing.
With global waste generation estimated at over 11 billion tonnes annually and uncontrolled municipal waste projected to rise sharply by 2050, the signatories believe co-processing represents a practical and scalable response. With appropriate policy backing, it can help divert waste from landfills, reduce fossil fuel use in cement manufacturing and transform waste into a valuable societal resource.    

Continue Reading

Trending News