Connect with us

Concrete

Bartin Cimento Meets Guarantees

Published

on

Shares

In April 2012 Belim Makina completed the installation of a new 3000 t/d kiln line of Bartin Cimento, Turkey. Just one month later during a 48 hours test run at full production all parameters met the guarantees of IKN, who had provided the design of the complete pyro line. In addition, IKN had supplied key components like ID fan, valves, dampers, kiln drive, girth gear, kiln roller stations and the clinker cooler.

Bartin Cimento, a member of Sanko Holding, in 2010 decided to replace its old wet kiln line with state-of- the-art equipment, in order to increase production to 3.000 t/d and reduce energy consumption to the best possible level. The new line was to be placed adjacent to the existing wet kiln, which had to be maintained in operation. Upon stable production of the new line the old kiln was to be dismantled. The customer as well as Belim Makina, who was selected as EPC contractor, knew IKN well from earlier projects in Turkey and accepted its proposed solution for the pyro line as it promised operational reliability in combination with attractive process parameters. In particular, the decision to select IKN as supplier for the complete pyro line was based on process guarantees and mechanical warranties. The final solution comprised a six-stage LUCY type preheater with inline calciner, a conventional 4.2x62m 3-pier kiln and a Pendulum Cooler, which is known for its linear pendulum suspension and horizontal aeration. The calciner and kiln burners were designed for burning a mixture of pet coke and coal. In addition a modern multi-channel burner was required for the use of heavy fuel oil as an alternative during start-up.

Preheater LUCY
LUCY stands for low under pressure cyclones, a development of IKN’s sister company PSP of Czech Republic. The six-stage preheater tower rises 100 meters above ground level and accommodates amply two top cyclones followed by a single string of cyclones. The raw meal enters the preheater at the riser duct between the two top cyclones of 6 m diameter. It passes the cyclone stages C2 to C6 which are 7.5m in diameter. In line with the LUCY concept, the pressure drops and the corresponding degrees of raw meal separation decrease towards the hot gas inlet. The separated raw meal leaves the cone of the respective cyclone through steep and wide raw meal chutes equipped with flaps designed for continuous release of the meal at minimal counter flow of hot gas.

Calciner
Between cyclones C5 and C6 an inline calciner type KKN-AS with low NOx duct is installed. The preheated raw meal enters the calcining channel just above the location where the burner pipes and tertiary air ducts are attached. The lower part of the calciner has a width of 4.35m square. It ensures an efficient mixing of 4.35 m square. It ensures an efficient mixing of meal and fuel with the oxygen-rich tertiary air. The upper part of the calciner has a diameter of 4.1m. It ends in a swirl head followed by a down comer duct to the C6 inlet. Initial mixing in the bottom part and repeated mixing by the swirl head together with specified retention time care for complete fuel combustion at low oxygen surplus. Parallel to the calciner channel a so-called low NOx duct bypasses oxygen-rich tertiary air to the swirl head so that the calciner duct generates CO, which reduces a good portion of nitrogen oxides summarized as NOx. Combustion is completed in the swirl head and the down comer duct of the calciner in an oxygen rich atmosphere. The calciner burner is designed to burn any combination of petcoke or coal.

Kiln
For the production of 3.000 t/d a 62m long and 4.2m shell inner diameter rotary kiln of 3 per cent inclination supported by three piers was selected. Its diameter and volume allows for a reserve in gas volume along with higher production or along with alternate fuel combustion. The 12 radial roller bearings of the kiln supplied by IKN have spherical seats for the bushes, which tolerate bending of the roller shafts and render overheating less likely. They are equipped with an oil and water distribution system for lubrication and cooling. Temperature of oil and thrust ring are monitored by thermocouples. Adjustment boxes on the frame serve for horizontal alignment during operation. For uniform wear of rollers and tires regular axial shifts of the kiln take place. A shift to its upper position is performed by a single hydraulic thrust roller pushing against the tire of bottom pier #1. The kiln is then allowed to travel down by gravity against the thrust roller, which has meanwhile returned to its lower position. The axial shifts are programmed in regular intervals of 5 – 8 hours. Shell temperatures and tire slips are monitored by scanners. Combined with proven shell materials and statics, forced axial kiln shifts and spherical roller bearings provide optimal protection against mechanical kiln failures.

The inlet and outlet seals are air cooled double lamella types, which are easily maintained.

The 55MW thermal capacity multi-channel burner is designed to burn 100 per cent pet coke, 100 per cent coal or a mixture of both. For start-up heavy fuel oil can be used through a separate fuel lance of 5.280 kg/h capacity.

Cooler
The clinker cooler still is the key to the availability and heat efficiency of the pyro line. IKN’s Pendulum Cooler has an aerated surface of 68m2. Availability is assured by a single stage, single hydraulic cylinder drive located at the front end, by Linear Pendulum Supports (LPS) with no lubricated parts within the confined area of the under grate housing, by minimal number of movable parts of the grate surface, by a slow motion roller crusher capable of handling chunks up to a size passing the kiln burner pipe and by a minimal number of 7 fans connected to 7 compartments of the 21m long grate.

Heat efficiency equal to secondary and tertiary air of high and stable temperature is assured by the clinker inlet distribution system KIDS, which with regard to the width of the 3.2m wide grate generates a clinker bed of uniform resistance against the passage of air, and by air distribution to all clinker voids by gentle horizontal COANDA aeration. Named after Henry Coanda of Romania, this effect creates horizontal air jets which are aerating the clinker bed and by keeping adjacent to the grate surface provide an efficient cooling of the grate itself. Safe cooler operation is simply limited to the observance of a pre-set bed pressure drop of the first air compartment, which is controlled by the speed of the hydraulic cylinder. Rather than close automated control, which is provided as well, IKN recommends a fixed grate speed allowing for a pre-set range of bed pressure variation. In most cases – including Bartin Cimento – fixed grate speed comes along with stable kiln operation.

Thanks to the accuracy of the grate alignment and the minimal gaps between moving and fixed parts of the grate, the amount of clinker falling into the under-grate compartments is minimal. The dust could be evacuated during annual shut downs. For comfort and safety, a tube chain conveyor is installed for the extraction of any clinker dust to the clinker discharge. Typically, the tube extractor is operated once a day for a couple of hours.

Installation
Installation of the pyro line took place from September 2011 until April 2012. During this period IKN delegated various experts for inspection of local manufacturing based on its detail drawings and for assistance of Belim Makina for speedy identification and installation of parts. The cooperation with Belim Makina was excellent as the company had earlier experience with IKN equipment.

A highlight and challenging task was the installation and alignment of the kiln girth gear. Using a crane, both halves of the girth gear were wrapped around the kiln and firmly bolted together. Upon measurements of an acceptable run-out, the crew installed the auxiliary drive, adjusted the rollers to their final position, and finalized the gear alignment. auxiliary drive, adjusted the rollers to their final position, and finalized the gear alignment. For cooler grate surface installation, preassembly tools specifically designed for this project were used, which reduced installation time and which made sure that all parts fitted easily into their position. For LPS alignment a laser-light theodolite was used and the reference points marked on the kiln foundation were protocolled for later verification.

Finally, the six-stage preheater at Bartin is the new landmark which represents the latest technology in cement production in the area.

Commissioning/Testing
In May 2012 the new pyroline was started up. Within the two days performance test the same month all relevant technical parameters were measured during operation and a protocol was signed.

Conclusions
The performance of the new pyro line at Bartin Cimento confirms that the combination of IKN Pendulum Coolers with a state-of-the-art pyro system provides excellent results. The combination leverages the IKN cooler performance to an over-all plant performance which in this case benefits Bartin +Cimento. It confirms further that for new pyro lines and refurbishment projects, excellent process know-how, in-house manufacturing capability coupled with thorough design experience provides superior results in terms of time, efficiency, and cost.

by Frank Lichomski, IKN GmbH, Germany

Design Parameters:

Capacity

3.000 tpd

Preheater 6 stage single string type LUCY with inline calciner (KKN-AS)
Calciner burner "for 100% petcoke, 100% coal or mixture of both alternatively 100% HFO"
Kiln 4,2m x 62 m
Kiln Burner "for 100% petcoke, 100% coal or mixture of both alternatively 100% HFO"
specific heat consumption <688 kcal/kg
Cooler "single stage with single hydraulic cylinder drive suspended by Linear Pendulum Support (LPS) aerated surface: 67 m2
installed cooling air: 2,1 Nm3/kg clinker"
cooler discharge clinker temperature 65?C above ambient
Roller crusher Roll crusher with 3 rolls, width: 3m
Exhaust fan 245 Nm3/h

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Concrete

Shree Cement Expands Bangur Concrete Network with Patna Plant

New facility takes the company’s national RMC network to 36 plants

Published

on

By

Shares

Shree Cement has inaugurated a 60 m³/hour ready-mix concrete plant in Patna, Bihar, under its Bangur Concrete brand. The facility takes the company’s ready-mix concrete (RMC) network to 36 plants across India and strengthens its presence in eastern markets.

The plant was inaugurated by Neeraj Akhoury, managing director of Shree Cement, in the presence of senior company officials and other guests. It has been established to serve demand for ready-mix concrete in Patna and neighbouring areas, where infrastructure development, urban expansion and real estate activity are supporting construction growth.

The facility is designed to supply construction projects across Patna and surrounding markets. Its installed capacity of 60 m³/hour will enable Bangur Concrete to serve customers across the region while improving distribution and supply capabilities in eastern India.

The expansion is intended to improve customer service, strengthen the company’s market presence and support development activity in Bihar. The plant incorporates modern batching technology, material handling systems and quality control processes aimed at maintaining consistency in production and improving operational efficiency.

With the addition of the Patna facility, Bangur Concrete now operates 36 RMC plants across India. The business is expanding its footprint in key construction markets to improve customer access to ready-mix concrete, which is increasingly used in infrastructure, commercial and residential projects because it supports controlled production, consistent quality and more efficient material management at construction sites.

The facility will also follow environmentally responsible operating practices, in line with Shree Cement’s focus on sustainable construction solutions. The latest addition adds capacity to the company’s RMC operations and supports its efforts to serve regional construction markets as development activity continues across Bihar.

Continue Reading

Concrete

Ambuja Plans 2.9 MTPA Godda Cement Unit

Proposed unit forms part of Ambuja Cements’ Rs. 145 bn expansion

Published

on

By

Shares

Ambuja Cements has proposed a 2.9 mn tonnes per annum (MTPA) cement grinding unit in Godda district, Jharkhand, as part of a Rs. 145 bn expansion programme. The plan is intended to lift the company’s overall cement capacity to 155 MTPA by financial year 2029-30 (FY30), from its current 113.5 MTPA.

The proposal forms part of the Adani Group company’s wider manufacturing expansion across eastern and northeastern India, according to a company statement issued on Monday. The Godda unit would add grinding capacity to Ambuja Cements’ network and is intended to help serve demand in Jharkhand and neighbouring states.

Locating production closer to these markets is expected to reduce transportation costs and delivery times, while the project could support employment in plant operations, maintenance, logistics and administration. The company also linked the facility to indirect activity in transportation, contract services, construction, warehousing and local supply chains.

The expansion plan includes a 2.9 MTPA grinding unit each in Assam and Bihar, as well as additional clinker capacity in Assam. Together, the projects are designed to distribute manufacturing capacity more widely and improve the connection between clinker production and grinding operations, Ambuja Cements’ cement-business chief executive Vinod Bahety said.

Clinker is the intermediate material produced before it is ground and blended to make cement, making the Godda proposal part of a broader materials and logistics network rather than an isolated facility. Ambuja Cements has not provided a commissioning timeline, a Godda-specific investment breakdown, land details or a detailed employment estimate in the supplied announcement.

The project’s impact will depend on implementation of the plant, associated transport links and local supply chains. The announcement sets out the capacity objective but does not specify the project’s construction schedule or operational start date.

Continue Reading

Concrete

Dhanekula Institute Signs MoU with Adani Cement

Agreement to expand internships, industrial visits and practical learning

Published

on

By

Shares

The Department of Civil Engineering at Dhanekula Institute of Engineering & Technology, Ganguru, organised an industrial interaction programme under the Adani FutureX Programme on Thursday. The programme focused on strengthening engagement between the institute and the cement industry while giving students greater exposure to professional practices.

Yedukondalu, technical head for Andhra Pradesh and Telangana at Adani Cement, delivered a technical lecture on concrete as a man-made material. The session covered the importance of concrete in construction, its properties and applications, and its significance in modern infrastructure development.

The lecture also addressed the role of quality cement and suitable concrete technology in supporting durable and sustainable construction. The discussion connected classroom learning with the technical considerations involved in infrastructure projects and construction practices.

A key part of the programme was the signing of a memorandum of understanding (MoU) between the Department of Civil Engineering and Adani Cement under the Adani FutureX Partnership Agreement. The agreement is intended to strengthen industry-academia collaboration through opportunities for student internships and industrial visits.

The initiative is expected to provide students with practical exposure, improve their understanding of industrial practices and help bridge the gap between theoretical knowledge and real-world applications. Dhanekula Institute Chairman Dhanekula Ravindranath Tagore, Secretary Dhanekula Venkata Bhavani Prasad and Director DKRK Ravi Prasad supported the initiative, with the institute leadership highlighting the importance of industry-institution interaction in enhancing students’ technical employability.

Continue Reading

Video Thumbnail
â–¶

    SIGN-UP FOR OUR GENERAL NEWSLETTER

    Trending News

    SUBSCRIBE TO THE NEWSLETTER

     

    Don't miss out on valuable insights and opportunities to connect with like minded professionals.

     


      This will close in 0 seconds