Bangladesh’s Chhatak Cement Co Ltd has announced plans to modernise its facility and convert it from wet process to dry process. The company has begun to prepare a development project proposal, with a schedule to implement the upgrades by 2021.
According to company officials, Chhatak Cement has incurred an accumulated loss of over BDT3.63bn (US$43.25m) between FY13-14 and FY17-18, mainly due to its outdated machinery resulting in loss of production capacity. The plant is currently operating at 70,000 tonnes per annum (tpa).
However, the new project is anticipated to boost production capacity and increase annual company profit to around BDT1bn. The modernisation is expected to be financed by a BDT8.9bn investment from the government, with BDT5.34bn as a loan with a payback period of seven years and the rest as equity, according to The Financial Express.
Image Source: Google