J K Cement on Monday said it has resumed production at its 3-million tonne per annum Karnataka facility which was temporarily stopped following caving in of the silo roof. ?Production of Clinker and cement has resumed with operation of the Kiln by making an alternate arrangement using two RBC belts for feeding the clinker directly to the Cement Mill,? The company has said that though the output has been halted cement available with its depots had served the market. While halting production it has said that alternate arrangement for operation of Kiln is being initiated which is expected to normalise the clinker and cement production within 15 days from this unit but restoration of clinker silo is expected to take six months time. The actual loss is being assessed by the company.